摘要:工程手工算量计算繁琐,不易统计和修改,因而算量软件陆续出现。然而算量软件操作必须严格按软件要求操作,对软件公司的指导依赖性很强;另外算量软件采用三维建模来实现计算的,较手工算量多出了繁琐的建模工作。

随着我国工程量清单规范的实施,编制自己的企业定额已日趋必要,企业定额的数据主要来源于历史数据的记录和统计分析。Excel具有强大的数据处理能力,本人通过实际经验总结,制作了工程算量模板。本模板在计算工程量及投标报价上具有以下优点:数据清晰性强,数据追溯性强,调价直观性强。

当然模板在算量时智能化及精度无法与三维软件相比,追求清晰性、实用性、高效性的最佳组合。

关键词:Excel应用,Excel-CAD表格互导、工程算量软件,工程量清单规范,企业定额。

Abstract: It is troublesome to calculating by hand, and its not convenient to make statistics or modify. As a result, calculating soft wares have appeared one by one. However, we have to follow their instructions in order to use the soft wares, and we depend a lot on the guidance of software companies; besides, when using soft wares to calculate, we have to do a lot of modeling work, which is the core of their calculating system.

As the specification for bill of quantities carries out, it becomes necessary to make the enterprise ration, the data of which come from the records and statistics of historical data. Excel has powerful data-dealing ability. After a lot of practice, I make a template for construction budget. It has the following advantages on construction budget and tender offer:  The data is clear. It can easily tell the sources. It is easy to read for adjusting prices.

Though the template can not beat the software on intelligence and precision, I am seeking for a perfect combination of clearnesspracticability and efficiency.

Key: Application of Excel, data-in and data-out between tables of Excel and CAD, software for construction budget, specification for bill of quantities, the enterprise ration.


 

一、与传统手工算量及软件算量的比较

1、与传统手工算量的比较

传统手工算量的缺点

Excel模板算量的处理方案

汇总统计烦

Excel数据处理,布局清晰

数据提取烦

相关设计参数查询烦

影响工程量的细部节点计算入公式模板,不影响投标报价的节点忽略

关联构件扣减难,支座判断难

按主次构件拆分建筑物,支座项目计入次构件

异型构件列式计算难

编辑公式模板,直接调用

变更错误准确调整难

Excel数据处理,布局清晰

核量对量难

 

2、与算量软件的比较

算量软件优点

算量软件缺点

Excel模板算量

三维建模形象直观

由于三维模型无法用于施工,二维图纸作为施工依据是必须的,也是完全可行的。算量软件仅仅为了算量就使用三维建模并不值得。

在二维环境下就地解决,并配合打印图纸保持清晰性。

人为错误易于检查,不会出现大的计算错误

软件界面尚不成熟,操作者进对软件的迁就性较大

核心技术就23项,熟悉了就能操作,先进性主要表现在布局的科学合理性。

 

工程整体性差,图形、钢筋、安装分别计量,导出清单后才能套价

工程整体性好,从算量到出价一气合成。

对于软件合与分的说明:话说世间万物,合久必分,分久必合,然而合者易分,分者却难合。建立数学模型如下:

本模板    A=K(X+Y+Z)=KX+KY+KZ  

算量软件  A=K1X+K2Y+K3Z=K1(X+K2/K1Y+ K3/K1Z)

(A-工程量  K-本模板  K1K2K3算量软件图形、钢筋、安装等软件

虽然软件在K2/K1方面作了一些工作,即图形和钢筋文件互导,但使用范围有限。

 

二、核心途径

1、有限多维数据的清晰化处理

1)多级目录是多维数据的最基本方式,工程量清单就是采用得这种方式,将复杂的工程按清单项目目录综合成一体。

2)表格的行与列可组成矩阵,属二维数据,较目录形式的一维数据更加清晰。

3)数据的排序功能。假设有一个三维数据(ABC),我们将AB合并,数据更改为二维数据(A&B,C),但A&B本身仍是一维数据,现对A&B进行排序,顺序依次为(A1&B1,A1&B2,A2&B1,A2&B2),即目录化的二维数据。

2工程量的公式合并

根据工程量清单规范,工程量的计量单位有件数、长度、面积、体积、重量,因此工程量计算公式并不多(不超过50个),我们需对不同的项目编辑公式,并将其合并为一个公式。

我们知道,使用IF公式,只可以对7个以下公式进行合并,且公式太过复杂不易检查。

这里我使用了宏自定义函数,操作如下:工具vb编辑器弹出vb编辑器窗口

依次点击菜单插入模块1,在窗口编辑如下内容:

Function gcl(biaoji, L, B, H, n, d, one, two, three, four, five, six)

    If biaoji = "构件" Then

        gcl = 0

ElseIf biaoji = "件数" Then

        gcl = n

     

    ElseIf biaoji = "长度" Then

        gcl = L / 1000 * n

。。。。。。

 

    Else

        gcl = ""

    End If

End Function

这里自定义的公式为gcl(),输入的参数包括L, B, H, n, d基本参数及one, two, three, four, five, six自定义参数,对于不同的biaoji,可定义不同的自定义参数。

因为不同的公式需要不同的参数,这里我使用语言描述(语言描述的应用)并使用Excel的公式识别语言并设置条件格式,提示需要输入哪些参数及自定义参数代表的名称,我们仍然通过自定义函数:

Function sm(biaoji)

    If biaoji = "构件" Then

        sm = "构件名称构件数量LBH"

    ElseIf biaoji = "长度" Then

        sm = "Ln"

    。。。。。

    ElseIf biaoji = "上部筋" Then

       sm = "Lnd1柱宽2跨数(边跨输2,中间跨输100)"

。。。。。

    Else

        sm = ""

    End If

End Function

然后根据sm的内容进行条件格式的设置,需要输入的参数显示黄色,不需要的显示灰色,(一个构件的计算项目中有很多参数是一致的,为了避免多次输入,我们将公用参数作为构件参数,项目参数引用构件参数,显示蓝色,不一致时自行输入,显示黄色),效果如下图:

3、数据汇总

输入参数后,模板自动对项目进行编号,并自动在汇总表中引用该项目名称,并统计每个项目的工程量。同时在横向对分类进行编号并引用,并对每个项目的工程量按分类进行拆分,(表格的应用)如下图:

三、亮点介绍

由于ExcelCAD在表格和图形方面功能非常强大,二者配合可以大大提高工作效率。以下对其优势作说明如下:

1、流程简便,对量简单,只需核对输入数据是否与图纸一致模板中30多个公式的正确性。(流程图见下页)

2参数输入快捷通道:

1)导入装修做法表,将其复制到Excel模板的相应位置,模板会自动计算装修做法,只需输入房间名称及尺寸、数量(对于矩形房间输入长宽高,异形房间输入面积、周长和净高)(图形的应用)。

2)导入门窗表,我们在导入的门窗表后添加三列(扣墙体、扣两面装饰),这样模板在计算门窗时会自动扣除门窗洞口的相应项目。避免了在计算装饰面积时去重复计算扣除门窗的面积。

3)砼梁构件的参数根据平法标注统一输入,由模板进行计算自动填写参数。减少了人为输入的错误。

3、借用CAD图统计总长度。我们经常需要统计长度(比如计算室外水管的长度)。然而CAD中并没有对直线长度的汇总功能,只能在文本文件中显示列表。这样通过Excel强大的计算功能,就可以计算出总长度。将结果复制回CAD图适中当位置,打印出附图作为算量资料的一部分(图形的应用)。

 


工程列项

输入参数

工程量计算

钢筋含量分析

构件参数检查

工程量

输出

单价输入

参考总价

主要指标

统计长度数量

检查符合性

 

大部分构件已有模块,特殊构件自定义

 

 

 

配合CAD进行统计,打印图形进行备注

 

 

 

尽量按图纸格式输入参数,如梁平法标注

 

 

大部分公式已编辑好,遇有未编辑的公式,可自行输入,模板会以不同颜色区分自定义公式,或添加到自定义函数中

 

 

辅助工作,检查人为错误及钢筋指标

 

 

 

自动计算,按给定清单进行项目分类

 

 

 

模板中逐步添加初步价格

 

 

 

对占总价比重大的项目进行详细询价,保证总价的误差精度要求

 

 

计算主要指标,可参考类似工程的各项指标进行快速估价

 

 


4、指标输出功能,相似的工程具有相近的指标。所以在算量后进行指标统计是非常必要的,一方面可以检查错误,二方面可以加深宏观认识、快速进行工程概算。人材机图表,直观显示人材机总价,通过人工总价,可以估算出项目需要多少劳动力,进行技术标的设计。以下两项指标图均自动自成,非常方便。

四、模板在企业定额定价与工程量清单衔接中的应用

1、挖土方:工程量清单规范因为考虑不同投标单位的施工水平不一致,为了保持公平公正,规定土方工程量是按不放坡考虑的。但实际施工过程中确实是要放坡的,企业成本也是与放坡土方量成正比的。模板中是这样实现的:先按留工作面,放坡进行计算工程量,并计价,记录总价。对计算表格进行筛选挖土方,将工作面和放坡系数清除,得出不放坡工程量,填入清单。

2、不同构件的砼量:工程量清单规范对梁、柱、板及墙等构件是分开计量的,但作为施工单位,在将工作分配给班组长时,一般并不会按不同类型使用不同的价格。所以在模板算量时,对不同构件的同等级砼是统一定价的,以减少项目数量,加强数据清晰性。

3、化粪池等小型构件:工程量清单规范为了简化清单,对小型构件进行了整合。如果施工单位按构件进行定价,而图集中做法繁多,企业定额的计价项目将非常多。在本模板中,我们对小型构件进行拆分至清单项目进行计价,计价后再将构件价格输入到工程量清单中。

4、门窗:工程量清单规范为了将门窗五金综合到门窗综合价中,对门窗是按樘进行计量的,给施工单位的计价带来了很大的麻烦。在本模板中,门窗作为项目按面积进行计价,门五金按数量计价,汇总成构件将其构件单价填入工程量清单中。

五、总结

本模板在算量时具有一定的智能性,较手工算量效率大大提高;而利用excel的强大数据处理功能和CAD的图形处理功能,实现了项目预算的高效性、整体性,对于宏观调整非常有效。能满足投标报价的精度要求。同时,本模板能较好地结合企业信息,配合企业定额的编制。

当然,本模板在项目计算的全面性、模板布局、操作技巧方面还有提高的空间,希望能为土建预算人员带来方便,并一起完善模板,共同提高。

 

QQ:20439765 QQ群:56336868

Email:yaker_77@126.com

附:VBA编程文件

 


 

自定义工程量计算的数组公式

Option Base 1

Function gcl(biaoji, xm, L, B, H, n, d, one, two, three, four, five, six)

        If xm = "钢筋一级" Then

          dengji = "A"

        ElseIf xm = "钢筋二级" Then

          dengji = "B"

        ElseIf xm = "钢筋三级" Then

          dengji = "C"

        Else

          dengji = "?"

        End If

    Dim temp(6)

    Select Case biaoji

    Case Is = "构件"

        temp(1) = ""

        temp(2) = ""

        temp(3) = ""

        temp(4) = ""

        temp(5) = ""

        temp(6) = ""

    Case Is = "件数"

        temp(1) = ""

        temp(2) = ""

        temp(3) = ""

        temp(4) = " n=" & n

        temp(5) = n

        temp(6) = "U"

    Case Is = "长度"

        temp(1) = ""

        temp(2) = ""

        temp(3) = ""

        temp(4) = " n=" & n

        temp(5) = L / 1000 * n

        temp(6) = "M"

    Case Is = "面积"

        temp(1) = ""

        temp(2) = ""

        temp(3) = ""

        temp(4) = " n=" & n & " S=" & one & " 加长=" & two & " 加宽=" & three

        If one = 0 Then

        temp(5) = (L + two) / 1000 * (B + three) / 1000 * n

        Else

        temp(5) = one * n

        End If

        temp(6) = "M2"

    Case Is = "柱模板"

        temp(1) = ""

        temp(2) = ""

        temp(3) = ""

        temp(4) = " n=" & n & " 测周长=" & one

        If one = 0 Then

        temp(5) = (L + B) * 2 / 1000 * H / 1000 * n

        Else

        temp(5) = one / 1000 * H / 1000 * n

        End If

        temp(6) = "M2"

    Case Is = "梁模板"

        temp(1) = ""

        temp(2) = ""

        temp(3) = ""

        temp(4) = " 板厚=" & one

        temp(5) = L / 1000 * (B + 2 * (H - one)) / 1000

        temp(6) = "M2"

    Case Is = "体积"

        temp(1) = ""

        temp(2) = ""

        temp(3) = ""

        temp(4) = " n=" & n & " S=" & one

          If one = 0 Then

            temp(5) = L / 1000 * B / 1000 * H / 1000 * n

          Else

            temp(5) = one * H / 1000 * n

          End If

        temp(6) = "M3"

    Case Is = "圆柱体积"

        temp(1) = ""

        temp(2) = ""

        temp(3) = ""

        temp(4) = " n=" & n & " D=" & one & " t=" & two

          If two = 0 Then

            temp(5) = 3.1416 * one * one / 4000 * H / 1000 * n

          Else

            temp(5) = 3.1416 * (one * one - (one - two) * (one - two)) / 4000 * H / 1000 * n

          End If

        temp(6) = "M3"

    Case Is = "梁砼"

        temp(1) = ""

        temp(2) = ""

        temp(3) = ""

        temp(4) = " 板厚=" & one

        temp(5) = L / 1000 * B / 1000 * (H - one) / 1000

        temp(6) = "M3"

    Case Is = "梯形"

        temp(1) = ""

        temp(2) = ""

        temp(3) = ""

        temp(4) = " 上宽=" & one & " 下宽=" & two

        temp(5) = L / 1000 * (one + two) / 2000 * H / 1000

        temp(6) = "M3"

    Case Is = "梯形放坡"

        temp(1) = ""

        temp(2) = ""

        temp(3) = ""

        temp(4) = " 工作面=" & one & " 坡度=" & two

        temp(5) = L / 1000 * (B + one * 2 + two * H) / 1000 * H / 1000

        temp(6) = "M3"

    Case Is = "锥形"

           Sone = L / 1000 * B / 1000

        temp(1) = " S1=" & Sone

           Stwo = one / 1000 * two / 1000

        temp(2) = " S2=" & Stwo

        temp(3) = ""

        temp(4) = " 上长=" & one & " 下宽=" & two

        temp(5) = (Sone + Stwo + Sqr(Sone * Stwo)) * H / 3000

        temp(6) = "M3"

    Case Is = "放坡锥形"

          Sone = (L + one * 2) / 1000 * (B + one * 2) / 1000

        temp(1) = " S1=" & Sone

          Stwo = (L + one * 2 + two * H * 2) / 1000 * (B + one * 2 + two * H * 2) / 1000

        temp(2) = " S2=" & Stwo

        temp(3) = ""

        temp(4) = " 工作面=" & one & " 坡度=" & two

        temp(5) = (Sone + Stwo + Sqr(Sone * Stwo)) * H / 3000

        temp(6) = "M3"

    Case Is = "面积锥形"

        temp(1) = ""

        temp(2) = ""

        temp(3) = ""

        temp(4) = " S1=" & one & " S2=" & two

        temp(5) = (one + two + Sqr(one * two)) * H / 3000

        temp(6) = "M3"

    Case Is = "柱钢筋"

           gjn = n

       temp(1) = gjn

          gjl = H + one + two

       temp(2) = gjl

          If three = 0 Then

           djl = 0

          Else

            djl = 40 * d * (three + 1)

          End If

       temp(3) = djl

        temp(4) = biaoji & n & dengji & d

        temp(5) = gjn * (gjl + djl) / 1000 * Round(3.1416 * d * d * 7.85 / 4000, 3) / 1000

       temp(6) = "T"

    Case Is = "柱箍筋"

       temp(6) = "T"

           gjn = ((H - five) / two + five / one) * n

       temp(1) = gjn

          gjl = L * three + B * four

       temp(2) = gjl

          djl = 40 * d * Int(gjl / 9000)

       temp(3) = djl

        temp(4) = biaoji & n & dengji & d & "@" & one & "/" & two & "(" & three & "*" & four & ")" & " 加密长" & five

        temp(5) = gjn * (gjl + djl) / 1000 * Round(3.1416 * d * d * 7.85 / 4000, 3) / 1000

    Case Is = "上部筋"

           gjn = n

       temp(1) = gjn

          If two = 100 Then

          gjl = L + one

          Else

          gjl = Int(L + one * (two + 1) / two + 15 * d * 2 / two)

          End If

       temp(2) = gjl

          djl = Int(40 * 0.8 * d * gjl / 9000)

       temp(3) = djl

        temp(4) = biaoji & n & dengji & d

        temp(5) = gjn * (gjl + djl) / 1000 * Round(3.1416 * d * d * 7.85 / 4000, 3) / 1000

       temp(6) = "T"

    Case Is = "加强筋"

           gjn = n

       temp(1) = gjn

          If two = 100 Then

          gjl = L + one

          Else

          gjl = Int(L * 2 / 3 + one * (two + 1) / two + 15 * d * 2 / two)

          End If

       temp(2) = gjl

          djl = Int(40 * 0.8 * d * gjl / 9000)

       temp(3) = djl

        temp(4) = biaoji & n & dengji & d

        temp(5) = gjn * (gjl + djl) / 1000 * Round(3.1416 * d * d * 7.85 / 4000, 3) / 1000

       temp(6) = "T"

     Case Is = "下部筋"

           gjn = n

       temp(1) = gjn

          If two = 100 Then

          gjl = L + one

          Else

          gjl = Int(L + one * (two + 1) / two + 15 * d * 2 / two)

          End If

       temp(2) = gjl

          djl = Int(28 * 0.8 * d * gjl / 9000)

       temp(3) = djl

        temp(4) = biaoji & n & dengji & d

        temp(5) = gjn * (gjl + djl) / 1000 * Round(3.1416 * d * d * 7.85 / 4000, 3) / 1000

       temp(6) = "T"

    Case Is = "梁箍筋"

            If H > 250 Then

               jml = H * 4

            Else

               jml = 1000

            End If

           gjn = ((L - jml) / two + jml / one) * n

       temp(1) = gjn

          gjl = H * three + B * 2

       temp(2) = gjl

          djl = 40 * d * Int(gjl / 9000)

       temp(3) = djl

        temp(4) = biaoji & n & dengji & d & "@" & one & "/" & two & "(" & three & ")"

        temp(5) = gjn * (gjl + djl) / 1000 * Round(3.1416 * d * d * 7.85 / 4000, 3) / 1000

       temp(6) = "T"

    Case Is = "零星箍筋"

           gjn = n

       temp(1) = gjn

          gjl = H * one + B * two

       temp(2) = gjl

          djl = 40 * d * Int(gjl / 9000)

       temp(3) = djl

        temp(4) = biaoji & n & dengji & d & "(" & one & "*" & two & ")"

        temp(5) = gjn * (gjl + djl) / 1000 * Round(3.1416 * d * d * 7.85 / 4000, 3) / 1000

       temp(6) = "T"

    Case Is = "拉筋"

        gjn = L / one * n

       temp(1) = gjn

          gjl = B

       temp(2) = gjl

         djl = 0

       temp(3) = ""

        temp(4) = biaoji & n & dengji & d

        temp(5) = gjn * (gjl + djl) / 1000 * Round(3.1416 * d * d * 7.85 / 4000, 3) / 1000

       temp(6) = "T"

    Case Is = "长分布筋"

           gjn = (B + three - 2 * four) / one * n

       temp(1) = gjn

          gjl = L + two - 2 * four

       temp(2) = gjl

          djl = 40 * d * Int(gjl / 9000)

       temp(3) = djl

        temp(4) = biaoji & n & dengji & d & "@" & one

        temp(5) = gjn * (gjl + djl) / 1000 * Round(3.1416 * d * d * 7.85 / 4000, 3) / 1000

       temp(6) = "T"

     Case Is = "宽分布筋"

           gjn = (L + two - 2 * four) / one * n

       temp(1) = gjn

          gjl = B + three - 2 * four

       temp(2) = gjl

          djl = 40 * d * Int(gjl / 9000)

       temp(3) = djl

        temp(4) = biaoji & n & dengji & d & "@" & one

        temp(5) = gjn * (gjl + djl) / 1000 * Round(3.1416 * d * d * 7.85 / 4000, 3) / 1000

       temp(6) = "T"

    Case Is = "双层加固"

           gjn = Int(L / one * B / two)

       temp(1) = gjn

          gjl = H + 6.5 * d

       temp(2) = gjl

       temp(3) = ""

        temp(4) = biaoji & n & dengji & d & "@" & one & "*" & two

        temp(5) = gjn * (gjl + djl) / 1000 * Round(3.1416 * d * d * 7.85 / 4000, 3) / 1000

       temp(6) = "T"

    Case Is = "零星钢筋"

       temp(6) = "T"

           gjn = n

       temp(1) = gjn

          gjl = L

       temp(2) = gjl

          djl = 40 * d * Int(gjl / 9000)

       temp(3) = djl

        temp(4) = biaoji & n & dengji & d

        temp(5) = gjn * (gjl + djl) / 1000 * Round(3.1416 * d * d * 7.85 / 4000, 3) / 1000

    Case Is = "钢板"

        temp(1) = ""

        temp(2) = ""

        temp(3) = ""

        temp(4) = " n=" & n & " =" & one

        temp(5) = L / 1000 * B / 1000 * one / 1000 * n * 7.85

        temp(6) = "T"

    Case Is = "花纹板"

        temp(1) = ""

        temp(2) = ""

        temp(3) = ""

        temp(4) = " n=" & n & " 规格 " & one

        temp(5) = L / 1000 * B / 1000 * two * n

        temp(6) = "T"

    Case Is = "型材"

        temp(1) = ""

        temp(2) = ""

        temp(3) = ""

        temp(4) = " n=" & n & " 规格" & one & "单重" & two

        temp(5) = n * L / 1000 * two / 1000

        temp(6) = "T"

   Case Else

        temp(1) = ""

        temp(2) = ""

        temp(3) = ""

        temp(4) = ""

        temp(5) = ""

        temp(6) = ""

    End Select

    gcl = temp

End Function

 

 

自定义参数说明公式

Function sm(biaoji)

    If biaoji = "构件" Then

        sm = "构件名称构件数量LBH"

    ElseIf biaoji = "件数" Then

        sm = "n"

    ElseIf biaoji = "长度" Then

        sm = "Ln"

    ElseIf biaoji = "面积" Then

        sm = "LBn1测量面积2加长3加宽"

    ElseIf biaoji = "柱模板" Then

        sm = "LBHn1测量周长"

    ElseIf biaoji = "梁模板" Then

        sm = "LBH1板厚"

    ElseIf biaoji = "体积" Then

        sm = "LBHn1测量面积"

    ElseIf biaoji = "圆柱体积" Then

        sm = "Hn1直径2壁厚"

    ElseIf biaoji = "梁砼" Then

        sm = "LBH1板厚"

    ElseIf biaoji = "梯形" Then

        sm = "LH1上宽2下宽"

    ElseIf biaoji = "梯形放坡" Then

        sm = "LBH1工作面2坡度"

    ElseIf biaoji = "锥形" Then

        sm = "LBH1上长2上宽"

    ElseIf biaoji = "放坡锥形" Then

        sm = "LBH1工作面2坡度"

     ElseIf biaoji = "面积锥形" Then

        sm = "H1下部面积2上部面积"

     ElseIf biaoji = "柱钢筋" Then

        sm = "Hnd1下加长2上加长3层数"

    ElseIf biaoji = "柱箍筋" Then

        sm = "LBHnd12间距34筋数5加密长"

    ElseIf biaoji = "上部筋" Then

       sm = "Lnd1柱宽2跨数(边跨输2,中间跨输100)"

    ElseIf biaoji = "加强筋" Then

        sm = "Ln(平均值)d1柱宽2跨数"

    ElseIf biaoji = "下部筋" Then

        sm = "Lnd1柱宽2跨数"

    ElseIf biaoji = "梁箍筋" Then

        sm = "LBHnd12间距3立筋数"

    ElseIf biaoji = "零星箍筋" Then

        sm = "BHnd12筋数"

    ElseIf biaoji = "拉筋" Then

        sm = "LBnd1间距"

    ElseIf biaoji = "长分布筋" Then

        sm = "LBnd1间距2钢筋加长3布置加宽4保护"

     ElseIf biaoji = "宽分布筋" Then

        sm = "LBnd1间距2布置加长3钢筋加宽4保护"

    ElseIf biaoji = "双层加固" Then

        sm = "LBHd12间距"

    ElseIf biaoji = "零星钢筋" Then

        sm = "Lnd"

    ElseIf biaoji = "钢板" Then

        sm = "LBn1板厚"

    ElseIf biaoji = "花纹板" Then

        sm = "LBn1板厚2单位重量"

    ElseIf biaoji = "型材" Then

        sm = "Ln1规格2单位重量"

    Else

        sm = ""

    End If

End Function

 

    本站是提供个人知识管理的网络存储空间,所有内容均由用户发布,不代表本站观点。请注意甄别内容中的联系方式、诱导购买等信息,谨防诈骗。如发现有害或侵权内容,请点击一键举报。
    转藏 分享 献花(0

    0条评论

    发表

    请遵守用户 评论公约

    类似文章 更多