SH∕T 3503-2017 石油化工建设工程项目交工技术文件规定 (非正式版)20190524
2022-10-21 | 阅:  转:  |  分享 
  




ICS

P 72

备案号:





中华人民共和国石油化工行业标准



SH/T 3503— 2017

代替 SH/T 3503— 2007











石油化工建设工程项目交工技术文件规定



Specification on handover technical documentation for petrochemical

construction projects







































2017-07-07发布 2018-01-01实施



中华人民共和国工业和信息化部 发布



SH/T 3503— 2017

I

目 次

前言 ···························································································································· Ⅳ

1 范围 ························································································································· 1

2 规范性引用文件 ·········································································································· 1

3 术语和定义 ················································································································ 1

4 总则 ························································································································· 2

5 交工技术文件的内容与份数 ··························································································· 3

6 交工技术文件的编制、整理与交付 ·················································································· 3

6.1 交工技术文件的编制 ····························································································· 3

6.2 交工技术文件的整理 ····························································································· 4

6.3 交工技术文件的交付 ····························································································· 6

附录 A(规范性附录)交工技术文件通用表 ··········································································· 7

附录 B(规范性附录)交工技术文件土建工程用表 ································································ 54

附录 C(规范性附录)交工技术文件设备安装工程用表 ·························································· 68

附录 D(规范性附录)交工技术文件管道安装工程用表 ························································ 140

附录 E(规范性附录)交 工技术文件电气安装工程用表 ························································· 164

附录 F(规范性附录)交工技术文件仪表安装工程用表 ························································· 176

附录 G(规范性附录)交工技术文件压力容器现场组焊安装工程用表 ······································ 188

附录 H(规范性附录)交工技术文件起重机械安装工程用表 ·················································· 202

Appendix A( Normative Appendix) Handover Technical Documentation— General ·························· 217

Appendix B( Normative Appendix) Handover Technical Documentation— Civil ···························· 264

Appendix C( Normative Appendix) Handover Technical Documentation— Equipment Installation ······ 278

Appendix D( Normative Appendix) Handover Technical Documentation— Piping Installation ·············· 351

Appendix E( Normative Appendix) Handover Technical Documentation— Electrical Installation ·········· 376

Appendix F( Normative Appendix) Handover Technical Documentation— Instrumentation Installation ··· 388

Appendix G( Normative Appendix) Handover Technical Documentation— Pressure Vessel Site

Assembly Welding and Installation ······································································ 400

Appendix H( Normative Appendix) Handover Technical Documentation— Lifting Machinery Installation · 414

本标准用词说明 ············································································································ 429

附:条文说明 ··············································································································· 430

SH/T 3503— 2017

II

Contents

Foreword ······················································································································ Ⅲ

1 Scope ························································································································ 1

2 Normative reference documents ························································································· 1

3 Terms and definitions ····································································································· 1

4 General ······················································································································ 2

5 Contents and copies of handovertechnicaldocumentation ··························································· 3

6 Preparation, sorting out and delivery of handover technicaldocumentation ······································ 3

6.1 Preparation of handover technicaldocumentation ······························································ 3

6.2 Sorting out of handover technicaldocumentation ······························································ 4

6.3 Delivery of handover technicaldocumentation ································································· 6

Appendix A( Normative Appendix) Handover Technical Documentation— General (Chinese) ················· 7

Appendix B( Normative Appendix) Handover Technical Documentation— Civil (Chinese)··················· 54

Appendix C( Normative Appendix) Handover Technical Documentation— Equipment Installation

(Chinese) ······································································································ 68

Appendix D( Normative Appendix) Handover Technical Documentation— Piping Installation (Chinese) · 140

Appendix E( Normative Appendix) Handover Technical Documentation— Electrical Installation

(Chinese) ····································································································· 164

Appendix F( Normative Appendix) Handover Technical Documentation— Instrumentation Installation

(Chinese) ····································································································· 176

Appendix G( Normative Appendix) Handover Technical Documentation— Pressure Vessel Site Assembly

Welding and Installation (Chinese) ······································································· 188

Appendix H( Normative Appendix) Handover Technical Documentation— Lifting Machinery Installation

(Chinese) ····································································································· 202

Appendix A( Normative Appendix) Handover Technical Documentation— General (English) ·············· 217

Appendix B( Normative Appendix) Handover Technical Documentation— Civil (English) ·················· 264

Appendix C( Normative Appendix) Handover Technical Documentation— Equipment Installation

(English) ······································································································ 278

Appendix D( Normative Appendix) Handover Technical Documentation— Piping Installation (English) ·· 351

Appendix E( Normative Appendix) Handover Technical Documentation— Electrical Installation

(English) ······································································································ 376



SH/T 3503— 2017

III

Appendix F( Normative Appendix) Handover Technical Documentation— Instrumentation Installation

(English) ······································································································ 388

Appendix G( Normative Appendix) Handover Technical Documentation— Pressure Vessel Site Assembly

Welding and Installation (English) ······································································· 400

Appendix H( Normative Appendix) Handover Technical Documentation— Lifting Machinery

Installation (English) ······················································································· 414

Explanation of wording in this specification ············································································ 429

Attachment: Explanation of provisions ·················································································· 431



SH/T 3503— 2017

IV

前 言

根据中华人民共和国工业和信息化部《 2013年第四批行业标准制修订计划》(工信厅科 [2013]217号)

的要求,标准编制组经广泛调查研究,认真总结实践经验,参考有关国 内标准和国外先进标准,并在广

泛征求意见的基础上,修订本标准。

本标准共分 6章和 8个附录, 8个附录均为规范性附录。

本标准的主要技术内容是:总则、交工技术文件的内容与份数、交工技术文件的编制、整理与交付。

本标准是在《石油化工建设工程项目交工技术文件规定》 SH/T 3503— 2007的基础上修订而成,修

订的主要技术内容是:

—— 补充了竣工图、项目管理单位的术语 ,以及项目管理单位对交工技术文件的管理责任;

—— 调整了设备、材料质量证明文件和竣工图的编制责任与要求;

—— 对原交工技术文件的表格进行了修改和必要的增 补;

—— 附录 B补充了石油化工常用设备基础、构筑物、防水等工程交工技术文件表格;

—— 附录 C增加了往复式压缩机组装等交工技术文件表格;

—— 附录 E补充了变电所受电条件确认、盘柜基础型钢质量验收记录、电缆安装质量验收记录等交

工技术文件表格;

—— 附录 F补充了部分仪表检、试验交工技术文件表格;

—— 附录 G压力容器现场组焊安装工程用表;

—— 附录 H起重机械安装用表;

—— 调整了交工技术文件分类组卷的要求。

本标准由中国石油化工集团公司负责管理,由中国石油化工集团公司施工技术中心站负责日常管

理,由石油化工工程质量监 督总站燕山石化分站负责具体技术内容的解释。执行过程中如有意见和建议,

请寄送日常管理单位和主编单位。

本标准日常管理单位:中国石油化工集团公司施工技术中心站

通讯地址:天津市滨海新区(大港)世纪大道 180号

邮政编码: 300270

电话: 022-63863843

传真: 022-25990156

本标准主编单位:石油化工工程质量监督总站燕山石化分站 /中石化第四建设有限公司

通讯地址:北京市房山区燕山岗东路 14号 /天津市滨海新区(大港)世纪大道 180号

邮政编码: 102500/300270

本标准参编单位:中国石 油化工股份有限公司齐鲁分公司

石油化工工程质量监督总站镇海石化分站

中国石化工程建设有限公司

北京燕华工程建设有限公司

主要起草人:吉章红 毕瑞凤 孙秀环 葛春玉 唐秀丽 胡联伟 关慰清 李文轩 沈 丽

张虎伟 袁庆水 陈国荣 宁 波 王 雁 黄志新 吴 红 刘洪伟 李 江

万寿香 崔建操 赵 阳 徐春然

SH/T 3503— 2017

V

主要审查人:周 国 周家祥 杨振刚 吴忠宪 迟玉东 汤卫国 杨新和 赵 勇 陈 雷

王勋涛 朱 杰 叶晓文 胡海波 李红星 李昀鹏 杨宝祥 安 蓓 王一帆

孙立祥 徐奇生 张永斌 曹 巍 周 龑 陆忠儒 杨金良 韩建华 张奉忠

张桂红 马超超 陈昌才 张之平 孙志芬 张 波 孙明达 吴 红 黄志新

刘洪伟 于明玮 白铁英 刘小平 李兆太 刘金生 杨 峻

本标准于 1986年首次发布, 1993年第 1次修订, 2001年第 2次修订, 2007年第 3次修订,本次为第 4

次修订。





SH/T 3503— 2017

1

石油化工建设工程项目交工技术文件规定

1 范围

本标准明确了石油化工建设工程项目从工程开工到 工程交工验收过程中形成的设计、采购、施工及

检测等交工技术文件的要求。

本标准适用于石油化工新建、扩建和改建工程项目的交工技术文件编制、整理和交付。

2 规范性引用文件

下列文件对于本标准的应用是必不可少的。凡是注日期的引用文件,仅注日期的版本适用于本标准。

凡是不注日期的引用文件,其最新版本(包括所有的修改单)适用于本标准。

GB/T 10609.3 技术制图复制图的折叠方法

GB/T 11822 科学技术档案案卷构成的一般要求

GB/T 14689 技术制图图纸幅面和格式

GB 50300 建筑工 程施工质量验收统一标准

GB/T 50328 建设工程文件归档规范

DA/T 28 国家重大建设项目文件归档要求与档案整理规范

SH/T 3508 石油化工安装工程施工质量验收统一 标准

SH/T 3903 石油化工建设工程 项目 监理规范

SH/T 3904 石油化工建设工程项目竣工验收规范

3 术语和定义

GB/T 50328、 SH/T 3903 和 SH/T 3904 确立的及以下术语和定义适用于本 标准 。

3.1

交工技术文件 handover technical documentation

工程总 承包单位或设计、采购、施工、检测等承包单位在建设工程项目实施过程中形成并在工程交

工时移交建设单位的工程实现过程、使用功能符合要求的证据及竣工图等技术文件的统称,是建设工程

文件归档的组成部分。

3.2

质量证明文件原件 original quality certificate

加盖生产厂检验专用章或质量证明专用章的产品质量证明文件或由供应商、采购单位在产品质量证

明文件复印件上加盖确认印章的延续性质量证明文件。

3.3

项目管理单位 project management contractor

按照合同约定和 建设单位授权,代表建设单位为工程项目实施各阶段提供工程项目管理服 务 并 承担

相应管理责任的工程项目管理企业或经建设单位批准成立的项目管理机构(包括 PM、 PMC、 IPMT 等

SH/T 3503— 2017

2

项目管理模式下的项目管理 机构 )。

3.4

竣工图 as-built drawings

真实反映建设工程项目施工结果的图样。

4 总则

4.1 建设单位应按本标准在合同或相关文件中明确对交工技术文件的要求和管理责任,在项目开工前

根据项目特征或具体要求明确交工技术文件编制方案。下列参建单位应对工程实施过程中形成的交工技

术文件进行管理:

a)工 程总承包单位;

b)设计、采购、施工、检测等承包单位;

c)项目管理单位、工程监理单位。

注: 本标准不包括工程监理单位根据监理规范自身形成的文件。

4.2 建设工程项目实行工程总承包或设计、采购、施工的一项或多项承包的,工程总承包单位与分承

包单位签订合同时,应明确对交工技术文件的 编制 要求和管理责任。

4.3 建设工程项目中有关铁路、公路、港口码头、电信、电站 、 35kV以上送变电工程和油气田、长输

管道等工程的交工技术文件内容应按国家相关标准规定执行。

4.4 锅炉、压力容器、压力管道、起重机械、电梯等特 种设备安装工程的交工技术文件内容除执行本

标准外,还应执行特种设备安全技术监察机构的规定。

4.5 土建工程中的钢结构、房屋建筑工程及其附属建筑电气、暖通、建筑智能化等交工技术文件内容

应执行建设工程项目所在地建设行政主管部门的规定,设备基础、构筑物等工程交工技术文件内容执行

本标准 。

4.6 交工技术文件应真实、完整,案卷整理、编目、签证应规范。

4.7 交工技术文件中的设备和材料质量证明文件应有一份质量证明文件原件。采购单位在发放工程材

料时应核对并记录材料的名称、规格型号、数量和领用单位,为领用单位提供 质量证明文件原件。

4.8采购单位和施工单位工程师应对材料质量证明文件原件进行确认并签字。

4.9 建设工程项目交工技术文件中 /英文用表格式应符合本标准的要求,有关标准规范和本标准同时列

有同类表格时,应优先采用本标准 附录 A~ 附录 H 列入 的表格:

—— 附录 A(规范性附录)交工技术文件通用表 /Appendix A( Normative Appendix) Handover

Technical Documentation—General;

——附录 B(规范性附录)交工技术文件土建工程用表 /Appendix B( Normative Appendix)

HandoverTechnical Documentation—Civil;

——附录 C(规范性附录)交工技术文件设备安装工程用表 /Appendix C( Normative Appendix)

Handover Technical Documentation—Equipment Installation;

——附录 D(规范性附录)交工技术文件管道安装工程用表 /Appendix D( Normative Appendix)

Handover Technical Documentation—Piping Installation;

——附录 E(规范性附录)交工技术文件电气安装工程用表 /Appendix E( Normative Appendix)

Handover Technical Documentation—Electrical Installation;

——附录 F(规范性附录)交工技术文件仪表安装工程用表 /Appendix F( Normative Appendix)

Handover Technical Documentation—Instrumentation Installation;

——附录 G(规范性附录)交工技术文件压力容器现场组焊安装工程用表 /Appendix G( Normative

SH/T 3503— 2017

3

Appendix) Handover Technical Documentation—Pressure Vessel Site Assembly Welding and

Installation;

——附录 H(规范性附录)交工技术文件起重机械安装工程用表 /Appendix H( Normative Appendix)

Handover Technical Documentation—Lifting Machinery Installation。

5 交工技术文件的内容与份数

5.1 交工技术文件的内容应包括:

a) 施工图会审记录;

b) 工程施工开工、工程中间交接、工程交工验收等工程文件;

c) 土建、安装工程施工质量检验、检测、质量验收文件;特种设备安全监察机构和特种设备安装

监督检验机构等监督检验文件;

d) 设备、材料质量证明文件及材料的检测、复验报告;

e) 工程联络单、设计变更文件;

f) 竣工图。

5.2 交工技术文件份数可为两份,正本交建设单位,副本由编制单位保存。正本应为原件,副本可为

复制件;以电子版形式提供时,电 子文件格式应符合国家及行业有关标准。

5.3 无损检测单位应出具无损检测报告,交被检测工程的施工单位。管道工程无损检测报告可用无损

检测结果汇总表代替。

6 交工技术文件的编制、整理与交付

6.1 交工技术文件的编制

6.1.1 工程项目开工前,建设单位应按 GB 50300 和 SH/T 3508 组织划定工程项目的单项工程、单位

(子单位)工程,作为参建单位编制交工技术文件的指导性文件。

6.1.2 工程项目开工前,参建单位根据项目的具体情况及建设单位的交工技术文件编制方案,制定交

工技术文件编制细则。

6.1.3 建设工程项目的参建单位应与工程进度同步形成、积累、编制交工技术文件,并应符合下列规

定:

a)施工单位负责施工部分交工技术文件的编制,包括各专业的工程材料质量证明文件、工程检测

报告、工程设计变更一览表、工程联络单一览表的汇编;

b)设计单位负责竣工图的编制和移交;

c)采购单位负责锅炉、起重机械、塔、容器、反应器、冷换设备、动设备、成套设备等具有特定

设备位号的设备出厂资料的编制和移交;

d)检测单位负责无损检测报告和其他检测报告的编制,交由被检测工程的施工单位汇入相关工程

卷;

e)实行工程总承包的 项目,工程总承包单位负责组织各承包单位交工技术文件的编制和移交;

f) 监理单位负责 交工技术文件的真实性、完整性的审核;

g)建设单位或项目管理单位负责交工技术文件的审查,建设单位负责交工技术文件的接收。

6.1.4 交工技术文件除产品技术文件和设备质量证明文件、材料质量证明文件外,宜用计算机编制,

责任人员应用符合档案要求的书写工具签字确认,且应做到字迹清晰、签章完整。

6.1.5 检测报告和管道无损检测结果汇总表应符合下列规定:

SH/T 3503— 2017

4

a)设备无损检测报告应按设备位号编制,应有焊缝编号 (射线检测报告还应有片位 号 )、焊工代号、

返修及扩探等可追溯性标识,并附检测位置示意图;

b)管道无损检测结果汇总表应按管道编号编制,应有焊缝编号、固定焊焊接位置标记、焊工代号、

返修及扩探等可追溯性标识;

c)材料、配件的检测报告按材料、配件的种类编制,应有 质量证明文件编号、炉 /批号、检件编号

等可追溯性标识。

6.1.6 施工单位应按管道编号确认管道焊接接头实际无损检测比例,在管道轴测图或焊缝布置图上标

识焊缝编号、施焊焊工代号、固定口位置 、检测焊缝位置及无损检测种类、返修 标识,也可在轴测图空

白处集中 标识或附表 。

6.1.7 纸质 版交工技术文件的文字资料用纸规格应 为 A4。附录 A~ 附录 H 所列表格中表头左侧栏内

的字号为标准黑体五号字;表头中部表格名称为宋体加粗三号字;其他各栏文字为标准宋体五号字;录

入文字为五号楷体;页边距应按下列规定设置:

a)竖排版的文件左边距 25mm、上边距 20mm、右边距 20mm、下边距 20mm、 装订线位置在左侧;

b)横排版的文件左边距 20mm、上边距 25mm、右边距 20mm、下边距 20mm、 装订线位置 在 上部 。

6.1.8 竣工图页边距应执行 GB/T 14689 的规定。

6.1.9建设工程项目竣工图编制应符合 下列规定:

a)竣工图绘制依据为原施工图、已 经实施完成的 设计变更通知单、工程联络单等工程变更信息;

b) 施工图有变更的 应绘制竣工图,签署栏中的版次号标 注 为 J版(以竣工图“竣”字汉语拼音第

一个字母大写为标识 ; 部 分 施工图无变更的, 终版 施 工 图作为竣工图;目 录 标 注为 J版;

c)按图施工整 套设计文件 无变更的,终 版 施 工图 作为竣工图, 目录 标 注 J版 做为竣工图 ,并 加以

说明 。

6.1.10 电子版交工技术文件应符合下列规定:

a)交工技术文件电子版应与其对应的纸质版一致,其归档格式应符合 GB/T 50328 要求;

b)交工技 术文件电子版应以纸质版卷内目录中的序号为编制单元,一个序号的文件为一个电子文

件,一卷为一个文件夹,文件夹名称与对应纸质版案卷“卷名”相同。

6.2 交工技术文件的整理

6.2.1 交工技术文件的整理包括分类组卷、编目、装订等环节,各卷内均应有 案卷封面、卷内目录、

交工技术文件 封面 和交工技术文件说明,并加入备考 表。

6.2.2 交工技术文件由整理单位按单项工程编制。施工文件、材料质量证明文件、设备出厂资料、竣

工图应按专业分类。

6.2.3 施工文件可设单项工程综合卷,并按土建工程、设备安装工程、管道安装 工程、电气安装工程、

仪表安装工程等专业分类组卷。各专业文件较多时,可按单位 (单元 )工程等组卷。

6.2.4 锅炉、压力容器、压力管道、起重机械、电梯等特种设备安装工程的交工技术文件应单独组卷。

6.2.5 消防、环保、职业卫生、电信等设施安装交工技术文件宜单独组卷。

6.2.6 下列文件可归入施工综合卷:

a)工程施工开工报告;

b)工程中间交接证书;

c)重大质量事故处理报告(发生时);

d)单位工程质量验收记录(分部工程和分项工程质量验收记录编入专业工程综合卷) ;

e)其他文件。

6.2.7 工 程交工验收证书、交工技术文件移交证书按 SH/T 3904 规定签署,单独办理。

6.2.8 土建工程、设备安装工程、管道安装工程、电气安装工程、仪表安装工程等专业施工文件卷可

SH/T 3503— 2017

5

根据文件内容组成一卷或多卷。组成多卷时第一卷宜为专业综合卷,下列文件可归入专业综合卷:

a)工程施工开工报告;

b)焊工、无损检测人员登记表;

c)工程设计变更一览表及设计变更单;

d)工程联络单一览表及工程联络单;

e)工程中间交接证书;

f)其他文件。

6.2.9 土建工程施工卷除执行本标准 6.2.8条 专业综合卷规定外,尚应符合下 列规定:

a)施工文件宜按单位工程、分部工程、分项工程顺序组卷 。

b)卷内文件应按施工物资材料、施工记录、施工试验记录、过程质量验收记录等文件组卷。

6.2.10 设备安装工程施工卷除执行本标准 6.2.8条专业 综合卷规定外,尚应符合下列规定:

a)按单位工程、分部工程、分项工程顺序组卷;动、静设备分别组卷 ;

b)整体到货的设备,卷内文件应按设备类别、位号、施工工序顺序组卷。每台(组)设备按设备

开箱、基础复测、设备安装、垫铁隐蔽、检测、试验、内件安装、隐蔽验收、单机试车(动设

备)等工序形成的记录、报告的顺序 汇集成卷。同一设备的附属设备、附属设施、脱脂、防腐、

保温、保冷及隔热耐磨衬里等施工文件宜一并编入主设备施工卷 ;

c)现场组焊的锅炉、工业炉、压力容器、储罐等设备施工文件应单台组卷 ;

d)大型机组现场组装的施工文件及成套设备现场安装的施工文件应单独组卷 ;

e)设备的保温、保冷、脱脂、防腐及隔热耐磨衬等施工工程由专项施工单位施工的,可由专项施

工单位按单位工程、分部工程、分项工程顺序将施工文件单独整理成卷,提交建设单位或汇总

到设备安装工程卷中。

6.2.11 管道安装工程施工卷除执行本标准 6.2.8条专业 综 合卷 规定外,尚应符合下列规定:

a)管道材料质量证明文件及复验报告可分类组卷,材料质量证明文件一览表按管道材料质量证明

文件排列顺序填写并置于案卷中;

b)管道安装施工文件宜按试压包组卷,且试压包的内容应包括流程图、轴测图、管道焊接工作记

录、管道焊接接头热处理报告、硬度检测报告、金属材料化学成分分析检验报告、管道无损检

测结果汇总表、管道无损检测数量统计表、管道系统压力试验条件确认记录、管道系统压力试

验记录,管道试压包一览表按管道编号排列顺序填写并置于案卷中;

c)管道组成件验证性和补充性检验记录、阀门试验确认表、 安全阀调整试验记录、 弹簧 支 /吊架安

装检验记录、管道补偿器安装检验记录、安全附件安装检验记录、 管道静电接地测试记录 、管

道焊接接头热处理曲线、 管道系统泄漏性 /真空试验条件确认与试验记录 及 管道吹扫 /清洗检验

记录 等管道安装施工文件等,如不便于列入试压包,可分类汇编组卷;

d)管道安装工程中的防腐、保温、保冷等施工文件宜单独组卷。防腐、保温、保冷、脱脂等单独

委托施工的,应单独组卷提交。

6.2.12 电气安装工程施工卷除应执行本标准 6.2.8条专业综合卷规定外,尚应符合下列规定:

a)安装检验(质量验收)记录、隐蔽 工程记录及接地电阻测量记录等文件宜按单位工程、分部工

程、分项工程顺序整理,按供配电系统设备、系统位号、安装工序等顺序组卷;

b)电气设备质量证明文件及随机资料可按设备类别分类组卷,也可按设备位号单独组卷;

c)电气材料质量证明文件按材料类别、品种、规格等顺序组卷。

6.2.13 仪表安装工程施工卷除应执行本标准 6.2.8条专业综合卷规定外,尚 应符合下列规定:

a)仪表安装工程中的调试记录、安装检验记录宜按单位工程、分部工程、分项工程顺序整理,按

控制、检测回路位号顺序组成卷或仪表控制系统安装文件单独组卷;

SH/T 3503— 2017

6

b)仪表设备质量证明文件及随机资料应按设备类别组卷,也可按设备位号组卷,开箱检验记录一

并归入;

c)仪表材料质量证明文件应按材料类别、品种、规格等顺序组卷。

6.2.14 各专业材料质量证明文件组卷时应编写材料质量证明文件一览表,材料质量证明文件按一览表

中的顺序依次排列。

6.2.15 设备出厂资料组卷应符合下列规定:

a)按单台或成套采购的设备,宜单台或成套设备组卷;

b)设备出厂质量证明文件、设备使用维护说明书、图纸等技术资料应归档原件,且应按设备开箱

检验记录、设备出厂质量证明文件、设备使用维护说 明书、图纸的顺序排列,归档组卷时可不

做拆分或合并装订;

c)设备存在质量问题在施工现场进行整改的,相关整改及验收文件应一并编入。

6.2.16 竣工图卷宜按设计文件目录顺序组卷。

6.2.17 竣工图应按 GB/T 10609.3统 一折叠 成 A4幅面,图标栏应外露。

6.2.18 案卷编目 应符合 GB/T 11822 的规 定, 页号的编写应符合下列 规定:

a)归档文件均应按顺序编写页号,案卷封面、卷内目录、卷内备考表不应编写页号;

b)以卷装订的案卷,页号应从 1顺序编号;

c)以件装订的案卷,按件独立编写页号;

d) 页号编写位置:单面书写文件在右下角;双面书写文件,正面在右下角,背面在左下角。

6.2.19 交工技术文件装订应整齐、牢固。

6.3 交工技术文件的交付

6.3.1 设计单位应在工程交工验收前,按合同约定的时间向建设单位提交纸质版和电子版竣工图。

6.3.2 采购、施工或工程总承包单位应在工程交工验收前向建设单位提交交工技术文件。

6.3.3 交工技术文件经审查验收合格后,建设单位应与施工或工程总承包单位、设计单位、采购单位

签署交工技术文件移交证书,办理移交手续。

SH/T 3503— 2017

7

附 录 A

(规范性 附录 )

交工技术文件通用表

序号 名称 编号 页次

A.1 封面 SH/T 3503— J101A 9

A.2 封面 SH/T 3503— J101B 10

A.3 交工技术文件总目录 SH/T 3503— J102 11

A.4 交工技术文件目录 SH/T 3503— J103 12

A.5 交工技术文件说明 SH/T 3503— J104 13

A.6 工程施工开工报告 SH/T 3503— J105A 14

A.7 工程施工开工报告 SH/T 3503— J105B 15

A.8 工程中间交接证书 SH/T 3503— J106A 16

A.9 工程中间交接证书 SH/T 3503— J106B 17

A.10 工程交工验收证书 SH/T 3503— J107A 18

A.11 工程交工验收证书 SH/T 3503— J107B 19

A.12 交工技术文件移交证书 SH/T 3503— J108A 20

A.13 交工技术文件移交证书 SH/T 3503— J108B 21

A.14 重大质量事故处理报告 SH/T 3503— J109 22

A.15 工程设计变更一览表 SH/T 3503— J110 23

A.16 工程联络单一览表 SH/T 3503— J111 24

A.17 隐蔽工程验收记录 SH/T 3503— J112 25

A.18 垫铁隐蔽记录 SH/T 3503— J113 26

A.19 工程联络单 SH/T 3503— J114 27

A.20 合格焊工登记表 SH/T 3503— J115 28

A.21 无损检测人员登记表 SH/T 3503— J116









29

A.22 开箱检验记录 SH/T 3503— J117 30

A.23 防腐工程质量验收记录 SH/T 3503— J118 31

A.24 隔热工程质量验收记录 SH/T 3503— J119 32

A.25 防腐绝缘层电火花检测报告 SH/T 3503— J120 33

A.26 防火工程质量验收记录 SH/T 3503— J121 34

A.27 接地电阻测量记录 SH/T 3503— J122 35

A.28 安全阀调整试验记录 SH/T 3503— J123 36

A.29 安全附件安装检验记录 SH/T 3503— J124 37



SH/T 3503— 2017

8

交工技术文件通用表 (续)



序号 名称 编号 页次

A.30 材料及配件超声检测报告 SH/T 3503— J125-1 38

A.31 材料及配件超声检测报告(续) SH/T 3503— J125-2 39

A.32 材料及配件磁粉检测报告 SH/T 3503— J126-1 40

A.33 材料及配件磁粉检测报告(续) SH/T 3503— J126-2 41

A.34 材料及配件渗透检测报告 SH/T 3503— J127-1 42

A.35 材料及配件渗透检测报告(续) SH/T 3503— J127-2 43

A.36 超声测厚报告 SH/T 3503— J128-1 44

A.37 超声测厚报告(续) SH/T 3503— J128-2 45

A.38 金属材料化学成分检验报告 SH/T 3503— J129 46

A.39 硬度检测报告 SH/T 3503— J130 47

A.40 设备质量证明文件一览表 SH/T 3503— J131-1 48

A.41 设备质量证明文件一览表(续) SH/T 3503— J131-2 49

A.42 材料质量证明文件一览表 SH/T 3503— J132-1 50

A.43 材料质量证明文件一览表(续) SH/T 3503— J132-2 51

A.44 安装检查记录 SH/T 3503— J133 52

A.45 工程影像记录表 SH/T 3503— J134 53



SH/T 3503— 2017

9



SH/T 3503— J101A 封 面

卷号:











石油化工建设工程项目交工技术文件







工程名称:

卷 名:











建设单位 监理单位 施工单位

(项目部章) (项目部章) (项目部章)



项目经理: 项目总监: 项目经理:



年 月 日 年 月 日 年 月 日

SH/T 3503— 2017

10



SH/T 3503— J101B 封 面

卷号:













石油化工建设工程项目交工技术文件







工程名称:



卷 名:













建设单位 监理单位 总承包单位 施工单位

(项目部章) (项目部章) (项目部章) (项目部章)







项目经理: 项目总监: 项目经理: 项目 经理:



年 月 日 年 月 日 年 月 日 年 月 日

SH/T 3503— 2017

11



SH/T 3503— J102 交工技术文件总目录

工程名称:







序号 卷号 卷名 页数



















































编制人:

日期: 年 月 日

审核人:

日期: 年 月 日



SH/T 3503— 2017

12

SH/T 3503— J103 交工技术文件目录

工程名称:



单位工程名称:



序号 文件编号 文件名称 页次



















































编制人:

日期: 年 月 日

审核人:

日期: 年 月 日

SH/T 3503— 2017

13

SH/T 3503— J104 交工技术文件说明

工程名称:









编制人:

日期: 年 月 日

审核人:

日期: 年 月 日



SH/T 3503— 2017

14

SH/T 3503— J105A 工程施工开工报告

工程名称:







施工合同编号 设计单位

计划开工日期 年 月 日 计划交工日期 年 月 日



























































工程质量监督站长 /组长:(监督站 /组章) 年 月 日

建设单位 监理单位 施工单位



(项目部章)

项目经 理:



日期: 年 月 日



(项目部章)

项目总监:



日期: 年 月 日



(项目部章)

项目经理:



日期: 年 月 日

SH/T 3503— 2017

15

SH/T 3503— J105B 工程施工开工报告

工程名称:







施工合同编号 设计单位

计划开工日期 年 月 日 计划交工日期 年 月 日



























































工程质量监督站长 /组长:(监督站 /组章) 年 月 日

建设单位 监理单位 总承 包单位 施工单位



(项目部章)

项目经理:



日期: 年 月 日



(项目部章)

项目总监:



日期: 年 月 日



(项目部章)

项目经理:



日期: 年 月 日



(项目部章)

项目经理:



日期: 年 月 日

SH/T 3503— 2017

16

SH/T 3503— J106A 工程中间交接证书

工程名称:







施工合同编号 交接日期 年 月 日

































附:施工尾项清单:份。



















使用单位负责(代表)人: 年 月 日



























工程质量监督站长 /组长:(监督站 /组章) 年 月 日



建设单位 设计单位 监理单位 施工单位



(项目部章)

项目经理:



日期: 年 月 日



(项目部章)

项目经理:



日期: 年 月 日



(项目部章)

项目总监:



日期: 年 月 日



(项目部章)

项目经理:



日期: 年 月 日



SH/T 3503— 2017

17

SH/T 3503— J106B 工程中间交接证书

工程名称:







施工合同编号 交接日期 年 月 日

































附:施工尾项清单:份。



















使用单位负责(代表)人: 年 月 日



























工程质量监督站长 /组长:(监督站 /组章) 年 月 日



建设单位 设计单位 监理单位 总承包单位 施工单位



(项目部章)

项目经理:

年 月 日



(项目部章)

项目经理:

年 月 日



(项目部章)

项目总监:

年 月 日



(项目部章)

项目经理:

年 月 日



(项目部章)

项目经理:

年 月 日



SH/T 3503— 2017

18

SH/T 3503— J107A 工程交工验收证书

工程名称:







施工合同编号

实际开工日期 年 月 日 交工日期 年 月 日

工程内容:

工程验收意见:









使用单位负责(代表)人: 年 月 日

工程质量监督意见:











工程质量监督站长 /组长:(监督站 /组章) 年 月 日

建设单位 设计单位 监理单位 施工单位



(项目部章)

项目经理:



日期: 年 月 日



(项目部章)

项目经理:



日期: 年 月 日



(项目部章)

项目 总监:



日期: 年 月 日



(项目部章)

项目经理:



日期: 年 月 日



SH/T 3503— 2017

19

SH/T 3503— J107B 工程交工验收证书

工程名称:







施工合同编号

实际开工日期 年 月 日 交工日期 年 月 日

工程内容:

工程验收意见:









使用单位负责(代表)人 : 年 月 日

工程质量监督意见:











工程质量监督站长 /组长:(监督站 /组章) 年 月 日

建设单位 设计单位 监理单位 总承包单位 施工单位



(项目部章)

项目经理 :



年 月 日



(项目部章)

项目经理:



年 月 日



(项目部章)

项目总监:



年 月 日



(项目部章)

项目经理:



年 月 日



(项目部章)

项目经理:



年 月 日

SH/T 3503— 2017

20

SH/T 3503— J108A 交工技术文件移交证书

工程名称:



合同编号:









按《石油化工建设工程项目交工技术文件规定》( SH/T 3503— 2017)向办理工程建设交工技术文件移

交手续,共计文字资料卷,竣工图卷,电子文件盘。

附:交工技术文件移交清单。

建设单位 监理单位 承包 单位



(项目部章)

经办人 :

日期: 年 月 日



(项目部章)

审核人 :

日期: 年 月 日



(项目部章)

经办人:

日期: 年 月 日



SH/T 3503— 2017

21

SH/T 3503— J108B 交工技术文件移交证书

工程名称:



合同编号:









按《石油化工建设工程项目交工技术文件规定》( SH/T 3503— 2017)向办理工程建设交工技术文件移

交手续,共计文字资料卷,竣工图卷,电子文件盘。

附:交工技术文件移交清单。

建设单位 监理单位 总承包单位 施工单位



(项目部章)

经 办人 :



日期: 年 月 日



(项目部章)

审核人:



日期: 年 月 日



(项目部章)

经办人 :



日期: 年 月 日



(项目部章)

审核人:



日期: 年 月 日



SH/T 3503— 2017

22

SH/T 3503— J109

重大质量事故处理

报告

工程名称:

































责任单位代表:责任单位(公章) 年 月 日











































监理单位总监:(公章) 年 月 日



























工程质量监督站长:(公章) 年 月 日

相关单位



(公章)

代表:



日期: 年 月 日



(公章)

代表:



日期: 年 月 日



(公章)

代表:



日期: 年 月 日

SH/T 3503— 2017

23

SH/T 3503— J110 工程设计变更一览表

工程名称:



单位工程名称:

专业

序号 变更通知单号 变更 原因 实施图号及变更要点 实施情况说明





































注:变更原因填写设计原因或非设计原因 。

建设单位 监理单位 施工单位

专业工程师:







日期: 年 月 日

专业工程师:







日期: 年 月 日

编制人:



审核人:



日期: 年 月 日



SH/T 3503— 2017

24

SH/T 3503— J111 工程联络单一览表

工程名称:



单位工程名称:



专业

序号 联络单编号 事由 实施情况说明







































建设 /监理单位 总承包单位 施工单位

专业工程师:







日期: 年 月 日

专业工程师:







日期: 年 月 日

编制人:



审核人:



日期: 年 月 日



SH/T 3503— 2017

25



SH/T 3503— J112 隐蔽工程验收记录

工程名称:



单位工程名称:



隐蔽项目 施工图号







































建设 /监理单位 总承包单位 施工单位

专业工程师:





日期: 年 月 日

专业工程师:





日期: 年 月 日

施工班组长:

质量检查员:

专业工程师:

日期: 年 月 日



SH/T 3503— 2017

26

SH/T 3503— J113 垫 铁 隐 蔽 记 录

工程名称:





单位名称:

设备 /结构名称 位号

垫铁布置位置示意图:













垫铁情况说明:

平垫铁尺寸(长 × 宽 × 高): 斜垫铁尺寸(长 × 宽 × 薄端高): 斜度:

每组垫铁构成:块数:垫铁组高度:

检查项目 安装要求 检查结果

设备找正 数据符合规范要求 □不符合□符合

垫铁规格 符合施工方案要求 □不符合□符合

垫铁布置位置 符合规范要求 □不符合□符合

每组垫铁块数 符合规范要求 □不符合□符合

每组垫铁高度 符合设计文件和规范要求 □不符合□符合

斜垫铁搭接长度 符合规范要求 □不符合□符合

垫铁间点焊固定 符合规范要求 □不符合□符合

结论:

经检查,□不符合□符合设计文件和规范要求,□不可以□可以隐蔽。

建设/监理单位 总承包单位 施工单位

专业工程师:





日期: 年 月 日

专业工程师:





日期: 年 月 日

施工班组长:

质量检查员:

专业工程师:

日期: 年 月 日

SH/T 3503— 2017

27



SH/T 3503— J114 工程联络单

工程名称:

单位工程名称:

联络单编号 送达单位

事由:

内容:















经办人: 提出单位(项目章)

审核人: 年 月 日

接收单位处理意见:









经办人: 审核人: (项目章)

年 月 日 年 月 日

会签意见:



















代表:

会签单位(项目章)

日期: 年 月 日

会签意见 :



















代表:

会签单位(项目章)

日期: 年 月 日

会签意见:



















代表:

会签单位(项目章)

日期: 年 月 日

SH/T 3503— 2017

28

SH/T 3503— J115 合格焊工登记表

工程名称:







序号 焊工姓名 焊工代号 证书编号 合格项目代号 有效期限













































建设 /监理单位 总承包单位 施工单位

专业工程师:





日期: 年 月 日

专业工程师:





日期: 年 月 日

专业工程师:





日期: 年 月 日

SH/T 3503— 2017

29



SH/T 3503— J116 无损检测人员登记表

工程名称:







序号 姓名 证书编号 合格项目代号 级别 有效期限













































建设 /监理单位 总承包单位 检测单位

专业工程师:





日期: 年 月 日

专业工程师:





日期: 年 月 日

专业工程师:

制表人:



日期: 年 月 日



SH/T 3503— 2017

30

SH/T 3503— J117 开箱检验记录

工程名称:



单位工程名称:



名称 位号

型号 制造商

合同号 箱数

箱号 装箱单号











1.包装□无破损□有破损; 4.外观□无可见缺陷□有可见缺陷

2.规格与装箱单□相符□不相符; 5.质量证明文件□有□无

3.数量与装箱单□相符□不相符; 6.产品技术文件□有□无

























名称 份数 接收单位 接收人















名称 数量 接收单位 接收人







建设单位 监理单位 总承包单位 施工单位 采购单位

专业工程师:



日期: 年 月 日

专业工程师:



日期: 年 月 日

专业工程师:



日期: 年 月 日

专业工程师:



日期: 年 月 日

检验人员:



日期: 年 月 日



SH/T 3503— 2017

31

SH/T 3503— J118 防腐工程质量验收记录

工程名称:



单位工程名称:



防腐前表面状态











防腐

层结

构及

要求



检查项目与要求 检查结果

原材料符合设计要求及有关规范规 定,具有出厂质量合格证明文件及复验报告

设备、管道按规定进行了压力试验,具有工序交接记录

基层表面处理方法正确,处理结果符合设计等级要求

隔离层材料使用正确,层数或厚度符合规范规定

防腐层材料的配比、试验符合有关规范规定,报告齐全

防腐底层材料使用正确,层数、厚度符合规范规定

防腐中间层材料使用正确,层数、厚度符合规范规定

防腐面层材料使用正确,层数、厚度符合规范规定

部位 材料名称 牌号 生产厂家 设计漆膜厚度 mm 实测总漆膜厚度 mm

底层

中间层

面层

验收结论:

建设 /监理单位 总承包单位 施工单位

专业工程师:





日期: 年 月 日

专业工程师:





日期: 年 月 日

施工班组长:

质量检查员:

专业工程师:

日期: 年 月 日

SH/T 3503— 2017

32



SH/T 3503— J119 隔热工程质量验收记录

工程名称:



单位工程名称:























检查项目与要求 检查结果

原材料符合设计及有关规范要求,具有出厂质量证明文件及复验报告

设备、管道按规定进行了压力试验,防腐涂层完毕

具有工序交接记录

管支、托架处的隔热层结构不影响活动面的自由伸缩







成型制品同层错缝、内外层压缝,伸缩缝留置正确,嵌缝充填或粘贴紧密、厚度偏

差符合规范规定

缠裹材料同层靠紧,内外层缠裹方向相反,接缝错开,厚度偏差符合规范规定

散状材料和浇注材料,填充密实、均匀,厚度偏差符合规范规定







粘贴于隔热层上,无脱落和鼓包现象,表面平整,厚度符合规范规定







金属保护层应压边,搭接缝、表面平整度符合规范规定,无脱壳和凹凸不平

卷材保护层应紧贴表面,无 褶皱和开裂

抹面保护层应平整、光滑,端部棱角整齐,无显著裂纹,表面平整度符合规范规定

验收结论:

建设 /监理单位 总承包单位 施工单位

专业工程师:





日期: 年 月 日

专业工程师:





日期: 年 月 日

施工班组长:

质量检验员:

专业工程师:

日期: 年 月 日



SH/T 3503— 2017

33

SH/T 3543— J120 防腐绝缘层电火花检测报告

工程名称:



单位工程名称:

检测单位 报告编号

设备位号

/管道编号

(单线号)

名 称

防腐等级 执行标准

设计厚度 mm 防腐类型 电压 V

检测部位 检测结果 检测部位 检测结果



































备注:

检测人:



日期: 年 月 日

质量工程师:

日期: 年 月 日



SH/T 3503— 2017

34

SH/T 3503— J121 防火工程质量验收记录

工 程名称:



单位工程名称:

防火

部位



防火

结构

检查项目与要求 检查结果

原材料符合设计及有关规范要求,具有出厂质量证明文件及复验报告

防腐涂层完毕

具有工序交接记录

防火层表面平整,厚度均匀,厚度偏差符合规范规定

验收结论:

建设 /监理单位 总承包单位 施工单位

专业工程师:





日期: 年 月 日

专业工程师:





日期: 年 月 日

施工班组长:

质量检验员:

专业工程师:

日期: 年 月 日



SH/T 3503— 2017

35

SH/T 3503— J122 接地 电阻测量记录

工程名称:



单位工程名称:

专业工程 施工图号 测量日期 年月日

接地种类 测量仪表型号 允许值 Ω

接地电阻测量记录

序号 测量位置 实测值 Ω 环境相对湿度 % 测量时间 当天及前三天的天气情况























测量结论:

测量位置示意图:

建设 /监理单位 总承包单位 施工单位

专业工程师:





日期: 年 月 日

专 业工程师:





日期: 年 月 日

测量人:

质量检查员:

专业工程师:

日期: 年 月 日

SH/T 3503— 2017

36



SH/T 3503— 2017

37

SH/T 3503— J124 安全附件安装检验记录

工程名称:



单位工程名称:



管线 /设备 安全附件位号 名称 型号规格 合格证号 检查结果









































建设 /监理单位 总承包单位 施工单位

专业工程师:





日期: 年 月 日

专业工程师:





日期: 年 月 日

施工班组长:

质量检查员:

专业工程师:

日期: 年 月 日



SH/T 3503— 2017

38

SH/T 3503— J125-1

材料及配件

超声检测报告

第 页 共 页

工程名称:



单位工程名称:



委托单位 施工单位 报告编号

检件名称 检测标准 合格级别 检测灵敏度

验收标准 检测比例 耦合剂 热处理状态

探头 试块 检测面 设备型号 表面状态 表面补偿 扫描比例

序号 型号 型号 1 型号 2







质量证明

文件编号 炉 /批号 检件编号 检件规格 检件材质

探头

序号

缺陷情况或

缺陷示意图编号 评定级别

































检测人:

资格: UT 级

审核人:

资格: UT 级

检测单位:(公章)

报告 日期: 年 月 日



SH/T 3503— 2017

39

SH/T 3503— J125-2

材料及配件

超声检测报告 (续)

第 页 共 页

工程名称:



单位工程名称:



委托单位 施工单位 报告编号

质量证明

文件编号 炉 /批号 检件编号 检件规格 检件材质

探头

序号

缺陷情况或

缺陷示意图编号 评定级别



















































SH/T 3503— 2017

40

SH/T 3503— J126-1

材料及配件

磁粉检测报告

第 页 共 页

工程 名称:



单位工程名称:



委托单位 施工单位 报告编号

检件名称 检测标准 合格级别 灵敏度试片

验收标准 检测比例 表面状态 热处理状态

磁化方法 电流类型 磁化时间 提升力 /电流

磁悬液浓度 磁粉种类 设备型号 电 /磁极间距

质量证明

文件编号 炉 /批号 检件编号 检件规格 检件材质 检测面

缺陷情况或

缺陷示意图编号

评定

结果







































检测人:



资格: MT 级

审核人:



资格: MT 级

检测单位:(公章)



报告 日期: 年 月 日

SH/T 3503— 2017

41

SH/T 3503— J126-2

材料及配件

磁粉检测报告 (续)

第 页 共 页

工程名称:



单位工程名称:



委托单位 施工单位 报告编号

质量证明

文件编号 炉 /批号 检件编号 检件规格 检件材质 检测面

缺陷情况或

缺陷示意图编号

评定

结果



















































SH/T 3503— 2017

42



SH/T 3503— J127-1

材料及配件

渗透检测报告

第 页 共 页

工程名称:



单位工程名称:



委托单位 施工单位 报告编号

检件名称 检测标准 合格级别 检测灵敏度

验收标准 检测比例 表面状态 热处理状态

检测方法 检测试块 观察方法 检测剂牌号

渗透温度 渗透时间 显像时间 施加方法

质量证明

文件编号 炉 /批号 检件编号 检件规格 检件材质 检测面

缺陷情况或

缺陷示意图编号

评定

结果







































检测人:



资格: PT 级

审核人:



资格: PT 级

检测单位:(公章 )



报告 日期: 年 月 日

SH/T 3503— 2017

43



SH/T 3503— J127-2

材料及配件

渗透检测报告 (续)

第 页 共 页

工程名称:



单位工程名称:



委托单位 施工单位 报告编号

质量证明

文件编号 炉 /批号 检件编号 检件规格 检件材质 检测面

缺陷情况或

缺陷示意图编号

评定

结果





















































SH/T 3503— 2017

44

SH/T 3503— J128-1 超声测厚报告

第 页 共 页

工程名称:



单位工程名称:



委托单位 施工单位 报告编号

检件名称 检测标准 验收标准

检件规格 检件材质 检测比例

耦合剂 设备型号 测量 精度 mm

检测部位编号 名义厚度 mm 实测厚度 mm 检测部位编号 名义厚度 mm 实测厚度 mm





































检测结论:

共检测点,符合标准要求点,不符合标准要求点,具体检测部位详见示意图。

检测人:





审核人:





检测单位:(公章)





报告 日期: 年 月 日



SH/T 3503— 2017

45

SH/T 3503— J128-2 超声测厚报告 (续)

第 页 共 页

工程名称:



单位工程名称:



委托单位 施工单位 报告编号

检测部位编号 名义厚度 mm 实测厚度 mm 检测部位编号 名义厚度 mm 实测厚度 mm























































SH/T 3503— 2017

46

SH/T 3503— J129

金属材料化学成分

检验报告

第 页 共 页

工程名称:



单位工程名称:



委托单位 施工单位 报告编号

检件名称 检验标准 被检验材料 标准

检验方法 设备型号 检件材质

质量证明文件

编号 /炉批号 检验部位编号 规格

元素含量 %









































检验结论:

共检验点,符合标准要求点,不 符合标准要求点,具体检验部位详见示意图。

试验人:



资格:

审核人:



资格:

检测单位:(公章)

报告 日期: 年 月 日



SH/T 3503— 2017

47

SH/T 3503— J130 硬度检测报告

第 页 共 页

工程名称:

单位工程名称:

委托单位 施工单位 报告编号

检件名称 检测标准 验收标准

检件规格 检件材质 检测比例

检测方法 热处理状态 设备型号

检测部位编号 硬度值 检测部位编号 硬度值 检测部位编号 硬度值



































检测结论:

共检测点,符合标准要求点,不符合标准要求点,具体检测部位详见示意图。

试验人:



资格:

审核人:



资格:

检测单位:(公章)

报告 日期: 年 月 日

SH/T 3503— 2017

48



SH/T 3503— 2017

49

SH/T 3503— 2017

50

SH/T 3503— 2017

51



SH/T 3503— 2017

52



SH/T 3503— J133 安装 检查记录

工程名称:



单位工程名称:

专业工程 施工图号

检查项目:































检验结论:























建设/监理单位 总承包单位 施工单位

专业工程师:





日期: 年 月 日

专业工程师:





日期: 年 月 日

施工班组长:

质量检查员:

专业工程师:

日期: 年 月 日

SH/T 3503— 2017

53



SH/T 3503— J134 工程影像记录表

工程名称:



单位工程名称:

位 号 拍摄日期

部 位



影像图片:







情况说明:











日 期:

拍照单位 确认单位 施工单位

拍照人:







日期: 年 月 日

确认人:







日期: 年 月 日

专业工程师:







日期: 年 月 日

SH/T 3503— 2017

54

附 录 B

(规范性附录 )

交工技术文件土建工程用表

序号 名称 编号 页次

B.1 地基验槽(坑)记录 SH/T 3503—J201 55

B.2 地基处理记录 SH/T 3503—J202 56

B.3 工程定位测量记录 SH/T 3503—J203 57

B.4 设备基础复 测记录 SH/T 3503—J204 58

B.5 块体式设备基础允许偏差项目复测记录 SH/T 3503—J205 59

B.6 整体框架式设备基础允许偏差项目复测记录 SH/T 3503—J206 60

B.7 储罐基础允许偏差项目复测记录(一) SH/T 3503—J207-1 61

B.8 储罐基础允许偏差项目复测记录(二) SH/T 3503—J207-2 62

B.9 球形储罐基础允许偏差项目复测记录 SH/T 3503—J208 63

B.10 基础沉降观测记录 SH/T 3503—J209 64

B.11 水池蓄水试验记录 SH/T 3503—J210 65

B.12 土建隐蔽工程验收记录 SH/T 3503—J211 66

B.13 防水工程试水、蓄水通用检查记录 SH/T 3503—J212 67





SH/T 3503— 2017

55



SH/T 3503— J201 地基验槽(坑)记录

工程名称:



单位工程名称 :

施工图号 验槽部位











1.平面 尺寸: ________________________________________________________

2.开挖简图 :









1.基槽开挖至勘探报 告第 ______ 层,持力层为 __________层。

2.基底绝对高程和相对标高 ________________________________________________________。

3.土质情况 ______________________________________________________________________。

4.桩位置 _______、桩类型 ________、数量 ________,承载力满足设计要求。

5.其他说明情况。







附: □ 施工记录、 □ 桩检 测报告。

注:若土建工程无桩基或人工支护,则相应在第 4项填写处 划“ /”。



















□ 无异常,可进入下步工序 □ 需要地基处理 □ 检查情况影像

建设 /监理单位 设计 /总承包单位 勘 察 单 位 施 工 单 位

专业工程师:







日期: 年 月 日

专业工程师:







日期: 年 月 日

专业工程师:







日期: 年 月 日

填表人:

质量检查员:

专业工程师:



日期: 年 月 日

SH/T 3503— 2017

56



SH/T 3503— J202 地基处理记录

工程名称:



单 位工程 名称:

施工日期 年 月 日 至 年 月 日

处理依据 :

施工图号,设计变更 /洽商(编号)及有关国家现行标准、规范等。

处理方式:



处理部位及状况 (或用简图表示 ):

处理结果:







附: □ 施工记录、 □ 检测报告。

检验结论:









□ 通过,可进入下步工序 □ 未通过,整改后复查 □ 附检查情况影像

建设 /监理单位 设计 /总承包单位 勘 察 单 位 施 工 单 位

专业工程 师:







日期: 年 月 日

专业工程师:







日期: 年 月 日

专业工程师:







日期: 年 月 日

质量检查员:

专业工程师:





日期: 年 月 日

SH/T 3503— 2017

57



SH/T 3503— J203 工程定位测量记录

工程名称:





单 位工程 名称:

委托单位 施工图号

高程依据 平面坐标依据

允许误差 mm 仪器型号

施测日期 年 月 日 仪器检定日期 年 月 日



























建设 /监理单位 总承 包单位 施工单位 测量单位

专业工程师:







日期: 年 月 日



日期:

专业工程师:







日期: 年 月 日

专业工程师:







日期: 年 月 日

测量人:

复核人:

专业工程师:



日期: 年 月 日



SH/T 3503— 2017

58

SH/T 3503— J204 设备基础复测记录

工程名称:



单位工程名称:

基础名称 设备位号 施工图号

引点标桩号 引点标高 m 标高 ±0.00 m

观测仪器 复测日期 年 月 日 仪器检定 日期 年 月 日

复测项

目名称

测点

编号

设计坐标

m

坐标差

mm 测点

编号

设计标高

m

实测标高

m

标高差

mm

X Y ?X ?Y + -

















测点编号图示:

复测结果确认:

建设 /监理单位 总承包单位 施工单位



专业工程师:







日期: 年 月 日

专 业工程师:







日期: 年 月 日

测量人:

质量检查员:

专业工程师:



日期: 年 月 日

SH/T 3503— 2017

59

SH/T 3503— J205 块体式设备基础

允许偏差项目复测记录

工程名称:



单位工程名称:

基础名称 设备位号

施工图号 复测日期 年 月 日



号 复测项目

允许偏差

mm

各检查点实际偏差 mm

1 2 3 4 5 6 7 8 9 10

1 轴线位置 20

2 基础不同平面的标高 0, - 20

3

基础平面外形尺 寸 ± 20

基础凸台上平面外形尺寸 0, - 20

基础凹槽尺寸 + 20, 0

4 基础平面的水平度(包括 地坪上需安装设备部分) 每米 5 全长 10

5 基础侧面垂直度 每米 5 全长 10

6

预埋

地脚螺



标高(顶端) + 10, 0

中心距(在根部和顶

部两处测量) ± 2

7

地脚螺

栓预留



中心位置 ± 10

深度 + 20, 0

孔壁垂直度 10

8

预埋活

动地脚

螺栓

锚板

标高 + 20, 0

中心位置 ± 5







带槽的锚板 5

带螺纹孔的锚板 2

9

预埋活

动地脚

螺栓

套管

中心距 ± 5

垂直度 5

对角线长度、中心园直径 ± 5

相对基础中 心位置偏移 5

复测结果确认(检查点位置见附图):

接收单位 建设 /监理单位 总承包单位 施工单位

专业工程师:







日期: 年 月 日

专业工程师:







日期: 年 月 日

专业工程师:







日期: 年 月 日

质量检查员:

专业工程师:



日期: 年 月 日



SH/T 3503— 2017

60

SH/T 3503— J206 整体框架式设备基础

允许偏差项目复测记 录

工程名称:



单位工程名称:

基础名称 设备位号

施工图号 复测日期 年 月 日



号 复测项目

允许偏差

mm

各检查点实际偏差

mm

1 2 3 4 5 6 7 8 9 10

1 轴线位移

基础 15

独立基础 10

柱、梁 8

2







层间 5m 及以下 8 5m 以上 10

全高 H/1 000 且 ≤ 30

3 标高 层高 ± 10



全高 ± 10

4 截面尺寸 +8 -5

5 表面平整度 (用 2m 直尺检查) 8

6

预埋

设施

中心

位移

预埋件 5

预埋地脚螺栓 2

预埋管 3

7 预留洞中心位移 10

注: H 为结构全高,检查点位置见附图。

复测结果确认:

接收单位 建设 /监理单位 总承包单位 施工单位

专业工程师:





日期: 年 月 日



专业工程师:





日期: 年 月 日

专业工程师:





日期: 年 月 日

质量检查员:

专业工程师:



日期: 年 月 日

SH/T 3503— 2017

61

SH/T 3503— J207-1 储罐基础允许偏差项目

复测记录(一)

工程名称:



单位工程名称:

储罐位号 复测日期 年 月 日

储罐容积 m3 储罐直径 m

基础中心

标高

偏差, mm

允许值 ± 20 基础中心

位置偏差,

mm

允许值 20 直径允许

偏差, mm

允许值 +30 0

实测值 实测值 实测值















































接收单位 建设 /监理单位 总承包单位 施工单位

专业工程师:







日期: 年 月 日

专业工程师:







日期: 年 月 日

专业工程师:







日期: 年 月 日

质量检查员:

专业工程师:



日期: 年 月 日



SH/T 3503— 2017

62

SH/T 3503— J207-2 储罐基础允许偏差项目

复测记录(二)

工程名称:



单位工程名称:

储罐位号 复测日期 年 月 日

同心圆编号 /

平行线编号

计算标高

mm

实测点标高差

mm

任意两点

最大高差

mm

相邻两点

最大高差

mm











































注:“同心圆编号”用罗马数字表示;

“测点编号”用阿拉伯数字表示。

接收单位 建设 /监理单位 总承包单位 施工单位

专业工程师:







日期: 年 月 日

专业工程师:







日期: 年 月 日

专业工程师:







日期: 年 月 日

质量检查员 :

专业工程师:





日期: 年 月 日



SH/T 3503— 2017

63

SH/T 3503— J208 球形储罐基础允许偏差

项目复测记录

工程名称:



单 位工程 名称:

球罐位号 复测日期 年 月 日

球罐直径 m 球罐容积 m3

基础

编号

复测项目 地脚螺栓与基

础中心圆的距

离偏差 S1

mm

预留孔中心与基

础中心圆的距离

偏差 S2

mm

相邻支柱基

础中心间距

偏差 Δ S

mm

基础中心圆

直径偏差

mm 基础方位 偏差

(°)

基础标高

偏差

mm

基础平面

度偏差

mm 内 外 内 外 内 外

1

2

3

4

5

6

7

8

9

10

11

12

13

14

15

16

复测结果确认(球形储罐基础平面见附图):

接收单位 建设 /监理单位 总承包 单位 施工单位

专业工程师:





日期: 年 月 日

专业工程师





日期: 年 月 日

专业工程师:





日期: 年 月 日

质量检查员:

专业工程师:





日期: 年 月 日

SH/T 3503— 2017

64

SH/T 3503— J209 基础沉降观测

记 录

工程名称:



单 位工程 名称:

设备名称 设备位号

几何尺寸 容积

水准点编号 水准点高程

观测仪器 仪器精度 仪器检定日期 年 月 日

观测日期 自年月日时开始年月日时止

观测阶段 观测时间

观测点沉 降值

mm

1 2 3 4 5 6 7 8 9 10 11 12 13 14



















基础观测点平面示意图:



观测结果分析及结论:

建设 /监理单位 总承包单位 施工单位 测量单位

专业工程师:





日期: 年 月 日

专业工程师:





日期: 年 月 日

专业工程师:





日期: 年 月 日

测量人:

复核人:

专业工程师:

日期: 年 月 日

SH/T 3503— 2017

65

SH/T 3503— J210 水池蓄水试验记录

工程名称:



单 位工程 名称:

水池名称 水池位号

水池结构 防水等级

水池平面尺寸

( L×W) m 水面面积 A1 m

2

允许渗水量 , q0 L/(m2·d) 湿润面积 A2 m2

水深 m 试验日期 自 年 月 日 时 至 年 月 日 时

测读记录 初读 末读 两次读数差

水位测针读数 E,

mm E1 E2 E1- E2

蒸发水箱水位测针

读数 e, mm e1 e2 e1- e2

水温, ℃ -

大气温度, ℃ -

测读时间(月、日、

时、分) 月日时分 月日时分 -

实际渗水量 q

q= A1 /A2[(E1- E2)-

( e1- e2)]

L/(m2·d)

占允许渗水量的

百分率

q/q0

%

试验结果:



建设 /监理单位 总承包单位 施工单位

专业工程师:





日期: 年 月 日

专业工程师:





日期: 年 月 日

质量检查员:

专业工程师:



日期: 年 月 日



SH/T 3503— 2017

66

SH/T 3503— J211

土建隐蔽工程

验收记录

工程名称:



单 位工程 名称:

隐检项目 隐检日期

隐检部位 层 /轴线 /标高



隐检依据:施工图号,设计变更 /洽商(编号)及有关国家现行标准等。

主要材料名称及规格、型号:



隐检内容:





检查意见:



□ 同意隐蔽 □ 不同意隐蔽,整改后复查

□ 附检查情况影像

复查结论:







复查人: 复查日期:

建设 /监理单位 总承包单位 施工单位

专业工程师:





日期: 年 月 日

专业工程师:





日期: 年 月 日

质量检查员:

专业工程师:



日期: 年 月 日



SH/T 3503— 2017

67

SH/T 3503— J212 防水工程试水、 蓄水通用检查记录

工程名称:



单 位工程 名称:

工程位号 检查日期

检查部位 蓄水时间 从 年 月 日 时 至 年 月 日 时



检查依据:施工图号,设计变 更 /洽商(编号)及有关国家现行标准等。



检查方法及内容:





检查意见:



□ 通过,可进入下步工序 □ 未通过,整改后复查

□ 附检查情况影像

复查结论:



复查人: 复查日期:

建设 /监理单位 总承包单位 施工单位

专业工程师:





日期: 年 月 日

专业工程师:





日期: 年 月 日

质量检查员:

专业工程师:



日期: 年 月 日

SH/T 3503— 2017

68

附 录 C

( 规范性附录)

交工技术文件设备安装工程用表

序号 名称 编号 页次

C.1 机器安装检验记录 SH/T 3503—J301 71

C.2 轴对中记录 SH/T 3503—J302 72

C.3 机组轴对中记录 SH/T 3503—J303 73

C.4 空冷式换热器风机安装检验记录 SH/T 3503—J304 74

C.5 机器组装质量确认记录 SH/T 3503—J305 75

C.6 往复式压缩机找平找正记录(卧式) SH/T 3503—J306 76

C.7 往复式压缩机找平找正记录(立式) SH/T 3503—J307 77

C.8 往复式压缩机曲柄臂间距检查记录 SH/T 3503—J308 78

C.9 往复式压缩机主轴轴线与中体滑道轴线垂直度检查记录 SH/T 3503—J309 79

C.10 往复式压缩机主轴瓦与推力轴瓦间隙检查记录 SH/T 3503—J310 80

C.11 往复式压缩机十字头与中体滑道间隙检查记录(卧式) SH/T 3503—J311 81

C.12 往复式压缩机十字头与中体滑道间隙检查记录(立式) SH/T 3503—J312 82

C.13 往复式压缩机连杆组装记录 SH/T 3503—J313 83

C.14 往复式压缩机气缸余隙检查记录 SH/T 3503—J314 84

C.15 往复式压缩机活塞与气缸圆周间隙检查记录 SH/T 3503—J315 85

C.16 往复式压缩机活塞环安装记录 SH/T 3503—J316 86

C.17 往复式压缩机填料函各部间隙检查记录 SH/T 3503—J317 87

C.18 机器单机试车记录 SH/T 3503—J318-1 88

C.19 ____设备单机试车记录 SH/T 3503—J318-2 89

C.20 机组试车条件确认记录 SH/T 3503—J319 90

C.21 往复式压缩机试车记录 SH/T 3503—J320-1 91

C.22 往复式压缩机试车记录(续) SH/T 3503—J320-2 92

C.23 离心式压缩机试车记录 SH/T 3503—J321-1 93

C.24 离心式压缩机试车记录(续 1) SH/T 3503—J321-2 94

C.25 离心式压缩机试车记录(续 2) SH/T 3503—J321-3 95

C.26 汽轮机 /燃气轮机试车记录 SH/T 3503—J322-1 96

C.27 汽轮机 /燃气轮机试车记录 (续) SH/T 3503—J322-2 97

SH/T 3503— 2017

69

交工技术文件设备安装工程用表 (续)

序号 名称 编号 页次

C.28 电动机试车记录 SH/T 3503—J323 98

C.29 变速器试车记录 SH/T 3503—J324 99

C.30 釜类设备安装检验记录 SH/T 3503—J325 100

C.31 立式设备安装检验记录 SH/T 3503—J326 101

C.32 卧式设备安装检验记录 SH/T 3503—J327 102

C.33 塔盘安装检验记录 SH/T 3503—J328 103

C.34 设备填充检验 记录 SH/T 3503—J329 104

C.35 反应 /沉降器附件安装检验记录 SH/T 3503—J330 105

C.36 再生器附件安装检验记录 SH/T 3503—J331 106

C.37 立式圆筒形储罐组装质量检验记录 SH/T 3503—J332 107

C.38 立式圆筒形储罐罐底真空试验记录 SH/T 3503—J333-1 108

C.39 立式圆筒形储罐开孔补强圈气密性试验记录 SH/T 3503—J333-2 109

C.40 立式圆筒形储罐浮顶/船舱严密性试验记录 SH/T 3503—J333-3 110

C.41 立式圆筒形储罐总体试验记录 SH/T 3503—J333-4 111

C.42 湿式气柜组装质量检验记录 SH/T 3503—J334 112

C.43 湿式气柜底板严密性试验记录 SH/T 3503—J335-1 113

C.44 湿式气柜开孔补强圈气密性试验记录 SH/T 3503—J335-2 114

C.45 湿式气柜水槽严密性试验记录 SH/T 3503—J335-3 115

C.46 湿式气柜整体试验记录 SH/T 3503—J335-4 116

C.47 干式气柜组装质量检验记录 SH/T 3503—J336 117

C.48 干式气柜底板/活塞板/壁板严密性试验记录 SH/T 3503—J337-1 118

C.49 干式气柜开孔补强圈气密性试验记录 SH/T 3503—J337-2 119

C.50 干式气柜总体试验记录 SH/T 3503—J337-3 120

C.51 火炬塔架和管筒安装检验记录 SH/T 3503—J338 121

C.52 隔热耐磨衬里质量检验记录 SH/T 3503—J339 122

C.53 热交换设备耐压和泄漏试验记录 SH/T 3503—J340 123

C.54 设备耐压和泄漏试验记录 SH/T 3503—J341 124

C.55 设备热处理报告 SH/T 3503—J342 125

C.56 管式炉炉体钢结构安装检验记录 SH/T 3503—J343 126

SH/T 3503— 2017

70

交工技术文件设备安装工程用表 (续)

序号 名称 编号 页次

C.57 炉管通球试验记录 SH/T 3503—J344 127

C.58 管式 炉附件安装质量检验记录 SH/T 3503—J345 128

C.59 耐火砖砌筑炉衬质量检验记录 SH/T 3503—J346 129

C.60 耐火浇注料炉衬质量检验记录 SH/T 3503—J347 130

C.61 耐火纤维模块炉衬质量检验记录 SH/T 3503—J348 131

C.62 设备及构件焊缝射线检测报告 SH/T 3503—J349-1 132

C.63 设备及构件焊缝射线检测报告( 续 ) SH/T 3503—J349-2 133

C.64 设备及构件焊缝超声检测报告 SH/T 3503—J350-1 134

C.65 设备及构件焊缝超声检测报告( 续 ) SH/T 3503—J350-2 135

C.66 设备及构件焊缝磁粉检测报告 SH/T 3503—J351-1 136

C.67 设备及构件焊缝磁粉检测报告( 续 ) SH/T 3503—J351-2 137

C.68 设备及构件焊缝渗透检测报告 SH/T 3503—J352-1 138

C.69 设备及构件焊缝渗透检测报告( 续 ) SH/T 3503—J352-2 139



SH/T 3503— 2017

71



SH/T 3503— J301 机器安装检验记录

工程名称:



单位工程名称:

设备名称 设备位号 型号

项目 允许值 实测值

标高偏差, mm

中心线位置偏差, mm

纵向

横向

垂直偏差, mm

0°/180°

90°/270°

水平偏差, mm/m

纵向

横向





备注或附图:

检验结论:

建设 /监理单位 总承包单位 施工单位

专业工程师:





日期: 年 月 日

专业工程师:





日期: 年 月 日

施工班组长:

质量检查员:

专业工程师:

日期: 年 月 日



SH/T 3503— 2017

72

SH/T 3503— J302 轴对中记录

工程名称:

单位工程名称:

设备名称 设备位号

联轴器型式 测量方式 □双表□三表□其他



检测部位示意图单位: mm

联轴



编号

径向位移 轴向倾斜 端面间隙

百分表固



位置







实 测值 允





百分

表回

转直



实测值 允许



实测

值 a

1 a2 a3 a4 b1 b2 b3 b4











注 1:联轴器编号从驱动机侧开始顺序编号。

注 2:□有□无, 实际轴对中测量曲线图附后。

结论:

建设 /监理单位 总承包单位 施工单位

专业工程师:





日期: 年 月 日

专业工程师:





日期: 年 月 日

施工班组长:

质量检查员:

专业工程师:

日期: 年 月 日



SH/T 3503— 2017

73

SH/T 3503— J303 机组轴对中记录

工程名称:

单位工程名称:

设备名称 设备位号

驱动机轴侧



检测部位示意图单位: mm

联轴器编号 A1—B1 A2—B2 A3—B3

联轴器型式

轴端距

L1、 L2、

L3

允许值

实测值

检测部位 A1 B1 A2 B2 a

1 a2 a3 a4 b1 b2 b3 b4 a1 a2 a3 a4 b1 b2 b3 b4

允许值

实测值

检测部位 A3 B3 a

1 a2 a3 a4 b1 b2 b3 b4 a1 a2 a3 a4 b1 b2 b3 b4

允许值

实测值

注 1:联轴器编号从驱动机侧开始顺序编号。

注 2:□有□无, 实际轴对中测量曲线图附后。

结论:

建设 /监理单位 总承包单位 施工单位 设备制造厂

专业工程师:





日期: 年 月 日

专业工程师:





日期: 年 月 日

施工班组长:

质量检查员:

专业工程师:

日期: 年 月 日

现场代表:





日期: 年 月 日

SH/T 3503— 2017

74

SH/T 3503— J304

空冷式换热器风机安装

检验记录

工程名称:



单位工程名称:

设备名称 设备位号 设备型号

风筒直径 mm 叶片数量 皮带型号

项目 允许值

实测值

1 2 3 4 5 6

叶片安装角度, (o)

叶尖圆周水平高低差, mm

风机轴垂直度偏差, mm

主、从动轴皮带轮中心面

偏移 量, mm

主、从动轴皮带轮两轴平行度

皮带

张紧度

施加载荷 W, kN

切边长度 L, mm

中点挠度 f, mm

风筒内壁与风扇叶尖间距 , mm

实测值

0? 45? 90? 135? 180? 225? 270? 315?







注:表中 “实测值 ”栏中的数字 1~ 6,为风机叶片编号。

检验结论:

建设 /监理单位 总承包单位 施工单位

专业工程师:





日期: 年 月 日

专业工程师:





日期: 年 月 日

施工班组 长:

质量检查员:

专业工程师:

日期: 年 月 日



SH/T 3503— 2017

75

SH/T 3503— J305 机器组装质量确认记录

工程名称:



单位工程名称:

设备名称 设备位号





















































建设 /监理单位 总承包单位 施工单位 设备制造厂

专业工程师:





日期: 年 月 日

专业工程师:





日期: 年 月 日

施工班组长:

质量检查员:

专业工程师:

日期: 年 月 日

现场代表:





日期: 年 月 日

SH/T 3503— 2017

76



SH/T 3503— 2017

77



SH/T 3503— 2017

78

SH/T 3503— J308

往复式压缩机

曲柄臂间距检查 记录

工程名称:



单位工程名称:

设备名称 设备位号

1



1— 内径千分尺

检测部位示意图 (单位: mm)

气缸

列数 允许值

实测值

最大偏差值 /行程

0° 90° 180° 270°













备注:

结论:

建设 /监理单位 总承包单位 施工单位 设备制造厂

专业工程师:





日期: 年 月 日

专业工程师:





日期: 年 月 日

施工班组长:

质量检查员:

专业工程师:

日期: 年 月 日

现场代表:





日期: 年 月 日

1

SH/T 3503— 2017

79

SH/T 3503— J309

往复式压缩机主轴轴线

与中体滑道轴线垂直度

检查记录

工程名称:



单位工程名称:

设备名称 设备位号



1— 内径千分尺; 2— 钢丝线

检测部位示意图

气缸

列数

测量数据

mm

垂直度偏差

mm/m

轴向窜量

mm

A B C D E F G H 允许值 实测值 允许值 实测值















备注:



结论:



建设 /监理单位 总承包单位 施工单位 设备制造厂

专业工程师:





日期: 年 月 日

专业工程师:





日期: 年 月 日

施工班组长:

质量检查员:

专业工程师:

日期: 年 月 日

现场代表:





日期: 年 月 日

SH/T 3503— 2017

80

SH/T 3503— J310

往复式压缩机

主轴瓦与推力轴瓦间隙

检查记录

工程名称:



单位工程名称:

设备名称 设备位号





检测部位示意图 ( 单位: mm)

编号

主轴承 推力轴承

顶间隙 a 侧间隙 b1/ b2

编号 允许值

实测值

允许值 实测值 允许值

实测值

A B

b1 b2











备注:

结论:

建设 /监理单位 总承包单位 施工单位 设备制造厂

专业工程师:





日 期: 年 月 日

专业工程师:





日期: 年 月 日

施工班组长:

质量检查员:

专业工程师:

日期: 年 月 日

现场代表:





日期: 年 月 日



SH/T 3503— 2017

81

SH/T 3503— J311

往复式压缩机

十字头与中体滑道间隙

检查 记录(卧式)

工程名称:



单位工程名称:

设备名称 设备位号







检测部位示意图 ( 单位: mm)

气缸

级数 允许值

实测值

A1 A2 A3 A4 A5 A6 A7 A8











备注:







结论:







建设 /监理单位 总承包单位 施工单位 设备制造厂

专业工程师:





日期: 年 月 日

专业工程师:





日期: 年 月 日

施工班组长:

质量检查员:

专业工程师:

日期: 年 月 日

现场代表:





日期: 年 月 日

SH/T 3503— 2017

82



SH/T 3503— J312

往复式压缩机

十字头与中体滑道间隙

检查 记录(立式)

工程名称:



单位工程名称:

设备名称 设备位号





检测部位示意图 ( 单位: mm)

气缸

级数 允许值

实测值

A1 A2 A3 A4 A5 A6 A7 A8 A9 A10 A11 A12













备注:



结论:



建设 /监理单位 总承包单位 施工单位 设备制造厂

专业工程师:





日期: 年 月 日

专业工程师:





日期: 年 月 日

施工班组长:

质量检查员:

专业工程师:

日期: 年 月 日

现场代表:





日期: 年 月 日

SH/T 3503— 2017

83



SH/T 3503— J313 往复式压缩机连杆

组装 记录

工程名称:



单位工程名称:

设备名称 设备位号



大头轴瓦小头轴瓦

检测部位示意图 ( 单位: mm)



气缸

级数

大头轴瓦间隙 小头轴瓦间隙

A B C A B C

允许值 实测值 允许值 实测值 允许值 实测值 允许值 实测值 允许值 实测值 允许值 实测值









连杆螺栓连接

气缸

级数

螺栓

直径

mm

螺栓伸长量( mm) 力矩扳手拧紧

力矩( kN/m)

液压扳手液

压力 ( MPa)

允许值

1 2

紧前

长度

紧后

长度

实测伸

长量

紧前

长度

紧后

长度

实测伸

长量 允许值 实测值 允许值 实测值









备注:



结论:



建设 /监理单位 总承包单位 施工单位 设备制造厂

专业工程 师:





日期: 年 月 日

专业工程师:





日期: 年 月 日

施工班组长:

质量检查员:

专业工程师:

日期: 年 月 日

现场代表:





日期: 年 月 日

SH/T 3503— 2017

84

SH/T 3503— J314 往复式压缩机

气缸余隙检查 记录

工程名称:



单位工程名称:

设备名称 设备位号





检测部位示意图 ( 单 位: mm)

气缸级数

L1 L2

允许值 实测值 允许值 实测值









备注:







结论:







建设 /监理单位 总承包单位 施工单位 设备制造厂

专业工程师:







日期: 年 月 日

专业工程师:







日期: 年 月 日

施工班组长:

质量检查员:

专业工程师:



日期: 年 月 日

现场代表:







日期: 年 月 日

SH/T 3503— 2017

85

SH/T 3503— J315

往复式压缩机

活塞与气缸圆周间隙

检查 记录

工程名称:



单位工程名称:

设备名称 设备位号





检测部位示意图 ( 单位: mm)

气缸

级数

A B C D

允许值 实测值 允许值 实测值 允 许值 实测值 允许值 实测值













备注:



结论:



建设 /监理单位 总承包单位 施工单位 设备制造厂

专业工程师:





日期: 年 月 日

专业工程师:





日期: 年 月 日

施工班组长:

质量检查员:

专业工程师:

日期: 年 月 日

现场代表:





日期: 年 月 日

SH/T 3503— 2017

86

SH/T 3503— J316 往复式压缩机

活塞环安装 记录

工程名 称:



单位工程名称:

设备名称 设备位号



活塞环侧间隙活塞环沉入间隙

检测部位示意图 ( 单位: mm)

气缸级数

活塞环 工作位置( C) 侧间隙( A) 沉入间隙( B)

编号 材质 允许值 实测值 允许值 实测值 允许值 实测值















注:当活塞环为铸铁材料时,在安装前按设计文件规定检查其倒角和圆角。

备注:

结论:



建设 /监理单位 总承包单位 施工单 位 设备制造厂

专业工程师:





日期: 年 月 日

专业工程师:





日期: 年 月 日

施工班组长:

质量检查员:

专业工程师:

日期: 年 月 日

现场代表:







日期: 年 月 日

SH/T 3503— 2017

87

SH/T 3503— J317 往复式压缩机

填料函各部间 隙检查记 录

工程名称:



单位工程名称:

设备名称 设备位号

填料型式 □锥形填料□平填料





锥形填料平填料



检测部位示意图 ( 单位: mm)

检测部位 A B C D

允许值

实 测



一级缸

二级缸

三级缸

四级缸

备注:



结论:



建设 /监理单位 总承包单位 施工单位 设备制造厂

专业工程师:





日期: 年 月 日

专业工程师:





日期: 年 月 日

施工班组长:

质量检查员:

专业工程师:

日期: 年 月 日

现场代表:





日期: 年 月 日

SH/T 3503— 2017

88

SH/T 3503— J318-1 机器单机试车记录

工程名称:



单位工程名称:

设备名称 位号 工作介质

驱动机种类 转 速 r/min 试车介质

试车类别 □空负荷□负荷 环境温度 ℃ 试车日期 年 月 日

连续运转时间 h 启动电流 A 启动时刻

检查项目 设计值 /

允许值

实测值

运行记录时刻

压力

MPa

进口

出口

轴承温度



联轴器侧

非联轴器侧







轴承

温度



联轴器侧

非联轴器侧

电压, V

电流, A

汽压, MPa

蒸汽流量, kg/h

润滑油 压力, MPa 温度, ℃

冷却水 压力, MPa 温度, ℃

振动速度

(振动幅

度)

mm/s(μ m)

轴向

水平

竖直

保安联锁系统试验情况:

试车结论:

建设 /监理单位 总承包单位 施工单位 设备制造厂

专业工程师 :





日期: 年 月 日

专业工程师:





日期: 年 月 日

施工班组长:

质量检查员:

专业工程师:

日期: 年 月 日

现场代表:





日期: 年 月 日

SH/T 3503— 2017

89

SH/T 3503— J318-2 ________设备单机试车记录

工程名称:



单位工程名称:

设备名称 位号 工作介质

驱动机种类 转速 r/min 试车介质

试车类别 □空负荷□负荷 环境温度 ℃ 试车日期 年月日

连续运转

时间 h 启动电流 A 启动时刻

检查项 目 设计值 /

允许值

实测值

运行记录时刻

































保安联锁系统试验情况:

试车 结论:

建设 /监理单位 总承包单位 施工单位 设备制造厂

专业工程师:







日期: 年 月 日

专业工程师:







日期: 年 月 日

施工班组长:

质量检查员:

专业工程师:

日期: 年 月 日

现场代表:







日期: 年 月 日

SH/T 3503— 2017

90



SH/T 3503— J319 机组试车条件确认记录

工程名称:



单位工程名称:

设备名称 设备位号

设备型号 能力

驱动机种类 转速 r/min

确认项目 技术要求

确认人

确认日期 建设 /监

理单位

总承包

单位

施工

单位

设备制

造厂

设备本体拆检 拆检、回装完成,记录符合规范要求



辅助系统 检查合格

油管路系统 冲洗和压力试验完成,记录符合规范要求

循环或润滑油 符合要求

电气设施 安装完成,调试合格,记录符合规范要求

仪表联锁、控制系



安装完成,系统调校合格,

记录符合规范要求

工艺管道系统

安装完成,压力试验、吹扫

(清洗)合格,记录符合规

范要求



机组试车方案 试车程序、措施、质量验收要求明确

生产 配套工艺及

操作条件 按试车方案要求准备完毕

建设单位试车负责人:

试车条件确认 具备试车条件

试车总负责人:



SH/T 3503— 2017

91

SH/T 3503— J320-1

往复式压缩机

试车记录

共()页第()页

工程名称:



单位工程名称:

设备名称 设备位号

设备型号 工作介质

试车类别 □空负荷□负荷 试车介质 环境温度 ℃

驱动机种类 转速 r/min 启动电流 A

连续运转时间 h 试车日期 年 月 日 启动时刻

检查项目 设计值 /

允许值

实测值

运 行记录时刻







入口压力, MPa

入口温度, ℃

出口温度, ℃







入口压力, MPa

入口温度, ℃

出口温度, ℃

振动速度

(振动幅度 )

mm/s(μm)

轴向

水平

竖直

轴承

温度



前轴承

后轴承

止推轴承











压力, MPa

温度, ℃





压力, MPa

温度, ℃

填料函温度, ℃



建设 /监理单位 总承包单位 施工单位 设备制造厂

专业工程师:





日期: 年 月 日

专业工程师:





日期: 年 月 日

施工班组长:

质量检查员:

专业工程师:

日期: 年 月 日

现场代表:





日期: 年 月 日



SH/T 3503— 2017

92

SH/T 3503— J320-2 往复式压缩机

试车记录 (续)

工程名称:



单位工程名称:

检查项目 设计值 /

允许值

实测值

运行记录时刻











压力, MPa

温度, ℃





压力, MPa

温度, ℃

填料函温度, ℃















压力, MPa

温度, ℃





压力, MPa

温度, ℃

填料函温度, ℃















压力, MPa

温度, ℃





压力, MPa

温度, ℃

填料函温度, ℃





保安联锁系统试验情况:

试车后检查情况:

试车结论:

SH/T 3503— 2017

93



SH/T 3503— J321-1

离心式压缩机

试车记录

共()页第()页

工程名称:



单位工程名称:

设备名称 设备位号

设备型号 工作介质 试车介质

驱动机种类 转速 r/min 启动电流 A

试车类别 □空负荷□负荷 环境温度 ℃ 试车日期 年月日

连续运转时间 h 停机惰走时间 s 启动时刻

检查项目 设计值 /

允许值

实测值

运行记录时刻













流量, Nm3/h

压力, MPa

温度, ℃





压力, MPa

温度, ℃

轴承

温度



前轴承

后轴承

止推轴承

振动速

度 (振

动幅

度 )

mm/s

(μm)







水平

竖直

轴向







水平

竖直

轴向

轴 位移值, mm

建设 /监理单位 总承包单位 施工单位 设备制造厂

专业工程师:





日期: 年 月 日

专业工程师:





日期: 年 月 日

施工班组长:

质量检查员:

专业工程师:

日期: 年 月 日

现场代表:





日期: 年 月 日

SH/T 3503— 2017

94



SH/T 3503— J321-2 离心式压缩机

试车记录 (续 1)

工程名称:



单位工程名称:

检查项目 设计值 /

允许值

实测值

运行记录时刻















流量, Nm3/h

压力, MPa

温度, ℃





压力, MPa

温度, ℃

轴承

温度



前轴承

后轴承

止推轴承

振动速

度 (振

动幅

度 )

mm/s

(μm)







水平

竖直

轴向







水平

竖直

轴向

轴位移值, mm













流量, Nm3

压力, MPa

温度, ℃





压力, MPa

温度, ℃

轴承

温度



前轴承

后轴承

止推轴承

振动速

度 (振

动幅

度 )

mm/s

(μm)







水平

竖直

轴向







水平

竖直

轴向

轴位移值 , mm

SH/T 3503— 2017

95

SH/T 3503— J321-3 离心式压缩机

试车记录 (续 2)

工程名称:



单位工程名称:

检查项目 设计值 /

允许值

实测值

运行记录时刻







压力, MPa

入口温度, ℃

出口温度, ℃

密封油压, MPa

动力油压, MPa

气封压力, MPa

油冷

却器

油入口温度, ℃

油出口温度, ℃



















保安联锁系统试验情况:





试车后检查情况:





试车结论:





SH/T 3503— 2017

96

SH/T 3503— J322-1

汽轮机 /燃气轮机

试车记录

共()页第()页

工程名称:



单位工程名称:

设备名称 设备位号

设备型号 转速 r/min

试车类别 □空负荷□负荷 试车日期 年月日 启动时刻

连续运转时间 h 环境温度 ℃ 试车介质

最低工作转速 r/min 额定转速 r/min 临界转速 r/min

超速跳闸整定值 r/min 惰走时间 s

检查项目 设计值 /

允许值

实测值

运行记录时刻

转速, r/min





压力, MPa

温度, ℃





压力, MPa

温度, ℃

冷凝器真空度, MPa

轴承

温度



前轴承

后轴承

止推轴承

振动

速度

(振动

幅度 )

mm/s

(μm)







轴向

水平

竖直







轴向

水平

竖直

轴位移值, mm

控制油压, MPa

建设 /监理单位 总承包单位 施工单位 设备制造厂

专业工程师:





日期: 年 月 日

专业工程师:





日期: 年 月 日

施工班组长:

质量检查员:

专业工程师:

日期: 年 月 日

现场代表:





日期: 年 月 日

SH/T 3503— 2017

97

SH/T 3503— J322-2 汽轮机 /燃气轮机

试 车记录 (续)

工程名称:



单位工程名称:

检查项目 设计值 /

允许值

实测值

运行记录时刻







入口压力, MPa

入口温度, ℃

出口温度, ℃







进水压力, MPa

回水压力, MPa

进水温度, ℃

回水温度, ℃













测点位置示意图:



超速脱扣试验:

保安联锁系统试验:

试车后检查:

试车结论:

SH/T 3503— 2017

98



SH/T 3503— J323 电动机试车记录

工程名称:



单位工程名称:

设备名称 设备位号

电动机型号 转速 r/min 试车类别 □空负荷□负荷

试车日期 年月日 启动时刻 环境温度 ℃

连续运转时间 h 惰走时间 s 启动电流 A

检查项目 设计值 /

允许值

实测值

运行记录时刻

电压 , V

电流, A

轴承

温度



联轴器侧

非联轴器侧

振动速

度 (振

动幅

度 )

mm/s

(μm)

联轴器

侧轴承

轴向

水平

竖直

非联

轴器

侧轴承

轴向

水平

竖直







入口压力, MPa

入口温度, ℃

出口温度, ℃







入口压力, MPa

入口温度, ℃

出口温度, ℃

试车结论:

建设 /监理单位 总承包单位 施工单位 设备制造厂

专业工程师:





日期: 年 月 日

专业工程师:





日期: 年 月 日

施工班组长:

质量检查员:

专业工程师:

日期: 年 月 日

现场代表:





日期: 年 月 日

注 :本表用于 200kW及以上电动机驱动主机时,电动机运行情况的记录。

SH/T 3503— 2017

99



SH/T 3503— J324 变速器试车记录

工程名称:



单位工程名称:

设备名称 设备位号 设备型号

变速器类别 环境温度 ℃ 试车类别 □空负荷□负荷

连续运转时间 h 试车日期 年 月 日 启动时刻

检查项目 设计值 /

允许值

实测值

运行记录时刻











输入轴 前轴承 后轴承

中间轴

1

前轴承

后轴承

中间轴

2

前轴承

后轴承

输出轴 前轴承 后轴承

振动

速度

(振

动幅

度 )

mm/s

(μm)







前轴



水平

竖直

后轴



水平

竖直







前轴



水平

竖直

后轴



水平

竖直





试车结 论:

建设 /监理单位 总承包单位 施工单位 设备制造厂

专业工程师:





日期: 年 月 日

专业工程师:





日期: 年 月 日

施工班组长:

质量检查员:

专业工程师:

日期: 年 月 日

现场代表:





日期: 年 月 日



SH/T 3503— 2017

100

SH/T 3503— J325 釜类设备安装检验记录

工程名称:



单位工程名称:

设备名称 设备位号

项目 允许值 mm 实测值 mm

釜体标高偏差

釜体方位偏差

釜体垂直偏差

0° /180°

90° /270°

釜体上口法兰面

水平偏差

0° /180°

90° /270°

搅拌轴垂直偏差

0° /180°

90° /270°

搅拌轴末端径向跳动值

搅拌轴轴向窜量

搅拌轴轴封处轴的径向位移偏差

齿轮箱内部清洁度确认:

润滑系统确认:

冷却系统确认:

密封系统确认:

检验结论:

建设 /监理单位 总承包单位 施工单位

专业工程师:





日期: 年 月 日

专业工程师:





日期: 年 月 日

施工班组长:

质量检查员:

专业工程师:

日期 : 年 月 日

SH/T 3503— 2017

101



SH/T 3503— J326 立式设备安装检验记录

工程名称:



单位工程名称:

设备名称 设备位号

规格



注: h 为两测点间的距离,取 h= mm。

单位: mm

项目 测量部位 允许值 实测值 项目 测量部位 允许值 实测值

标高

偏差

0o

支座中心

位置偏差

0o

90o 90o

180o 180o

270o 270o

垂直

偏差

0o/180o

方位偏差 0o 90o/270o

检验结论:

建设 /监理单位 总承包单位 施工单位

专业工程师:





日期: 年 月 日

专业工程师:





日期: 年 月 日

施工班组长:

质量检查员:

专业工程师:

日期: 年 月 日

SH/T 3503— 2017

102



SH/T 3503— J327 卧式设备安装检验记录

工程名称:



单位工程名称:

设备名称 设备位号

规格



注 1:图中 B、 C、 D、 E 为设备筒体水平度测量基准点。

注 2:设备安装标高测量值为设备基础上的标高基准线到设备支座底板下表面的距离。

注 3:轴向水平偏差应低向排液口方向。

注 4: L 为两端测点间的距离,取 L= mm。

单位: mm

项目 测量部位 允许值 实测值 项目 测量部位 允许值 实测值

支座中心

位置偏差

纵向 纵向水平

偏差

B-C

横向 D-E

支座标高

偏差

滑动端 横向水平

偏差

B-D

固定端 C-E

滑动端鞍座滑动裕量 滑动端螺母松动核验结果

注:滑动 端地脚螺栓的双螺母应在设备配管完成后松开,保持与支座板一定间隙后锁紧。

检验结论:

建设 /监理单位 总承包单位 施工单位

专业工程师:





日期: 年 月 日

专业工程师:





日期: 年 月 日

施工班组长:

质量检查员:

专业工程师:

日期: 年 月 日

SH/T 3503— 2017

103

SH/T 3503— J328 塔盘安装检验记录

工程名称:



单位工程名称:

设备名称 设备位号

规格 塔盘型式

检查项目,

mm

塔盘水平

偏差

塔盘支撑件 溢流堰 降液板与受液盘 其他

间距 水平度 水平偏差 高度偏差 垂直距离 水平距离

允许值

塔盘编号 实测值 实测值 实测值 实测值 实测值 实测值 实测值

1











2

















检验结论:

说明:

建设 /监理单位 总承包单位 施工单 位

专业工程师:





日期: 年 月 日

专业工程师:





日期: 年 月 日

施工班组长:

质量检查员:

专业工程师:

日期: 年 月 日



SH/T 3503— 2017

104

SH/T 3503— J329 设备填充检验记录

工程名称:



单位工程名称:

设备名称 设备位号

规格

分段编号 填料名称 填料规格

填充高度

m

填充量

m3 备注

设计值 实际值 设计值 实际值

































检验结论:

建设 /监理单位 总承包单位 施工单位

专业工程师:





日期: 年 月 日

专业工程师:





日期: 年 月 日

施工班组长:

质量检查员:

专业工程师:

日期: 年 月 日



SH/T 3503— 2017

105

SH/T 3503— J330 反应 /沉降器

附件安装检验记录

工程名称:



单位工程名称:

设备名称 设备位号

项目 允许值 实测最大值







与壳体同心度偏差 mm

开孔方位偏差 mm

水平偏差 mm

提升管垂直度 mm

待生催化剂立管垂直度 mm

旋风分离器系统 允许值 分离器

1 2 3 4 5 6 7 8

一级分离器入口标高偏差 mm

分离器垂直度

mm

一级

二级

翼阀安 装角度偏差



一级 允许值 实测值

二级 允许值 实测值

检查项目 安装要求 检查结果

进料喷嘴 安装角度、尺寸符合设计文件要求,油嘴无堵塞

吊杆螺母与检修平台支持角钢螺母 留出膨胀间隙,锁紧螺母锁紧

拉杆的焊接垫板 留有通气孔

分离器料腿、翼阀 通畅无异物

人字 /环形挡板 符合设计文件要求

检验结论:

建设 /监理单位 总承包单位 施工单位

专业工程师:





日期: 年 月 日

专业工程师:





日期: 年 月 日

施工班组长:

质量检查员:

专业工程师:

日期: 年 月 日



SH/T 3503— 2017

106

SH/T 3503— J331 再生器

附件安装检验记录

工程名称:



单位工程名称:

设备名称 设备位号

项目 允许值 实测最大值

环形

分布管

水平偏差 mm

相邻盘管间距偏差 mm

树枝状

分布管

标高偏差 mm

水平度 mm

空气环 中心偏差 mm 水平度 mm

集气室 与壳体同心度偏差 mm 开孔方位偏差 mm

旋风分离器系统 允许值 分离器 /翼阀

1 2 3 4 5 6 7 8

一级分离器入口标高偏差 mm

分离器垂 直度

mm

一级

二级

翼阀安 装角度偏差



一级 允许值 实测值

二级 允许值 实测值

检查项目 安装要求 检查结果

吊杆螺母与检修平台支持角钢螺母 留有膨胀间隙,加背帽锁紧

料腿拉杆处或垫板焊缝 留有通气孔

分离器料腿、翼阀 通畅、无异物

检验结论:

建设 /监理单位 总承包单位 施工单位

专业工程师:





日期: 年 月 日

专业工程师:





日期: 年 月 日

施工班组长:

质量检查员:

专业工程师:

日期: 年 月 日



SH/T 3503— 2017

107

SH/T 3503— J332 立式圆筒形储罐

组装质量检验记录

工程名称:



单位工程名称:

设备名称 设备位号 结构型式

规格 容积 m3 材质

项目 允许值 mm 实测最大值 mm 检查点数 合格点数 合格率 %

罐壁几

何尺寸

高度偏差

罐底圈水平半径偏差

垂直度

罐壁

导向支柱

量油管

内浮顶环形边缘侧板

局 部 凹

凸度偏



罐底

罐壁内表面

拱顶

浮顶

内浮顶内浮盘

单盘板

备注:

检查项目与要求 检查结果

管口标高符合设计文件要求

管口方位偏差符合设计文件和规范要求

法兰、接管规格和接管外伸长度偏差符合设计文件和规范要求

检验结论:

建设 /监理单位 总承包单位 施工单位

专业工程师:





日期: 年 月 日

专业工程师:





日期: 年 月 日

施工班组长:

质量检查员:

专业工程师:

日期: 年 月 日



SH/T 3503— 2017

108

SH/T 3503— J333-1 立式圆筒形储罐

罐底真空试验记录

工程名称:



单位工程名称:

设备名称 设备位号 结构型式

规格 容积 m3 材质

试验日期

试验方法 :



真空度 kPa



试验记录 :

试验结论 :

建设 /监理单位 总承包单位 施工单位

专业工程师:





日期: 年 月 日

专业工程师:





日期: 年 月 日

施工班组长:

质量检查员:

专业工程师:

日期: 年 月 日

SH/T 3503— 2017

109

SH/T 3503— J333-2 立式圆筒形储罐开孔

补强圈气密性试验记录

工程名称:



单位工程名称:

设备名称 设备位号 结构型式

规格 容积 m3 材质

试验日期 :

试验的管口号:



试验方法描述 :

充气 kPa,用肥皂水检查。



试验记录:

















试验结论:

建设 /监理单位 总承包单位 施工单位

专业工程师:





日期: 年 月 日

专业工程师:





日期: 年 月 日

施工班组长:

质量检查员:

专业工程师:

日期: 年 月 日



SH/T 3503— 2017

110

SH/T 3503— J333-3 立式圆筒形储罐浮顶 /船舱

严密性试验记录

工程名称:



单位工程名称:

设备名称 设备位号 结构型式

规格 容积 m3 材质

试验日期

试验项目:□ 船舱焊缝严密性试验 □ 船舱底板严密性试验

□ 船舱气密性试验 □ 单盘板严密性试验







试验方法描述: □ 真空度 kPa, □ 用肥皂水检查,充气 kPa, □ 用肥皂水检查; □上水试验



试验记录:























试验结论:



建设 /监理单位 总承 包单位 施工单位

专业工程师:





日期: 年 月 日

专业工程师:





日期: 年 月 日

施工班组长:

质量检查员:

专业工程师:

日期: 年 月 日

SH/T 3503— 2017

111



SH/T 3503— J333-4 立式圆筒形储罐

总体试验记录

工程名称:



单位工程名称:

设备名称 设备位号 结构型式

规格 容积 m3 材质

项目 试验方法描述

罐底 严密性试验

罐壁 严密性和强度试验

固定顶

严密性和强度试验 正压 kPa,用肥皂水检查

稳定性试验 负压 kPa,观察检查

浮顶 /内浮顶升降试验 充水试验法

中央排水管试漏 充水时观察检查

试验记录:











试验结论:





建设 /监理单位 总承包单位 施工单位

专业工程师:





日期: 年 月 日

专业工程师:





日期: 年 月 日

施工班组长:

质量检查员:

专业工程师:

日期: 年 月 日



SH/T 3503— 2017

112

SH/T 3503— J334 湿式气柜组装质量检验记录

工程名称:



单位工程名称:

设备名称 设备位号 结构型式

规格 容积 m3 材质

项目 允许值 mm 实测最大值 mm 备注

底板 局部凹凸变形

钟罩拱顶

角钢圈

直径偏差

水平偏差

钟罩壁板

直径偏差

局部凹凸变形

水槽壁 最上圈与最下圈直径偏差

上、下水封

立板垂直偏差

立板直径偏差

水平板平整度

检查项目与要求 检查结果

中节壁板直径偏差和局部凹凸变形符合设计文件和规范要求

立柱中心沿圆周方向偏差和两立柱间距偏差符合设计文件和规范要求

直升导轨径向偏差和切向偏差符合设计文件和规范要求

两相邻直 升导轨周向间距偏差符合设计文件和规范要求

两相邻螺旋导轨平行偏差和与基准圆径向偏差符合设计文件和规范要求

检验结论:

建设 /监理单位 总承包单位 施工单位

专业工程师:





日期: 年 月 日

专业工程师:





日期: 年 月 日

施工班组长:

质量检查员:

专业工程师:

日期: 年 月 日



SH/T 3503— 2017

113

SH/T 3503— J335-1 湿式气柜底板

严密性试验记录

工程名称:



单位工程名称:

设备名称 设备位号 结构型式

规格 容积 m3 材质

试验日 期

试验方法描述 : 真空度 kPa, 用肥皂水检查 。







试验记录 :





























试验结论 :







建设 /监理单位 总承包单位 施工单位

专业工程师:





日期: 年 月 日

专业工程师:





日期: 年 月 日

施工班组长:

质量检查员:

专业工程师:

日期: 年 月 日



SH/T 3503— 2017

114

SH/T 3503— J335-2 湿式气柜开孔

补强圈气密性试验记录

工程名称:



单位工程名称:

设备名称 设备位号 结构型式

规格 容积 m3 材质

试验日期 :

试验的管口号:





试验方法描述 :

充气 kPa,用肥皂水检查。

试验记录:













试验结论:



建设 /监理单位 总承包单位 施工单位

专业工程师:





日期: 年 月 日

专业工程师:





日期: 年 月 日

施工班组长:

质量检查员:

专业工程师:

日期: 年 月 日



SH/T 3503— 2017

115

SH/T 3503— J335-3 湿式气柜水槽

严密性试验记录

工程名称:



单位工程名称:

设备名称 设备位号 结构型式

规格 容积 m3 材质

试验日期 :

试验方法描述 : 注水试验法。











试验记录:























试验结论:









建设 /监理单位 总承包单位 施工单位

专业工程师:





日期: 年 月 日

专业工程师:





日期: 年 月 日

施工班组长:

质量检查员:

专业工程师:

日期: 年 月 日



SH/T 3503— 2017

116

SH/T 3503— J335-4 湿式气柜整体试验记录

工程名称:



单位工程名称:

设备名称 设备位号 结构型式

规格 容积 m3 材质

项目 试验方法 试验日 期 结果

钟罩和中节升

降以及气密性

试验

罐壁严密性 充气 kPa,用肥皂水检查

各塔节升降状况 观察检查

气柜快速升降

试验

上下水封扣合情况 观察检查

钟罩顶板严密性 充气 kPa,用肥皂水检查

导轮与导轨接触情况 观察检查

配重平衡情况 观察检查

升降次数 记数检查

升降速度 测量检查

安全限位装置试验 观察检查

备注:

试验结论:









建设 /监理单位 总承包单位 施工单位

专业工程师:





日期: 年 月 日

专业工程师:





日期: 年 月 日

施工班组长:

质量检查员:

专业工程师:

日期: 年 月 日



SH/T 3503— 2017

117

SH/T 3503— J336 干式气柜组装质量

检验记录

工程名称:



单位工程名称:

设备名称 设备位号 结构型式

规格 容积 m3 材质

项目 允许值 mm 实测最大值 mm 备注

立柱

标高偏差

间距偏差

垂直度 周向 径向

柜体 垂直度 圆度

活塞围栏顶部外围型钢与 T围栏下端内侧型钢间的

尺寸偏差

T围栏顶部型钢外缘与壁板间的尺寸偏差

柜顶

外周

环板

水平板水平偏差

立板垂直偏差

立柱到外周环板的距离偏差

主梁

主梁轴向偏差

主梁圆顶部高度偏差

拱顶曲率半径偏差

检查项目与要求 检查结果

气柜底板、活塞板、顶板搭接尺寸符合设计文件要求

活塞围栏立柱垂直度、活塞围栏组装后的高度符合设计文件要求

T围栏上下端垂直度、水平度符合设计文件要求

与橡胶密封膜接触部位的焊缝表面打磨光滑,符合规范要求

导向装置、 调平装置、放散装置安装符合设计文件要求,滑轮转动灵活

检验结论:

建设 /监理单位 总承包单位 施工单位

专业工程师:





日期: 年 月 日

专业工程师:





日期: 年 月 日

施工班组长:

质量检查员:

专业工程师:

日期: 年 月 日

SH/T 3503— 2017

118



SH/T 3503— J337-1 干式气柜底板/活塞板/

壁板严密性试验记录

工程名称:



单位工程名称:

设备名称 设备位号 结构型式

规格 容积 m3 材质

试验日期

试验项目: □气柜底板 □活塞板 □贮气部分壁板 □ T围栏底板









试验方法 : □ 真空度 kPa, 用肥皂水检查 ; 充气 kPa,用肥皂水检查;

□煤油试漏法;□





试验记录 :

试验结论 :



建设 /监理单位 总承包单位 施工单位

专业工程师:





日期: 年 月 日

专业工程师:





日期: 年 月 日

施工班组长:

质量检查员:

专业工程师:

日期: 年 月 日

SH/T 3503— 2017

119



SH/T 3503— J337-2 干式气柜开孔

补强圈气密性试验记录

工程名称:



单位工程名称 :

设备名称 设备位号 结构型式

规格 容积 m3 材质

试验日期 :

试验的管口号 :



试验方法 :充气 kPa,用肥皂水检查。



试验记录:



试验结论:



建设 /监理单位 总承包单位 施工单位

专业工程师:





日期: 年 月 日

专业工程师:





日期: 年 月 日

施工班组长:

质量检查员:

专业工程师:

日期: 年 月 日



SH/T 3503— 2017

120

SH/T 3503— J337-3 干式气柜总体试验记录

工程名称:



单位工程名称:

设备名称 设备位号 结构型式

规格 容积 m3 材质

项目 试验方法 试验日期 结果

气柜

试运转

调整

活塞慢速升降试验 观察检查

活塞快速升降试验 观察检查

气柜

严密性

试验

贮气部分壁板严密性 充气 kPa, 用肥皂水检查

活塞板严密性 充气 kPa, 用肥皂水检查

活塞围栏、 T 围栏密

封安装用型钢焊接处

严密性

充气 kPa, 用肥皂水检查

密封装置严密性 充气 kPa, 用肥皂水检查

总体间接气密性试验 容积测定法

升降速度 测量检查

备注:







试验结论:







建设 /监理单位 总承包单位 施工单位

专业工程师:





日期: 年 月 日

专业工程师:





日期: 年 月 日

施工班组长:

质量检查员:

专业工程师:

日期: 年 月 日

SH/T 3503— 2017

121



SH/T 3503— J338 火炬塔架和管筒安装

检验记录

工程名称:



单位工程名称:

设备名称 设备位号

实测项目 允许值 mm 实测值 mm







横截面宽度最大偏差

节间距最大偏差

标高偏差

高度偏 差

垂直偏差 0o 90o







标高偏差

高度偏差

垂直偏差 0o 90o

检查项目与要求 检查结果







两相交腹杆在同一平面内

各杆件汇交于节点

焊缝外观质量符合设计文件和规范要求

焊缝无损检测符合设计文件和规范要求

主肢直线度最大偏差符合规范要求

竖面对角线长度差符合规范要求





焊缝外观质量符合设计文件和规范要求

管筒焊缝无损检测符合设计文件和规范要求

耐热衬里层符合设计文件和规范要 求

检验结论:

建设 /监理单位 总承包单位 施工单位

专业工程师:





日期: 年 月 日

专业工程师:





日期: 年 月 日

施工班组长:

质量检查员:

专业工程师:

日期: 年 月 日



SH/T 3503— 2017

122

SH/T 3503— J339 隔热耐磨衬里质量

检验记录

工程名称:



单位工程名称:

设备名称 设备位号

衬里

结构

序号 检查项目 检查结果 检查日期 检查人员 建设 /监理单位 总承包单位

施工单位

一 衬里材料质量证明文件和复验报告

二 器壁表面处理

三 锚固钉



1 锚固钉布置

2 锚固钉焊接

3 锚固钉与器壁垂直度

4 锚固钉与端板焊接

四 龟甲网



1 龟甲网拼接与安装

2 龟甲网与端板、挡板的焊接

3 龟甲网与插入管的焊接

五 埋入衬里的金属件和插入管外包裹陶瓷纤维纸

六 龟甲网双层衬里

1 隔热层混凝土质量

2 耐磨层混凝土质量

七 龟甲网单层衬里高耐磨混凝土层质量

八 无龟甲网单层衬里隔热耐磨层混凝土质量

九 侧拉圆环型锚固钉双层衬里

1 隔热层混凝土质量

2 耐磨混凝土质量

十 侧拉圆环型锚固钉单层衬里高耐磨层混凝土质量

十一 工程试块

备注:



SH/T 3503— 2017

123

SH/T 3503— J340 热交换设备耐压和泄漏

试验记录

工程名称:



单位工程名称:

设备名称 设备位号 产品编号

设备型号 操作介质 管程:壳程:

设计压力 管程: MPa 壳程: MPa 设计温度 管程: ℃壳程: ℃

压力表编号 压力表精度等级 压力表检定日期

压力表量程 MPa 试验介质温度 ℃ 环境温度 ℃

奥氏体不锈钢设备试验用水氯离子含量 mg/L

试验程序:

试验

类型 试验部位

试验

介质

介质

温度



试验

压力

MPa

保压

时间

min

试验

日期

试验

结果

检查人员

建设 /监理

单位 总承包单位 施工单位





























补充试验:



SH/T 3503— 2017

124

SH/T 3503— J341 设备耐压和泄漏试验记录

工程名称:



单位工程名称:

试验类型 产品编号

设备名称 设备位号

设计压力 MPa 操作介质

设计温度 ℃ 压力表编号

压力表

精度等级 压力表量程 MPa

压力表

检定日期

压力表

表盘直径 mm

环境温度 ℃ 试验介质温度 ℃

奥氏体不锈钢设备试验用水氯离子含量 mg/L

耐压

试验

试验部位 试验介质

试验压力 MPa 保压时间 min

试验结论

□ 有渗漏□无渗漏

□ 有可见异常变形□无可见异常变形

□ 有异常响声□无异常响声

□ 不合格□合格

泄漏

试验

试验部位 试验介质

试验压力 MPa 保压时间 min

试验结论

□ 有渗漏□无渗漏

□ 有可见异常变形□无可见异常变形

□ 有异常响声□无异常响声

□ 不合格□合格

补充

试验



建设 /监理单位 总承包 单位 施工单位

专业工程师:





日期: 年 月 日

专业工程师:





日期: 年 月 日

施工班组长:

质量检查员 :

专业工程师:

日期: 年 月 日



SH/T 3503— 2017

125

SH/T 3503— J342 设备热处理报告

工程名称:





单位工程名称:

设备名称 设备位号 产品编号

热处理部

位 材质 报告编号

热处理方法 试件热处理 状态 试件 数量

热处理工艺要求

升温速度

℃ /h

保温温度



保温时间

h

降温速度

℃ /h

冷却方式及

时间

□同炉热处理 □无试件

热处理温度 -时间曲线





















附:热处理温度 -时间自动记录曲线图

热处理方法简介(包括主要热处理设备、仪表与热电偶数量、隔热层等):

检验结论:

建设 /监理 单位 总承包单位 施工单位 热处理单位

专业工程师:





日期: 年 月 日

专业工程师:





日期: 年 月 日

质量检查员:

专业工程师:



日期: 年 月 日

施工班组长:

质量检查员:

专业工程师:

日期: 年 月 日

SH/T 3503— 2017

126

SH/T 3503— J343 管式炉炉体钢结构安装

检验记录

工程名称:



单位工程名称:

设备名称 设备位号 结构型式

检验项目 允许值 mm 检查 点数 合格 点数 最大偏差 mm 结果 备注

立柱

中心位

置偏差

横向

纵向

垂直偏差

柱底标高偏差

柱身扭曲偏差

直线度偏差

横梁

标高偏差

水平偏差

中心位置偏差

框架 对角线差

圆筒炉

内半径 偏差

圆度

炉壁板

垂直度

平整度

检查项目与要求 检查结果

炉主体结构焊缝外观质量符合设计文件和规范要求

炉壁板焊缝外观质量符合规范要求

梯子、平台板焊缝外观 质量符合规范要求

备注:

建设 /监理单位 总承包单位 施工单位

专业工程师:





日期: 年 月 日

专业工程师:





日期: 年 月 日

施工班组长:

质量检查员:

专业工程师:

日期: 年 月 日

SH/T 3503— 2017

127

SH/T 3503— J344 炉管通球试验记录

工程名称:



单位工程名称:

设备名称 设备位号

炉管规格 炉管材质

通球部位 通球方法

炉管内径 mm 通球材料 mm

炉管弯曲半径 mm 实际球外径 mm

球设计半径 mm 炉管通球数量

通球炉管结构及试验方法简图:



试验结论:



建设 /监理单位 总承包 单位 施工单位

专业工程师:





日期: 年 月 日

专业工程师:





日期: 年 月 日

施工班组长:

质量检查员:

专业工程师:

日期: 年 月 日



SH/T 3503— 2017

128

SH/T 3503— J345 管式炉附件安装质量

检验记录

工程名称:



单位工程名称:

设备名称 设备位号

序号 检查项目 检查要求 检查结果 检查日期

1 燃烧器 内件清洗、组装 符合规范规定

2 燃烧器安装标高、中心位置、水平 /垂 直度 符合设计和规范规定

3 作业门安装标高、中心位置 符合设计和规范规定

4 防爆门安装标高、中心位置 符合设计和规范规定

5 看火孔安装标高、中心位置 符合设计和规范规定

6 清理孔安装标高、中心位置 符合设计和规范规定

7 吹灰器 安装标高、中心位置、 水平度 符合设计和规范规定

8 吹灰器调试 符合规范规定

9 风道系统 安装 符合规范规定

10 烟道 系统安装 符合规范规定

检验结论:

备注:

建设 /监理单位 总承包 单位 施工单位

专业工程师:





日期: 年 月 日

专业工程师:





日期: 年 月 日

施工班组长:

质量检查员:

专业工程师:

日期: 年 月 日

SH/T 3503— 2017

129



SH/T 3503— J346 耐火砖砌筑炉衬质量检验

记录

工程名称:



单位工程名称:

设备名称 设备位号

检验项目 允许值 mm 实测最大值 mm 实测点数 个 合格点数 个 合格率 %

炉墙垂

直度

每米

全高

炉墙

平面度

砌筑墙面

挂砖墙面

拱脚砖下的炉墙上表面

炉 墙水

平度

每米长

全长

线尺寸

偏差

箱式炉长度

箱式炉宽度

箱式炉对角线长度差

圆筒炉膛内半径

拱的跨度

烟道的高度和宽度

圆筒炉墙圆度

膨胀缝宽度偏差

砌体砖缝宽度偏差

烧嘴砖中心位置偏差

烧嘴砖分上下两层时同心度偏差

烧嘴与砌体的膨胀缝尺寸偏差

检查项目 检查要求 检查结果 检查日期

耐火制品质量证明文件 符合设计及规范要 求,复验合格

砌体砖缝布置、拱顶锁砖布置与块数 符合规范要求

表面平整度、砖缝泥浆饱满度 符合规范要求

检验结论:

建设 /监理单位 总承包 单位 施工单位

专业工程师:





日期: 年 月 日

专业工程师:





日期: 年 月 日

施工班组长:

质量检查员:

专业工程师:

日期: 年 月 日

SH/T 3503— 2017

130

SH/T 3503— J347 耐火浇注料炉衬质量检验

记录

工程名称:



单位工程名称:

设备名称 设备位号

检验项目 允许值 mm 实测最大值 mm 实测点数 个 合格点数 个 合格率 %

炉衬厚度偏差

炉衬表面平整度

炉衬表面垂直度

膨胀缝宽度偏差

箱式炉几何尺寸偏差

圆筒炉衬圆度

圆筒炉衬内半径偏差

检查项目 检查要求 检查结果 检查日期

材料质量证明文件及复验报告 符合设计及规范要求,复验合格

炉壁板表面处理 符合规范要求

锚固钉布置、间距、焊接 符合设计及规范要求

钢纤维加入数量 符合规范要求

施工缝型式 符合规范要求

养护环境温 度、养护方法和养

护时间 符合设计及规范要求

表面质量 符合规范要求

工程试块 符合设计及规范要求

备注:

检验结论:

建设 /监理单位 总承包 单位 施工单位

专业工程师:





日期: 年 月 日

专业工程师:





日期: 年 月 日

施工班组长:

质量检查员:

专业工程师:

日期: 年 月 日



SH/T 3503— 2017

131

SH/T 3503— J348

耐火纤维模块炉衬

质量检验记录

工程名称:



单位工程名称:

设备名称 设备位号

检验项目 允许值 mm 实测点数 个 合格点数 个 合格率 % 实测最大值 mm

模块炉衬厚度偏差

炉衬表面平整度

炉衬表面垂直度

检查项目 检查要求 检查结果 检查日期

材料质量证明文件及复验报告 符合设计及规范要求,复验合格

锚固钉布置、间距、焊接 符合设计及规范要求

模块安装 符合设计及规范要求

模块非折叠方向与其他耐火炉衬的处理 符合设计及规范要求

模块捆绑带、包装纸拆除时机 符合设计及规范要求

备注:

检验结论:

建设 /监理单位 总承包 单位 施工单位

专业工 程师:





日期: 年 月 日

专业工程师:





日期: 年 月 日

施工班组长:

质量检查员:

专业工程师:

日期: 年 月 日



SH/T 3503— 2017

132

SH/T 3503— J349-1

设备及构件

焊缝射线检测报告

第页共页

工程名称:



单位工程名称:



委托单位 施工单位 报告编号

检件编号 检件名称 检测标准 合格级别

检件材质 焊接方法 技术等级 检测比例 %

检测时机 显影温度 ℃ 显影时间 min 底片黑度

焊缝规格

mm× mm

透照

方式

线径

编号

焦距

mm

有效

片长

管电压

源能量

管电流

源活度

曝光

时间

设备型号

射源种类

焦点

尺寸 增感方式 胶片牌号







检测批号 焊缝编号 焊工号 焊缝规格 片号 缺陷性质 缺陷定量 评定级别 备注

































评片人:

资格: RT 级

审核人:

资格: RT 级

检测单位:(公章)

报告 日期: 年 月 日

SH/T 3503— 2017

133



SH/T 3503— J349-2

设备及构件

焊缝射线检测报告 (续)

第页共页

工程名称:



单位工程名称:



委托单位 施工单位 报告编号

检测批号 焊缝编号 焊工号 焊缝规格 片号 缺陷性质 缺陷定量 评定级别 备注

















































SH/T 3503— 2017

134



SH/T 3503— J350-1

设备及构件

焊缝超声检测报告

第页 共页

工程名称:



单位工程名称:



委托单位 施工单位 报告编号

检件编号 检件名称 检测标准 合格级别

检件材质 焊接方法 技术等级 检测比例

检测时机 坡口型式 耦合剂 检测灵敏度

探头 试块

检测面 设备型号 表面状态 表面补偿 扫描比例

序号 型号 型号 1 型号 2







检测批号 焊缝编号 焊工号 焊缝规格 探头 序号 缺陷情况或 缺陷示意图编号 评定级别 备注































检测人:

资格: UT 级

审核人:

资格: UT 级

检测单位:(公章)

报告 日期: 年 月 日

SH/T 3503— 2017

135



SH/T 3503— J350-2

设备及构件

焊缝超声检测报告 (续)

第页共页

工程名称:



单位工程 名称:



委托单位 施工单位 报告编号

检测批号 焊缝编号 焊工号 焊缝规格 探头 序号 缺陷情况或 缺陷示意图编号 评定级别 备注





















































SH/T 3503— 2017

136

SH/T 3503— J351-1

设备及构件

焊缝磁粉检测报告

第页共页

工程名称:



单位工程名称:



委托单位 施工单位 报告编号

检件编号 检件名称 检测标准 合格级别

检件材质 焊接方法 检测比例 热处理状态

检测时机 表面状态 电流类型 磁化方法

设备型号 电 /磁极间距 提升力 /电流 磁化时间

磁粉种类 磁悬液浓度 施加方法 灵敏度试片

检测批号 焊 缝编号 焊工号 焊缝规格 检测面 缺陷情况或 缺陷示意图编号 评定 级别 备注





































检测人:



资格: MT 级

审核人:



资格: MT 级

检测单位:(公章)



报告 日期: 年 月 日

SH/T 3503— 2017

137



SH/T 3503— J351-2

设备及构件

焊缝磁粉检测报告 (续)

第页共页

工程名称:



单位工程名称:



委托单位 施工单位 报告编号

检测批号 焊缝编号 焊工号 焊缝规格 检测面 缺陷情况或 缺陷示意图编号 评定 级别 备注























































SH/T 3503— 2017

138

SH/T 3503— J352-1

设备及构件

焊缝渗透检测报告

第页共页

工程名称:



单位工程名称:



委托单位 施工单位 报告编号

检件编号 检件名称 检测标准 合格级别

检件材质 焊接方法 检测比例 热处 理状态

检测时机 表面状态 检测方法 检测灵敏度

渗透温度 观察方法 施加方法 检测试块

渗透时间 显像时间 渗透检测剂牌号

检测批号 焊缝编号 焊工号 焊缝规格 检测面 缺陷情况或 缺陷示意图编号 评定 级别 备注





































检测人:



资格: PT 级

审核人:



资格: PT 级

检测单位:(公章)



报告 日期: 年 月 日

SH/T 3503— 2017

139

SH/T 3503— J352-2

设备及构件

焊缝渗透检测报告 (续)

第页共页

工程名称:



单位工程名称:



委托单位 施工单位 报告编号

检测批号 焊缝编号 焊工号 焊缝规格 检测面 缺陷情况或 缺陷示意图编号 评定 级别 备注





















































SH/T 3503— 2017

140

附 录 D

(规范性附录)

交工技术文件管道安装工程用表

序号 名 称 编号 页次

D.1 管道组成件验证性和补充性检验记录 SH/T 3503—J401 141

D.2 阀门试验确认表 SH/T 3503—J402 142

D.3 弹簧支 /吊架安装检验记录 SH/T 3503—J403 143

D.4 滑动 /固定管托安装检验记录 SH/T 3503—J404 144

D.5 管道补偿器安装检验记录 SH/T 3503—J405 145

D.6 管道系统压力试验条件确认记录 SH/T 3503—J406-1 146

D.7 管道系统压力试验记录 SH/T 3503—J406-2 147

D.8 管道系统泄漏性 /真空试验条件确认与试验记录 SH/T 3503—J407 148

D.9 管道吹扫 /清洗检验记录 SH/T 3503—J408 149

D.10 给排水压力流管道压力试验条件确认与试验记录 SH/T 3503—J409A 150

D.11 给排水压力流管道放水法试验记录 SH/T 3503—J409B 151

D.12 给排水压力流管道注水法试验记录 SH/T 3503—J409C 152

D.13 给排水无压力管道闭水试验条件确认与试验记录 SH/T 3503—J410 153

D.14 管道焊接接头热处理报告 SH/T 3503—J411-1 154

D.15 管道焊接接头热处理报告(续) SH/T 3503—J411-2 155

D.16 管道无损检测结果汇总表 SH/T 3503—J412-1 156

D.17 管道无损检测结果汇总表(续) SH/T 3503—J412-2 157

D.18 管道无损检测数量统计表 SH/T 3503—J413-1 158

D.19 管道无损检测数量统计表(续) SH/T 3503—J413-2 159

D.20 管道 试压包 一览表 SH/T 3503—J414 160

D.21 管道焊接工作记录 SH/T 3503—J415-1 161

D.22 管道焊接工作记录(续) SH/T 3503—J415-2 162

D.23 管道静电接地测试记录 SH/T 3503—J416 163









SH/T 3503— 2017

141

SH/T 3503— 2017

142



SH/T 3503— 2017

143



SH/T 3503— J403 弹簧支 /吊架安装检验记录

工程名称:



单位 工程名称:

管 道编 号 /单线号 支 /吊架 位号 结构型式 位移方向 设计冷态 负荷值 安装冷态负 荷值 检查结果







































备注:

建设 /监理单位 总 承 包 单 位 施 工 单 位

专业工程师:







日期: 年 月 日

专业工程师:







日期: 年 月 日

施工班组长:

质量检查员:

专业工程师:



日期: 年 月 日

SH/T 3503— 2017

144

SH/T 3503— J404 滑动 /固定管托安装检验

记 录

工程名称:



单位 工程名称:

管道编号

/单线号 管托编号 型 式 位移方向

设计位移



安装位移

量 检验结果







































注: 本表用于设计温度 >350℃管道和低于 -29℃管道中,管托有位移要求的滑 动和固定管托的安

装检验。

备注:

建设 /监理单位 总 承 包 单 位 施 工 单 位

专业工程师:





日期: 年 月 日

专业工程师:





日期: 年 月 日

施工班组长:

质量检查员:

专业工程师:

日期: 年 月 日



SH/T 3503— 2017

145



SH/T 3503— 2017

146



SH/T 3503— J406-1 管道系统压力试验条件

确认记录

工程名称:



单位 工程名称:

系统名称 系统编号

检查项目与要求 检查结果

管道安装符合设计文件和规范要求

管道组成 件复验合格

焊接工作记录齐全

无损检测结果符合设计文件和规范要求

热处理结果符合设计文件和规范要求

支、吊架安装正确

合金钢管道材质标记清楚

不参与管道系统试验的安全附件、仪表已按规定拆除或隔离,参与

试压的系统内的阀门全部开启

临时加固措施、盲板位置与标识符合施工方案要求

焊接接头及需要检验的部位未被覆盖

试压用压力表量程、精度等级、检定状态符合规范要求

不锈钢管道试验用水符合规范要求、附水质分析报告

备注:

建设 /监理单位 总 承 包 单 位 施 工 单 位

专业工程师:







日期: 年 月 日

专业工程师:







日期: 年 月 日

施工班组长:

质量检查员:

专业工程师:



日期: 年 月 日

SH

/T35

03



20

××



SH/T 3503— 2017

147

SH/T 3503— J406-2 管道系统压力试验记录

工程名称:



单位 工程名称:

系统名称 系统编号

试验 记 录

管 道编 号

/单线号

设计压力

MPa

设计温度



试验环境

温度



试验

介质

试验介质

温度



试验 压力

MPa

稳压时间

min



































试验结论:

建设 /监理单位 总 承 包 单 位 施 工 单 位

专业工程师:





日期: 年 月 日

专业工程师:





日期: 年 月 日

施工班组长:

质量检查员:

专业工程师:

日期: 年 月 日

SH/T 3503— 2017

148

SH/T 3503— J407 管道系统泄漏性 /真空

试验条件确认与试验记录

工程名称:



单位 工程名称:

系统名称 系统编号

检查项 目 与 要 求 检查结果

管道压力试验合格

压力试验采用的临时法兰、螺栓、垫片等均已更换

未参与压力试验的安全附件及仪表等已安装复位

试验管道系统的阀门已全部开启

试压用压力表、精度等级、检定状态符合规范要求

试验 记 录

管道编号

/单线号

设计 压力

MPa

设计 温 度



试验环境

温度



试验介质

温度



泄漏性试验 真空试验

压力

MPa 介质

压力

MPa 介质



















试验结论:

建设 /监理单位 总 承 包 单 位 施 工 单 位

专业工程师:







日期: 年 月 日

专业工程师:







日期: 年 月 日

施工班组长 :

质量检查员:

专业工程师:



日期: 年 月 日

SH/T 3503— 2017

149

SH/T 3503— J408 管道吹扫 /清洗检验记录

工程名称:



单位 工程名称:

系统名称 系统编号

检 查 项 目 与 要 求 检 查 结 果

管道压力试验合格

不参与吹扫 /清洗的安全附件及仪表等已隔离或拆除

管道系统的阀门已全部开启

不锈钢管道用水符合规范要求

管道编号 /单线号 材质 操作介质 吹扫介质 清洗介质



























注:不锈钢管道用水附水质分析报告。

检验方法及结论:

建设 /监理单位 总 承 包 单 位 施 工 单 位

专业工程师:







日期: 年 月 日

专业工程师:







日期: 年 月 日

记 录 人:

质量检查员:

专业工程师:



日期: 年 月 日

SH/T 3503— 2017

150

SH/T 3503— J409A 给排水压力流管道压力试验

条件确认与试验记 录

工程名称:



单位 工程名称:

系统名称 系统编号

试验环境温度 ℃ 试验介质温度 ℃

检查项 目 与 要 求 检查结果

管道安装完毕,除接口外已按规范规定回填

管道附件、附属构筑物检查合格

管道接口检查合格

管件的管墩、锚固设施的混凝土强度达到设计文件规定

埋地管道的轴线位置、标高、坡度及管基、垫层等复查合格

试验管段端口、敞口已封堵

不参与管道试验的组成件已按规定拆除或隔离

试验系统内阀门均已开启

试压用压力表量程、精度等级、检定状态、表盘直径符合规范要求

试 验 记 录

管 道编 号

/单线号

设计 压力

MPa

设计 温度



试验 压力

MPa 介质

稳压 时间

min











注:附试验管段位置示意图。

试验结论:

建设 /监理单位 总 承 包 单 位 施 工 单 位

专业工程师:





日期: 年 月 日

专业工程师:





日期: 年 月 日

施工班组长:

质量检查员:

专业工程师:

日期: 年 月 日



SH/T 3503— 2017

151

SH/T 3503— J409B 给排水压力流管道放水法

试验 记录

工程名称:



单位 工程名称 :

管道编号

/单线号 执行标准

桩号及地段









管道内径

mm 管材种类 接口种类

试验段长度

m



工作压力

MPa

试验压力

MPa

10min 降压值

MPa

允许渗水量

L/( min· km)





















由 试验压力 降压

0.1MPa 的时间 T1

min

由试验压力放水下降

0.1MPa 的 时间 T2

min

由试验压力放水下降

0.1MPa 的放 水量 W

L

实测渗水量

q

L/( min· km)

1

2

3

折合平均实测渗水量 L/( min· km)

外观检查:

结论:

建设 /监理单位 总 承 包 单 位 施 工 单 位

专业工程师:





日期: 年 月 日

专业工程师:





日期: 年 月 日

施工班组长:

质量检查员:

专业工程师:

日期: 年 月 日



SH/T 3503— 2017

152

SH/T 3503— J409C 给排水压力流管道注水法

试验 记录

工程名称:



单位 工程名称 :

管道编号

/单线号 执行标准

桩号及地段









管道内径

mm 管材种类 接口种类

试验段长度

m



工作压力

MPa

试验压力

MPa

10min 降压值

MPa

允许渗水量

L/( min· km)





















达到试验压力的

时间 T1

min

恒压结束的时间

T2

min

恒压时间 T

min

恒压时间内 补 入

的水量 W

L

实测渗水量

q

L/( min· km)

1

2

3

折合平均实测渗水量 L/( min· km)

外观检查:

结论:

建设 /监理单位 总 承 包 单 位 施 工 单 位

专业工程师:





日期: 年 月 日

专业工程师:





日期: 年 月 日

施工班组长:

质量检查员:

专业工程师:

日期: 年 月 日

SH/T 3503— 2017

153



SH/T 3503— J410 给排水无压力管道闭水试验

条件确认与试验记录

工程名称:



单位 工程名称:



系统名称 系统编号

试验环境温度 ℃ 试验介质温度 ℃

检 查 项 目 与 要 求 检查结果

管道及检查井施工完毕,质量符合规范要求

管道除接口外按规范规定回填

管沟内无积水

全部预留孔已封堵

管道两端堵板符合施工技术措施要求

管道的轴线位置、标高、坡度及管基、垫层已经复查合格

试 验 记 录

管 道编 号

/单线号

试验管段 试验

水头

m

试验

时间

h

允许渗水量

m3/( 24h·km)

实际渗水量

L/( min·m) 内径 mm 长度 m 材质 管口 种类 上游水头 m



























观测起始时间 T1

min

观测结束时间 T2

min

观测 时间 T

min

恒压时间内补

入的水量 W

L

实测渗水量

q

L/( min· m)

1

2

3

折合平均实测渗水量 : m3/( 24h· km)

备注:附试验管段位置示意图。

试验结论:

建设 /监理单位 总 承 包 单 位 施 工 单 位

专业工程师:





日期: 年 月 日

专业工程师:





日期: 年 月 日

施工班组长:

质量检查员:

专业工程师:

日期: 年 月 日

SH/T 3503— 2017

154



SH/T 3503— 2017

155



SH/T 3503— 2017

156



SH/T 3503— 2017

157



SH/T 3503— 2017

158



SH/T 3503— 2017

159



SH/T 3503— 2017

160

SH/T 3503— J414 管道试压包一览表

工程名称:



单位 工程名称 :

序号 管道编号 /单线号 试压包编号 序号 管道编号 /单线号 试压包编号













































备注:

专业工程师:



日期: 年 月 日

质量检查员:



日期: 年 月 日

填表人:



日期: 年 月 日





SH/T 3503— 2017

161



SH/T 3503— 2017

162



SH/T 3503— 2017

163

SH/T 3503— J416 管道静电接地测试 记录

工程名称:



单位 工程名称 :

管道编号 /单线号

法兰或螺纹接头 接地引线

接头型式

跨接导线 电阻 值

< 0.03Ω

规格 材质 对地电阻

< 100Ω 规格 材质











































建设 /监理单位 总承包单位 施工单位

专业工程师:





日期: 年 月 日

专业工程师:





日期: 年 月 日

施工班组长:

质量检查员:

专业工程师:

日期: 年 月 日

SH/T 3503— 2017

164





附 录 E

(规范 性 附录 )

交工技术文件电气安装工程用表

序号 名称 编号 页次

E.1 变电所受电条件确认表 SH/T 3503— J501 165

E.2 盘、柜基础型钢安装质量验收记录 SH/T 3503— J502 166

E.3 电缆桥架安装检查记录 SH/T 3503— J503 167

E.4 电缆敷设与绝缘检测记录 SH/T 3503— J504 168

E.5 电缆 安装质量验收记录 SH/T 3503— J505 169

E.6 交流电动机安装检验与空载运行记录 SH/T 3503— J506 170

E.7 变压器安装检验记录 SH/T 3503— J507 171

E.8 高 /低压开关柜安装检验记录 SH/T 3503— J508 172

E.9 保护 /控制盘(屏)安装检验记录 SH/T 3503— J509 173

E.10 直流系统 /UPS/EPS 安装检验记录 SH/T 3503— J510 174

E.11 火灾自动报警系统安装检验记录 SH/T 3503— J511 175































SH/T 3503— 2017

165

SH/T 3503— J501 变电所受电条件确认表

工程名称:



单位工程名称:

序号 检查项目与要求 检查结果

1 盘柜安装牢固、接地可靠,盘柜内电气元件齐全

2 所有受电设备内、外卫生良好

3 受电设备外观完整、无缺损,油漆完好,相色正确、醒目

4 绝缘套管的外绝缘和密封良好,符合设计和规程要求

5 变电所、变压器室内消防设施齐全

6 电缆规格符合设计,标牌齐全、正确;电缆桥架内无杂物、积水

7 电缆进出盘柜防火封堵严密

8 受电范围隔离符合要求,带电安全警示牌、 照明、通讯能满足受电要求

9 受电范围内的电气一、二次设备的试验已全部完成,报告齐全

10 变电所受电范围内涉及相应控制、保护和系统信号等调试完成

11 直流控制电源接入可靠、正常,绝缘良好,相应监视表计准确

12 二次回路接线正确、牢靠,回路编号正确、清晰,联锁调试完成

13 变电所所有表计显示正常,无报警现象

14 受送电方案已批准,各项组织措施、技术措施和安全措施已落实

15 操作、检修工器具齐全

16 变电所防小动物设施完备

备注:



结论:

建设单位代表:



日期: 年 月 日

监理单位代表:



日期: 年 月 日

承包单位代表:



日期: 年 月 日

相关单位代表:



日期: 年 月 日



SH/T 3503— 2017

166

SH/T 3503— J502 盘、柜基础型钢

安装质量验收记录

工程名称:



单位工程名称:

验收部位 执行标准

序号 检查项目 质量标准 检查结果

1 型钢规格、尺寸 型钢规格 、 安装尺寸符合设计 文件 要求

2 型钢 固定、 防腐 焊接牢固 , 防腐符合设计 文件 要求

3 型钢接地 有明显不少于两点的可靠接地 , 连接符 合规范要求

4 型钢顶部标高 型钢顶部宜高出最终地面 10mm, 手车式成套柜符 合产品技术要求

基础

型钢

安装

记录

检查项目 允许偏差 实测偏差

不直度 , mm

mm/m 1

mm/全长 5

不 平度 , mm

mm/m 1

mm/全长 5

位置偏差

及不平行度 , mm mm/全长 5

附:基础型钢测点布置示意图

备注:

结论 :

建设 /监理单位 总承包单位 施工单位

专业工程师:





日期: 年 月 日

专业工程师:





日期: 年 月 日

施工班组长:

质量检查员:

专业工程师:

日期: 年 月 日

SH/T 3503— 2017

167



SH/T 3503— J503 电缆桥架安装检查记录

工程名称:



单位工程名称:

名称 图号

序号 检查项目与要求 检查结果 检查日期

1

电缆桥架安装横平、竖直,坡度及走向符合设计要求,多层桥架

层间间距均匀,各层弯曲部分弧度一致,弯曲半径满足电缆敷设

弯曲半径的要求



2 防腐层完好无损

3 电缆桥架与支架连接牢固,对 口连接牢靠、无毛刺,并预留膨胀间隙,螺栓连接处已安装加强板,螺栓紧固,螺母在槽板的外侧

4 直线段钢制电缆桥架超过 30m、铝合金或玻璃钢制电缆桥架超过15m 时 应留有不少于 20mm 的伸缩缝

5 电缆桥架 跨越建筑物变形缝处 设置补偿装置

6 电缆桥架距离热力管道最小净距符合规范要求

7 电缆桥架内部平整、光洁,无杂物、无毛刺

8 电缆桥架隔板固定牢固

9 电缆桥架盖板固定牢固

10 电缆桥架支架间距合理,焊接牢固

11 电缆桥架有良好的接地

12 托盘桥架上的 保护管开孔,应采用机械开孔,开孔位置在桥架侧壁高度的 2/3 处以上

13 铝合金桥架在钢制支吊架上固定时,有防电化腐蚀的措施

备注:

结论:

建设 /监理单位 总承包单位 施工单位

专业工程师:





日期: 年 月 日

专业工程师:





日期: 年 月 日

施工班组长:

质量检查员:

专业工程师:

日期: 年 月 日

SH/T 3503— 2017

168



SH/T 3503— 2017

169



SH/T 3503— J505 电缆安装质量验收记录

工程名称:



单位工程名称:

序号 检查项目 与 要 求 检查结果 检查日期

1 电 缆型号、规格符合设计规定,保护层无机械损伤

2 电缆固定、弯曲半径和单芯电力电缆的金属护层接线符合规范规定

3 电缆之间,电缆与其他管道、道路、建筑物等之间平行和交叉时的最小净距符合规范规定

4 电缆排列整齐,不宜交叉,并留有余量

5 电缆线路所有应接地的接点与接地极接触良好,接地电阻值符合设计要求

6 电缆终端施工符合设计或生产厂商的要求

7 电缆终端、电缆接头固定牢靠 , 电缆接线端子与所接设备端子接触良好 , 互联接地箱和交叉互联箱的连接点应接触良好可靠

8 电缆终端 的相色正确,电缆支架等的金属部件防腐层完好 , 电缆管口封堵严密

9 标志牌装设齐全、正确、清晰

10 电缆沟内无杂物,无积水,盖板齐全

11 隧道内无杂物,照明、通风、排水等设施符合设计要求

12 直埋电缆路径标志,与实际路径相符 ; 路径标志清晰、牢固

13 水底电缆线路两岸,禁锚区内的标志和夜间照明装置符合设计要求

14 爆炸危险环境内的电缆连接 、 密封符合规范规定

15 电缆 相序排列应与设备连接相序一致,并符合设计要求

16 防火措施应符合设计,且施工质量合格

备注 :

结论:

建设 /监理单位 总 承 包 单 位 施工单位

专业工程师:









日期: 年 月 日

专业工程师:









日期: 年 月 日

施工班组长:

质量检查员:

专业工程师:

日期: 年 月 日

SH/T 3503— 2017

170

SH/T 3503— J506 交流电动机安装检验与

空载运行记录

工程名称:



单位工程名称:

位号 拖动机械名称







型号 额定功率 kW 轴承牌号

定子电压 V 转子电压 V 标准编号

定子电流 A 转子电流 A 出厂编号

转速 r/min 绝缘等级 出厂日期

防护等级 IP 防爆标志 制造厂

检查内容与 要 求 检查结果











线

铭牌参数、防爆类型、级别、组别等符合设计文件

接线盒内接线正确、紧固,绝缘件完好,电气间隙和爬电距离符合规范要求

防爆接线盒的隔爆面及进线密封符合要求,螺栓和防松设施齐全、可靠

电动机及其 启 动设备已按规定接地

测量定子绕组的绝缘电阻 M?

集电环表面清洁、光滑,刷架、刷握及电刷安装符合规范要求

轴承润滑脂(油)及填充量符合产品技术文件规定

转子盘动灵活,无碰卡声







短路保护设备整定值

过载保护设备整定值

主回路绝缘电阻 M?

控制回路绝缘电阻 M?

控制、保护和联锁回路模拟操作,其功能符合设计文件要求









定子电流 A / A / A 转子电流 A 振动测量值 mm/s(mm)

电 机温度 ℃ 轴承温度 负荷端: ℃ ;非负荷: ℃

运行时间 h 环境温度 ℃ 运行日期 年月日

备注:

建设 /监理单位 总 承 包 单 位 施工单位

专业工程师:









日期: 年 月 日

专业工程师:









日期: 年 月 日

施工班组长:

质量检查员:

专业工程师:

日期: 年 月 日



SH/T 3503— 2017

171

SH/T 3503— J507 变压器安装检验记录

工程名称:



单位工程名称:

位 号 名称







型号 额定容量 kVA 制造厂

额定电压 kV 冷却方式 出厂日期

额定电流 A 总重量 kg 出厂编号

检查内容与要求 检查结果

1 本体安装中心线、标高符合设计文件要求

2 安装固定可靠

3 散热器安装符合产品技术文件要求

4 油路中全部阀门灵活、开闭正确,法兰处密封无泄漏

5 储油柜安装符合产品技术文件要求, 油位指示准确

6 瓷套管表面无裂缝及伤痕,已清擦干 净

7 充油套管安装正确,密封,油位指示准确

8 压力释放阀安装及接线正确

9 突发压力保护 /泄放装置安装正确

10 吸湿器管路畅通,吸湿剂干燥、油封正确

11 气体继电器、温度计试验合格,安装及接线正确

12 风扇电动机及叶片牢固,转动灵活,方向正确,无振动和过热现象

13 电气线路排列整齐、防油,接线盒密封良好

14 绝缘油合格,注油至规定油位

15 接地线规格符合设计文件要求,连接可靠

16 分接开关位置已置位

17 整体密封检查无漏油及渗油

18 电气 设备试验已检查确认合格

检验结论:

建设 /监理单位 总 承 包 单 位 施工单位

专业工程师:





日期: 年 月 日

专业工程师:





日期: 年 月 日

施工班组长:

质量检查员:

专业工程师:

日期: 年 月 日



SH/T 3503— 2017

172

SH/T 3503— J508 高 /低压开关柜安装检验记录

工程名称:



单位工程名称:

名 称 制造厂

施工图号 柜号 台数 台

检查内容 与 要 求 检查结果

1 建筑工程应 具备盘柜 安装 条件 , 并验收合格

2 基础型钢安装已验收合格

3 外观、漆层完好,安装件及备件、操作专用工具、产品技术文件齐全

4 柜内电器元件齐全完好,安装位置正确、牢固,型号、规格符合设计文件要求

5 柜内母线规格、材质、对地和相间距离符合设计文件和规范要求

6 母线安装、连接符合规范要求,连接螺栓紧固力矩 符合规范要求

7 成套柜接地母线与主接地网连接可靠

8 抽屉式配电柜抽屉与柜体间接触良好,柜体、框架接地良好

9 抽屉、小车推拉灵活,主触头及二次回路连接插件接触良好

10 防 止电气误操作的“五防”装置齐全,动作灵活可靠

11 校验一、二次回路接线准确,连接可靠,标志齐全

12 盘 、 柜孔洞及电缆管封堵严密 ,可能结冰的地区 有防止电缆管内积水结冰的措施

13 柜内清扫、擦拭干净















检查项目 允许偏差 实测最大偏差

垂直度(每米) 1.5

水平偏差, mm 相临两柜顶部 2 成列柜顶部 5

柜面偏差, mm 相临两柜边 1 成列柜面 5

柜间接缝, mm 2

检验结论:

建设 /监理单位 总 承 包 单 位 施工单位

专业工程师:











日期: 年 月 日

专业工程师:









日期: 年 月 日

施工班组长:

质量检查员:

专业工程师:



日期: 年 月 日

SH/T 3503— 2017

173

SH/T 3503— J509

保护 /控制盘(屏)

安装检验记录

工程名称:



单位工程名称:

名称 制造厂

施工图号 盘(屏)号 台数 台

检查内容 与 要 求 检查结果

1 建筑工程应 具备盘(屏)安装 条件 , 并验收合格

2 基础型钢安装 已验收合格

3 外观、漆层完好,安装件及备件、产品技术文件齐全

4 盘内电器元件齐全完好,安装位置正确、牢固,型号、规格符合设计文件要求

5 小母线安装牢固,标志齐全

6 校验二次回路接线准确,连接牢靠,标志齐全

7 接地齐全,牢固可靠

8 继电器试验已检查确认合格

9 电气测量仪表检验 确认合格

10 电气模拟试验 已检查确认合格

11 柜内清扫、擦拭干净

12 测量绝缘电阻符合设计文件要求



(屏)









检 查 项 目 允许偏差 实测最大偏差

垂直度(每米) 1.5

水平偏差, mm 相临两盘顶部 2 成列盘顶部 5

盘面偏差, mm 相临两盘边 1 成列盘面 5

盘间接缝, mm 2

检验结论:

建设 /监理单位 总 承 包 单 位 施工单位

专业工程师:











日期: 年 月 日

专业工程师:









日期: 年 月 日

施工班组长:

质量检查员:

专业工程师:



日期: 年 月 日



SH/T 3503— 2017

174

SH/T 3503— J510

直流系统 /UPS/EPS

安装检验记录

工程名称:



单位工程名称:

名 称 位 号 施工图号

型 号 输入电压 V 制造厂

额定容量 kVA 输出电压 V 出厂编号

检查内容 与 要求 检查结果

1 建筑工程应 具备盘柜安装 条件 , 并验收合格

2 基础型钢安装 已验收合格

3 外观、漆层完好,安装件及备件、产品技术文件齐全

4 柜内电器安装牢固,接线准确、紧固,标志齐全

5 校验二次回路,插拔件无错位,插拔灵活,接触可靠

6 检查蓄电池外观有无变形、漏液

7 蓄电池组装和接线正确、牢固

8 柜体接地齐全,牢固可靠

9 电气设备调整试验已检查确认合格

10 电气测量仪表检验 确认合格

11 蓄电池充放电已检查确认合格

12 电气模拟试验 已检查确认合格

13 柜内清扫、擦拭干净

14 测量绝缘电阻符合设计文件要求













项目 允许偏差 实测最大偏差

垂直度(每米) 1.5

水平偏差, mm 相临两盘顶部 2 成列盘顶部 5

盘面偏差, mm 相临两盘边 1 成列盘面 5

盘间接缝, mm 2

检验结论:

建设 /监理单位 总 承 包 单 位 施工单位

专业工程师:





日期: 年 月 日

专业工程师:





日期: 年 月 日

施工班组长:

质量检查员:

专业工程师:

日期: 年 月 日

SH/T 3503— 2017

175

SH/T 3503— J511

火灾自动报警系统

安装检验记录

工程名称:



单位工程名称:

名称 施工图号 执行标准

检 查 内 容 与 要 求 检 查 结 果

1 报警控制器(盘)、探测器 、报警按钮、控制设备等设备铭牌符合设计文件要求

2 导线、电缆的型号、规格符合设计文件要求

3 管路及线槽安装牢固,支吊架位置及间距符合规范要求

4 同一穿线管或线槽的同一槽孔内没有不同系统、不同电压等级、不同电流类别的线路

5 接线盒内的接线牢靠,绝缘良好

6 测量线路的绝缘电阻,按回路填写于 J504 记录中

7 防爆、防护密封符合规范要求

8 探测器、报警按钮、控制设备安装牢固,位置、标高符合设计文件和规范要求

9 报警控制器(盘)安装牢固,配线整齐,端头标号清晰正确,接地 牢靠

10 系统的主电源和备用电源自动转换正确可靠,其容量分别符合相关标准的要求

11 通电检查报警控制器(盘)的各项功能符合规范和设计文件要求

12 采用专用检查仪器对探测器、报警按钮逐个试验,其动作均准确无误

13 用主电源和备用电源分别检查报警系统的各项控制、联动功能均正确可靠





自年月日时至年月日时系统连续运行 120h 无故障

检验结论:

备注:

建设 /监理单位 总 承 包 单 位 施 工 单 位

专业工程师:











日期: 年 月 日

专业工程师:











日期: 年 月 日

施工班组长:

质量检查员:

专业工程师:

日期: 年 月 日

SH/T 3503— 2017

176

附 录 F

(规范性附录)

交工技术文件仪表安装工程用表

序号 名称 编号 页次

F.1 仪表设备校验确认表 SH/T 3503— J601 177

F.2 节流装置检查记录 SH/T 3503— J602 178

F.3 仪表管道压力试验记录 SH/T 3503— J603 179

F.4 仪表管道泄漏性 /真空度试验条件确认与试验记录 SH/T 3503— J604 180

F.5 综合控制系统机柜 /仪表盘 /操作台安装检验记录 SH/T 3503— J605 181

F.6 综合控制系统送电条件确认表 SH/T 3503— J606 182

F.7 综合控制系统基本功能检测记录 SH/T 3503— J607 183

F.8 报警 /联锁系统与可编程序控制系统调试记录 SH/T 3503— J608 184

F.9 联校试验条件确认表 SH/T 3503— J609 185

F.10 联校调试记录 SH/T 3503— J610-1 186

F.11 联校调试记录(续) SH/T 3503— J610-2 187









































SH/T 3503— 2017

177

SH/T 3503— J601 仪表设备校验确认表

工程名称:



单位工程名称:

序号 校验项目 单位 数量 确认结果 确认日期 确认人

1 变送器 /转换器调校

2 调节阀 /执行器 /开关阀调校

3 工艺开关调校

4 物位仪表调校

5 就地指示仪调校

6 指示 /记录仪调校

7 分析仪调校

8 轴位移、轴振动仪表调校

9 安全栅 /分配器 /选择器调校

10 调节器调校

11 计算器调校

12 积算器调校

13 其他仪表调校









注:“确认结果”栏填写合格或不合格。

备注:

建设 /监理单位 总承包单位 施工单位

专业工程师:









日期: 年 月 日

专业工程师:









日期: 年 月 日

质量检查员:

专业工程师:



日期: 年 月 日

SH/T 3503— 2017

178

SH/T 3503— J602 节流装置检查记录

工程名称:



单位工程名称:

节流装置

名称 位号 测量介质

节流件直径 d

mm

节流件厚度 δ

mm

直管长度



测量管

引出

方式

检查

结果 设计 实测 设计 实测 上游 下游

































注:“直管长度”栏填写合格 /不合格。

建设 /监理单位 总 承 包 单 位 施 工 单 位

专业工程师:







日期: 年 月 日

专业工程师:







日期: 年 月 日

施工班组长:

质量检查员:

专业工程师:



日期: 年 月 日

SH/T 3503— 2017

179



SH/T 3503— J603 仪表管道压力试验记录

工程名称:



单位工程名称:

试验环境温度 ℃ 试验介质温度 ℃

仪表位号 管道名称 规格 材质 设计压力 MPa 试验压力 MPa 试验介质 试验结果 试验人







































注:本表格只能填写相同试验环境温度、相同 试验介质温度下的数据。

建设 /监理单位 总承包单位 施工单位

专业工程师:











日期: 年 月 日

专业工程师:











日期: 年 月 日

施工班组长:

质量检查员:

专业工程师:



日期: 年 月 日

SH/T 3503— 2017

180



SH/T 3503— J604 仪表管道泄漏性 /真空度

试验条件确认与试验记录

工程名称:



单位工程名称:

检查项 目 与 要 求 检 查结果

仪表管道压力试验合格

仪表管道与试验的工艺系统已经连通

试验 记 录

仪表位号 设计 压力 MPa 设计 温度 ℃

试验环境

温度



泄漏性试验 真空试验

压力

MPa 介质

压力

MPa 介质





























结论:

建设 /监理单位 总 承 包 单 位 施 工 单 位

专业工程师:







日期: 年 月 日

专业工程师:







日期: 年 月 日

施工班组长:

质量检查员:

专业工程师:



日期: 年 月 日



SH/T 3503— 2017

181

SH/T 3503— J605 综合控制系统 机柜 /仪表盘 /

操作台安装检 验 记录

工程名称:



单位工程名称:

名 称 型号 位号

检查项目 与 要 求 检查结果

1 外观无破损变形,内外表面无油漆脱落、无锈蚀等缺陷

2 基础型钢平直、牢靠,外 形尺寸与机柜、仪表盘、操作台的尺寸一致,表层已除锈防腐

3 机柜、盘、台的位置、铭牌、型号、位号、数量、外形尺寸、仪表开孔尺寸符合 设计文件要求

4 仪表、综合控制系统内部组件的型号、规格、数量、安装位置符合设计文件要求, 无破损、松动、脱落、受潮

5

综合控制系统机柜、仪表盘、操作台的安装符合设计文件要求,垂直度、水平度、

盘间接缝间隙、顶部高差、正面平面度等符合规范要求,与基础型钢之间采用防

锈螺栓牢固连接



6

盘间电缆(含专用电缆) /光缆型号、规格、数量,电缆头及接线(含内部接线)

正确牢固、整 齐美观,符合设计文件和规范要求,标志牌规范,标识清晰,本安

与非本安电线分开设置、敷设在不同汇线槽内



7 机柜、仪表盘、操作台及室内地板下、电缆沟及室内电缆槽内干燥、无尘土、无 异物,电缆出、入口已封闭

8 电缆(线)的导通、绝缘电阻符合规范要求,光缆测试符合规范要求

9 就地仪表盘安装在光线充足 、 环境干燥、操作维修方便的地方,且有良好的密封性,防爆性能符合设计文件要求

10 电源系统符合设计文件和规范的要求

11 工作接地系统符合设计 文件和规范的 要求

12 保护接地系统符合设计 文件和规 范的 要求

13 屏蔽接地系统符合设计 文件和规范的 要求

14 随盘技术文件 齐全



检验结论:

建设 /监理单位 总承包单位 施工单位

专业工程师:









日期: 年 月 日

专业工程师:









日期: 年 月 日

施工班组长:

质量检查员:

专业工程师:



日期: 年 月 日













SH/T 3503— 2017

182

SH/T 3503— J606 综合控制系统送电条件确认表

工程名称:

单位工程名称:

系统名称 系统型号

制造厂

检查项目 确认结果 检查项目 确认结果

控制室的土建交安

手续已办理 电缆

空调系统 配线

环境温度 系统安装

环境湿度 接地

室内清洁 电源

消防系统 照明







注:“确认结果”栏填写合格或不合格。

备注:

建设 / 监理单位 总承包单位 施工单位 制造厂

专业工程师:









日期: 年 月 日

专业工程师:









日期: 年 月 日

施工班组长:

质量检查员:

专业工程师:



日期: 年 月 日

现场代表:









日期: 年 月 日



SH/T 3503— 2017

183



SH/T 3503— J607

综合控制系统

基本功能检测记录

工程名称:

单位工程名称:

系统名称 系统型号

制造厂

系统基本功能检测记录

检测项目 判 断 检测结果 检测人 检测项目 判 断 检测结果 检测人

自诊断 □ 通讯功能 □

程序安装 □ 报警功能 □

画面检测 □ 冗余功能 □

键盘操作 □ 恢复功能 □

鼠标操作 □ 打印功能 □

触屏操作 □ LED 状态灯 □

按钮 □ 系统供电 □

检测依据













注 1:在“判断”栏中画“√”表示有该项功能;画“×”表示无该项功能。

注 2:“检测结果”栏填写合格或不合格。

建设 /监理单位 总承包单位 施工单位 /检测及施工单位 /调试单位

专业工程师:





日期: 年 月 日

专业工程师:







日期: 年 月 日

班组长:

质量检查员:

专业工程师:



日期: 年 月 日

SH/T 3503— 2017

184

SH/T 3503— J608 报警 /联锁系统与可编程序

控制系统调试记录

工程名称:



单位工程名称:

调试人

序号 联锁 /回路号 逻辑图号 确认 复位 调试 结果



































注 1: “确认”、“复位”栏填写“正常”、“不正常”。

注 2:“调试结果”栏填写合格或不合格。

备注:

建设 /监理单位 总承包单位 施工单位 /检测及施工单位 /调试单位

专业工程师:





日期: 年 月 日

专业工程师:





日期: 年 月 日

班组长:

质量检查员:

专业工程师:

日期: 年 月 日

SH/T 3503— 2017

185



SH/T 3503— J609 联校试验条件确认表

工程名称:



单位工程名称:

系统名称 系统型号

确认项目 判断 确认结果 确认项目 判断 确认结果

试验方案 □ 仪表管道压力试验 □

试验人员 □ 仪表管道泄漏性试验 □

试验设备 □ 仪表管道 真空度试验 □

仪表设备安装 □ 脱脂 □

仪表设备单体调校 □ 酸洗 □

仪表电气回路检验 □ 接地系统 □

电缆敷设及绝缘测试 □ 气源系统 □

仪表盘、柜、台安装 □ 电源系统 □

桥架安装 □ 控制系统调试 □



注 1:在“判断”栏中画“√”表示有该项目;画“×”表示无该项目。

注 2:“确认结果”栏填写合格或不合格。

备注:

建设 /监理单位 总承包单位 施工单位

专业工程师:











日期: 年 月 日

专业 工程师:











日期: 年 月 日

施工班组长:

质量检查员:

专业工程师:



日期: 年 月 日



SH/T 3503— 2017

186



SH/T 3503— 2017

187



SH/T 3503— 2017

188

附 录 G

( 规范 性附录)

交 工技术文件 压力容器现场组焊安装工程用表

序号 名称 编号 页次

G.1 现场组装记录 SH/T 3503— J701 189

G.2 球壳板 /支柱到货检验报告 SH/T 3503— J702 190

G.3 球形储罐预制件检查记录赤道带 /温带板 SH/T 3503— J703 191

G.4 球形储罐预制件检查记录极板 /极中板 SH/T 3503— J704 192

G.5 球形储罐预制件检查记录支柱 SH/T 3503— J705 193

G.6 球形储罐组装尺寸检查记录 SH/T 3503— J706 194

G.7 球形储罐组装尺寸检查记录(续) SH/T 3503— J707 195

G.8 球形储罐支柱检查记录 SH/T 3503— J708 196

G.9 球形储罐焊后几何尺寸检查记录 SH/T 3503— J709 197

G.10 封头 /过渡段组装尺寸检查记录 SH/T 3503— J710 198

G.11 设备焊接工作记录 SH/T 3503— J711-1 199

G.12 设备焊接工作记录(续) SH/T 3503— J711-2 200

G.13 焊缝返修施工记录 SH/T 3503— J712 201































SH/T 3503— 2017

189

SH/T 3503— J701 现场组装记录

工程名称:



单位工程名称:

设备名称 设备位号 产品编号

规格 组装方式 □立式□卧式

测量

部位

筒体外周长

偏差

mm

筒体上口

水平度偏



mm

分段筒体

垂直度偏差

mm

筒体最大

与最小直

径偏差

mm

组对方位

偏差

mm

对口

间隙

mm

对口

错边量

mm

角变形

mm







实测值 允

















实测值 允





实测









实测









实测最

大值







实测最

大值







实测最

大值 下口 上 口 0? 90?















总体尺寸与形位偏差

mm 允许值

实测值

0?/ 180? 90?/ 270?

筒体直线度

筒体总垂直度

筒体总长(高)度

检查结论:

建设 /监理单位 总承包单位 施工单位

专业工程师:





日期: 年 月 日

专业工程师:





日期: 年 月 日

施工班组长:

质量检查员:

专业工程师:

日期: 年 月 日



SH/T 3503— 2017

190

SH/T 3503— J702 球壳板 /支柱到货 检验报告



工程名称:



单位工程名称:

设备名称 设备位号 产品编号

公 称容积 m3 内直径 mm 厚度 mm

球壳板总数 支柱总数 材质

球壳板几何尺寸检查

检查数量 合格数量 合格率 % 检查记录编 号

张 张







编号 1 2 3 4 5 6 7

直线度偏差, mm

长度, mm

编号 8 9 10 11 12 13 14

直线度偏差, mm

长度, mm

无损测项目 检查数量 检查结果 判定 检查记录编号

球壳板周边超声检测 张

球壳板球全面积 超声检测 张

坡口检测 张

球壳板厚度检测 张 最小厚度 mm 最大厚度 mm

结论:

支柱全长直线度,实测数据 : □不符合□符合规范要求

支柱长度,实测数据 : □不符合□符合规范要求

球壳板厚度,实测数据 : □不符合□符合规范要求

球壳板周边超声检测 : □不符合□符合规范要求

球壳板全面积超声检测 : □不符合□符合规范要求

坡口表面检测 : □不符合□符合规范要求

建设 /监理单位 总承包单位 施工单位

专业工程师:





日期: 年 月 日

专业工程师:





日 期: 年 月 日

施工班组长:

质量检查员:

专业工程师:

日期: 年 月 日

SH/T 3503— 2017

191



SH/T 3503— J703

球形储罐预制件检查记录

赤道带 /温带板

工程名称:



单位工程名称:

设备名称 设备位号 产品编号

公称容积 m3 内直径 mm 厚度 mm

执行标准 检查数量 张 检查比例 %

项目 单位 允许 偏差值 设计值 球壳板编号及实侧值



球壳板与样板间隙 E mm ≤ 3

坡口钝边 A mm ± 1.5

坡口深度 t mm ± 1.5

坡口角度 α ( °) ± 2.5

长度方

向弦长

L1 mm ± 2.5

L2 mm ± 2.5

宽度方

向弦长

B3 mm ± 2

B2 mm ± 2

对角线

弦长

C1 mm ± 3

C2 mm ± 3

两条对角线间距 h mm 5

带支柱

赤道板

支柱直线度 mm

支柱轴线位移 mm

支柱断口周长 mm



检测部位示意图

外观检查:

结论:

建设 /监理单位 总承包单位 施工单位

专业工程师:





日期: 年 月 日

专业工程师:





日期: 年 月 日

施工班组长:

质量检查员:

专业工程师:

日期: 年 月 日



SH/T 3503— 2017

192

SH/T 3503— J704 球形储罐预制件检查记录

极板 /极中板

工程名称:



单位工程名称:

设备名称 设备位号 产品编号

公称容积 m3 内直径 mm 厚度 mm

执行标 准 检查数量 张 检查比例 %

项目 单位 允许 偏差值 设计值 球壳板编号及实侧值



球壳板与样板间隙 E mm ≤ 3

开孔处球壳曲率 mm ≤ 3

坡口钝边 A mm ± 1.5

坡口深度 t mm ± 1.5

坡口角度 α ( °) ± 2.5

直径 D mm ± 2



检测部位示意图

管口编号

管口位置偏差

mm

管口高度偏差 L

mm

法兰 水平度

mm/m

允许值 实测值 允许值 实测值 允许值 实测值

径向 周向 径向 周向









外观检查:

结论:

建设 /监理单位 总承包单位 施工单位

专业工程师:





日期: 年 月 日

专业工程师:





日期: 年 月 日

施工班组长:

质量检查员:

专业工程师:

日期: 年 月 日

SH/T 3503— 2017

193

SH/T 3503— J705 球形储罐预制件检查记录

支柱

工程名称:



单位工程名称:

设备名称 设备位号 产品编号

公称容积 m3 内直径 mm 厚度 mm

执行标准 检查数量 张 检查比例 %

支柱

编号

支柱全长直线度 e

mm

支柱长度 H

mm

支柱与底板垂直度

mm

分段支柱断口周长

mm

备注 允许

偏差

实测值 允许

偏差

实测

值 允许偏差 实测值 上段 下段 径向 周向



















检测部位示意图

外观检查:

结论:

建设 /监理单位 总承包单位 施工单位

专业工程师:





日期: 年 月 日

专业工程师:





日期: 年 月 日

施工班组长:

质量检查员:

专业工程师:

日期: 年 月 日



SH/T 3503— 2017

194

SH/T 3503— J706 球形储罐组装尺寸检查记录

工程名称:



单位工程名称:

设备名称 设备位号 产品编号

公称容积 m3 内直径 mm 厚度 mm

检查样板内半径 R 样 mm 检查样板弦长 L mm

检查项目 允许值 mm 焊缝编号及实测值 mm



组对

间隙

M

a

b

c

组对

错边

n

a

b

c

组对

棱角

E

a

b

c



检测部位示意图

结论:



建设 /监理单位 总承包单位 施工单位

专业工程师:





日期 : 年 月 日

专业工程师:





日期: 年 月 日

施工班组长:

质量检查员:

专业工程师:

日期: 年 月 日

SH/T 3503— 2017

195

SH/T 3503— J707 球形储罐组装尺寸检查记录

(续)

工程名称:



单位工程名称:

设备名称 设备位号 产品编号

公称容积 m3 内直径 mm 厚度 mm



检测部位示意图

检查项目 允许值 mm 实测值 mm

赤道截面最大内直径与设计内直径之差

赤道截面最小内直径与设计内直径之差

两极间内直径与设计内直径之差

赤道截面最大内直径与最小内直径之差

赤道截面最大内直径与两极间内直径之差

赤道截面最小内直径与两极间内直径之差

赤道线水平度

支柱焊缝与对接焊缝最小距离

相邻对接焊缝最小距离

项目 管口编号

管口水平度 Δ H,

mm

允许值

实测值

管口位置 mm 允许值 实测值

结论:

建设 /监理单位 总承包单位 施工单位

专业工程师:





日期: 年 月 日

专业工程师:





日期: 年 月 日

施工班组长:

质量检查员:

专业工程师:

日期: 年 月 日

SH/T 3503— 2017

196

SH/T 3503— J708 球形储罐 支柱检查记录

工程名称:



单位工程名称:

设备名称 设备位号 产品编号

公称容积 m3 内直径 mm 厚度 mm

检查时机

支柱

编号

支柱全长直线度

mm

支柱垂直度

mm

允许

偏差值

实测值 允许

偏差值

径向实测值 周向实侧值

径向 周向 a1 a2 a1- a2 a1 a2 a1- a2

1

2

3

4

5

6

7

8

9

10

结论:



检测部位示意图

建设 /监理单位 总承包单位 施工单位

专业工程师:





日期: 年 月 日

专业工程师:





日期: 年 月 日

施工班组长:

质量检查员:

专业工程师:

日期: 年 月 日



SH/T 3503— 2017

197

SH/T 3503— J709 球形储罐

焊后几何尺寸检查记录

工程名称:



单位工程名称:

设备名称 设备位号 产品编号

公称容积 m3 内直径 mm 厚度 mm

检查项目

检查结果

允许值

mm 总测点数 合格点数

合格率

%

实测最大

偏差值

mm

焊缝宽度偏差

内部焊缝

外部焊缝

焊缝余高偏差

内部焊缝

外部焊缝

焊缝棱角

角接焊缝焊脚高

赤道截面最大内直径

赤道截面最小内 直径

两极间实测内直径

最大内直径与最小内直径差值

最大内直径与设计内直径差值

最小内直径与设计内直径差值

结论:

建设 /监理单位 总承包单位 施工单位

专业工程师:





日期: 年 月 日

专业工程师:





日期: 年 月 日

施工班组长:

质量检查员:

专业工程师:

日期: 年 月 日

SH/T 3503— 2017

198

SH/T 3503— J710 封头 /过渡段组装尺寸

检查记录

工程名称:



单位工程名称:

设备名称 设备位号 产品编号

封头 /过渡段 规格 材质 执行标准

检查项目 允许值 mm

焊缝编号及实测值 mm



组对间隙

M

a

b

c

组对错边

n

a

b

c

组对棱角

E

检查样板

长度 L=

mm

a

b

c

封头 /过渡段规格整体检查

样板检查

形状偏差

大值

椭圆度

上 端

小值 下端



检测部位示意图

结论:

建设 /监理单位 总承包单位 施工单位

专业工程师:





日期: 年 月 日

专业工程师:





日期: 年 月 日

施工班组长:

质量检查员:

专业工程师:

日期: 年 月 日



SH/T 3503— 2017

199



SH/T 3503— 2017

200



SH/T 3503— 2017

201

SH/T 3503— J712 焊缝返修施工记录

工程名称:



单位工程名称:

设备名称 设备位号 产品编号

返修位置规格 返修位置材 质 返修焊接方 法

返修焊接工艺参数

序号 返修部 位 返修片 位号 缺陷 性质 返修 次数

返修尺寸

(长 ×宽 ×深 )

mm

热处理方

法 返修日期

焊工姓名或

钢印号 返修结果



























备注:



建设 /监理单位 总承包单位 施工单位

专业工程师:





日期: 年 月 日

专业工程师 :





日期: 年 月 日

施工班组长:

质量检查员:

专业工程师:

日期: 年 月 日



SH/T 3503— 2017

202

附 录 H

(规范性附录)

交工技术文件起重机械安装工程用表

序号 名称 编号 页次

H.1 起重机轨道与车 挡 安装检验记录 SH/T 3503— J801 203

H.2 手动单梁起重机安装检验记录 SH/T 3503— J802 204

H.3 手动双梁起重机安装检验记录 SH/T 3503— J803 205

H.4 手动单梁悬挂起重机安装检验记录 SH/T 3503— J804 206

H.5 电动单梁起 重机安装检验记录 SH/T 3503— J805 207

H.6 电动葫芦双梁起重机安装检验记录 SH/T 3503— J806 208

H.7 电动单梁悬挂起重机安装检验记录 SH/T 3503— J807 209

H.8 通用桥式起重机安装检验记录 SH/T 3503— J808 210

H.9 双梁通用门式起重机和装卸桥安装 检验记录 SH/T 3503— J809 211

H.10 单主梁门式起重机和装卸桥安装 检验记录 SH/T 3503— J810 212

H.11 臂上起重机和柱式悬臂起重机安装 检验记录 SH/T 3503— J811 213

H.12 起重机械负荷试验条件确认表 SH/T 3503— J812 214

H.13 起重机械空负荷试验记录 SH/T 3503— J813 215

H.14 起重机械负荷试验记录 SH/T 3503— J814 216





























SH/T 3503— 2017

203

SH/T 3503— J801 起重机轨道与车 挡 安装

检验记录

工程名称:



单位工程名称:

设备名称 设备 位号

规格型号 起重量 t 跨度 m

制造厂 工作级别 起升高度 m

控制方式 供电方式 工作环境

轨道型号 轨道长度 m 安装地点

实测项目 允许值 mm 实测值 mm 结论

导轨的实际中心线对吊车梁的实际中心线位置偏差

轨道跨度偏差

轨道顶面纵向倾斜度 每 2m 范围内 全长范围内

轨道顶面基准点的标高偏差

同一截面内两平行轨道的标高相对差

轨道沿长度方向在水平面内的弯曲

轨道接头

高低差

侧向错位

间隙

伸缩缝处间隙

轨道横向倾斜度偏差

检查项目 安装要求 检查结果

两平行导轨的接头位置 应错开,错开距离大于起 重机前后车轮的基距

导轨焊接接头 焊条符合要求,接头顶面及侧面焊缝打磨平整光滑

导轨接头处支撑垫板 垫板宽度( 沿 导轨长度方向)比其他处增加 1 倍

混凝土吊车梁的灌浆层 符合设计文件要求

钢轨下弹性垫板 规格和材质符合设计文件规定,拧紧螺栓前钢轨与弹性垫 板贴紧

钢吊车梁上的导轨 钢轨与钢吊车梁顶面应贴紧,当有间隙时,按照规定加垫板并焊接固定

连接螺栓 无缺扣无松动

车 挡 同一跨端两条轨道上的车 挡 与起重机缓冲器均应接触

结论:

建设 /监理单位 总 承 包 单位 施工单位

专业工 程师:





日期: 年 月 日

专业工程师:





日期: 年 月 日

施工班组长:

质量检查员:

专业工程师:

日期: 年 月 日

SH/T 3503— 2017

204

SH/T 3503— J802 手动单梁起重机安装

检验记录

工程名称:



单位工程名称:

设备名称 设备 位号

型号 起重量 t 跨度 m

制造厂 工作级别 起升高度 m

轨道长度 m 安装地点 工作环境



检测部位示意图

单位: mm

检测项目 允许值 实测值 结论

起重机跨度 S

起重机跨度 S1、 S2的相对差 | S1- S2|

对角线 L1、 L2的相对差 | L1- L2|

主梁上拱度 F

备注:



结论:

建设 /监理单位 总 承 包 单位 施工单位

专业工程师:





日期: 年 月 日

专业工程师:





日期: 年 月 日

施工班组长:

质量检查员:

专业工程师:

日期: 年 月 日



SH/T 3503— 2017

205

SH/T 3503— J803 手动双梁起重机安装

检验记录

工程名称:



单位工程名称:

设备名称 设备 位号

规 格型号 起重量 t 跨度 m

制造厂 工作级别 起升高度 m

轨道长度 m 安装地点 工作环境



检测部位示意图 单位: mm

检测项目 允许值 实测值 结论

起重机跨度 S

起重机跨度 S1、 S2的相对差 | S1- S2|

主梁上拱度 F

对角线 L1、 L2的相对差 | L1- L2|

小车轨距 K

小车轨距 K1、 K2的相对差 | K1- K2|

备注:



结论:

建设 /监理单位 总 承 包 单位 施工单位

专业工程师:





日期: 年 月 日

专业工程师:





日期: 年 月 日

施工班组长:

质量检查员:

专业工程师:

日期: 年 月 日

SH/T 3503— 2017

206

SH/T 3503— J804 手动单梁悬挂起重机安装

检验记录

工程名称:



单位工程名称:

设备名称 设备 位号

规格型号 起重量 t 跨度 m

制造厂 工作级别 起升高度 m

轨道长度 m 安装地点 工作环境



检测部位示意图

单位: mm

检测项目 允许值 实测值 结论

起重机跨度 S

起重机跨度 S1、 S2的相对差 | S1- S2|

主梁上拱度 F

对角线 L1、 L2的相对差 | L1- L2|

主梁旁弯度 f

备注:



结论:

建设 /监理单位 总 承 包 单位 施工单位

专业工程师:





日期: 年 月 日

专业工程师:





日期: 年 月 日

施工班组长:

质量检查员:

专业工程师:

日期: 年 月 日

SH/T 3503— 2017

207

SH/T 3503— J805 电动单梁起重机安装

检验记录

工程名称:



单位工程名称:

设备名称 设备 位号

规格型号 起重量 t 跨度 m

制造厂 工作级别 起升高度 m

轨道长度 m 安装地点 工作环境



检测部位示意图

单位: mm

检测项目 允许值 实测值 结论

起重机跨度 S

主梁上拱度 F

对角线 L1、 L2的相对差 | L1- L2|

主 梁旁弯度 f

备注:



结论:

建设 /监理单位 总 承 包 单位 施工单位

专业工程师:





日期: 年 月 日

专业工程师:





日期: 年 月 日

施工班组长:

质量检查员:

专业工程师:

日期: 年 月 日

SH/T 3503— 2017

208

SH/T 3503— J806 电动葫芦双梁起重机安装

检验记录

工程名称:



单位工程名称:

设备名称 设备 位号

规格型号 起重量 t 跨度 m

制造厂 工作级别 起升高度 m

轨道长度 m 安装地点 工作环境



检测部位示意图

单位: mm

检测项目 允许值 实测值 结论

起重机跨度 S

起重机跨度 S1、 S2的相对差 | S1- S2|

主梁上拱度 F

对角线 L1、 L2的相对差 | L1- L2|

大车车轮水平偏斜 tgφ

小车轨距 K 跨端 跨中



主梁旁弯度 f

同一截面上小车轨道高低 差 c

备注:



结论:

建设 /监理单位 总 承 包 单位 施工单位

专业工程师:





日期: 年 月 日

专业工程师:





日期: 年 月 日

施工班组长:

质量检查员:

专业工程师:

日期: 年 月 日

SH/T 3503— 2017

209

SH/T3503— J807 电动单梁悬挂起重机安装

检验记录

工程名称:



单位工程名称:

设备名称 设备 位号

规格型号 起重量 t 跨度 m

制造厂 工作级别 起升高度 m

控制方式 供电 方式 工作环境

轨道长度 m 安装地点



检测部位示意图 单位: mm

检测项目 允许值 实测值 结论

起重机跨度 S

起重机跨度 S1、 S2的相对差 | S1- S2|

主梁上拱度 F

主梁旁弯度 f

安装后,车轮轮缘内侧与工字钢轨道翼缘间的间隙 c

备注:



结论:

建设 /监理单位 总 承 包 单位 施工单位

专业工程师:





日期: 年 月 日

专业工程师:





日期: 年 月 日

施工班组长:

质量检查员:

专业工程师:

日期: 年 月 日

SH/T 3503— 2017

210

SH/T3503— J808 通用桥式起重机安装

检验记录

工程名称:



单位工程名称:

设备名称 设备 位号

规格型号 起重量 t 跨度 m

制造厂 工作级别 起升高度 m

控制方式 供电方式 工作环境

轨道长度 m 安装地点



检测部位示 意图 单位: mm

检测项目 允许值 实测值 结论

主梁上拱度 F

对角线 L1、 L2的相对差 | L1- L2|

小车轨距 K 跨端 跨中



同一截面上小车轨道高低差 c

主梁旁弯度 f

起重机跨度 S

起重机跨度 S1、 S2的相对差 | S1- S2|

大车车轮水平偏斜 tgφ

同一端梁下大车车轮同位差

结论:

建设 /监理单位 总 承 包 单位 施工单位

专业工程师:





日期: 年 月 日

专业工程师:





日期: 年 月 日

施工班组长:

质量检查员:

专业工程师:

日期: 年 月 日

SH/T 3503— 2017

211

SH/T 3503— J809 双梁通用门式起重机和

装卸桥安装检验记录

工程名称:



单位工程名称:

设备名称 设备 位号

规格型号 起重量 t 跨度 m

制造厂 工作级别 起升高度 m

控制方式 供电方式 工作环境

轨道长度 m 安装地点



检测部位示意图 单位: mm

检测项目 允许值 实测值 结论

起重机跨度 S

起重机跨度 S1、 S2的相对差 | S1- S2|

主梁上拱度 F

悬臂端上翘度 F0

对角线 L1、 L2的相对差 | L1- L2|

主梁旁弯度 f

同一截面上小车轨道高低差 c

小车轨距 K 跨端 跨中



备注:

结论:

建设 /监理单位 总 承 包 单位 施工单位

专业工程师:





日期: 年 月 日

专业工程师:





日期: 年 月 日

施工班组长:

质量检查员:

专业工程师:

日期: 年 月 日



SH/T 3503— 2017

212

SH/T 3503— J810 单主梁门式起重机和

装卸桥安装检验记录

工程名称:



单位工程名称:

设备名称 设备 位号

规格型号 起重量 t 跨度 m

制造厂 工作级别 起升高度 m

控制方式 供电方式 工作环境

轨道长度 m 安装地点



1— 铰接装置; 2— 起升机构车架; 3— 运行机构小车架 ; 4— 车轮组

检测部位示意图 单位: mm

检测项目 允许值 实测值 结论

起重机跨度 S

起重机跨度 S1、 S2的相对差 | S1- S2|

主梁上拱度 F

悬臂端上翘度 F0

主梁旁弯度 f

小车主车轮

与反滚轮的

中心距离

垂直反滚轮式小车 水平距离 K 垂直轨距 K



水平反滚轮式小车 钓钩侧 K2 走台侧 K



水平导向轮轴线对主车轮中心距离的 L1、 L2对称度

结论:

建设 /监理单位 总 承 包 单位 施工单位

专业工程师:





日期: 年 月 日

专业工程师:





日期: 年 月 日

施工班组长:

质量检查员:

专业工程师:

日期: 年 月 日

SH/T 3503— 2017

213

SH/T 3503— J811 臂上起重机和柱式悬臂

起重机安装检验记录

工程名称:



单位工程名称:

设备名称 设备 位号

规格型号 起重量 t 悬臂长度 L0 m

制造厂 工作级别 起升高度 m

控制方 式 安装地点 轨道长度 m



1— 上水平轮轨道; 2— 下水平轮轨道; 1— 上水平轮; 2— 小车 ;

3— 主车轮轨道 3— 下水平轮; 4— 主车轮(垂直轮)

检测部位示意图 单位 : mm

检测项目 允许值 实测值 结论

大车车轮轨道 实际中心线对吊车梁实际中心线位置偏差

纵向倾斜度

下水平轮轨道 顶面至大车车轮轨道中心线距离 a 中心线至大车车轮轨道顶面间距离 c



上水平轮轨道中心线至大车车轮轨道顶面间距离 h

上、下水平轮轨道顶面间的距离 b

起重机 臂 架 上、下水平轮间距 H 小车轨距 K

0

悬臂端翘度 F0

备注:

结论:

建设 /监理单位 总 承 包 单位 施工单位

专业工程师:





日期: 年 月 日

专业工程师:





日期: 年 月 日

施工班组长:

质量检查员:

专业工 程师:

日期: 年 月 日



SH/T 3503— 2017

214

SH/T 3503— J812 起重机械

负荷试验条件确认表

工程名称:



单位工程名称:

设备名称 设备位号 产品编号

规格型号 起重量 t 跨度 m

检 查 项 目 检查结果 建设 /监理 单位 总 承 包 单位 施工 单位 日期

1 安装相关资料



2 安全距离

3 金属结构连接

4 起重机械桥架组装偏差

5 跨度偏差(最大)

6 小车轨距极限偏差

7 轨道接头连接

8 最短轨道长度及挡块

9 司机室固定

10 大车轨距最大偏差

11 轨道接头间隙

12 轨道中心与梁中心偏差

13 轨道固定状况

14 吊钩标记和防脱钩装置

15 钢丝绳选用、安装及绳端固定

16 钢丝绳安全圈数

17 制动器调整

18 减速器联接与固定

19 减速器油位

20 联轴器联接

21 总电源开关



22 总电源回路的短路保护

23 零位保护

24 过流保护

25 照明

26 信号

27 电气设备的接地

28 金属结构的接地

29 手动盘车

30 各润油点润滑

31 供电方式 滑触线 电缆

SH/T 3503— 2017

215

SH/T 3503— J813 起重机械空负荷试验记录

工程名称:



单位工程名称:

设备名称 设备位 号 产品编号

规格型号 起重量 t 跨度 m

执行标准

试验状态与 试验程序 试验要求 试验结果 备注

1 操纵机构的操作方向与起重机各机构运转方向

大车

小车

起升机构

2 大车运行及限位 试验(不少于 5 次)

3 小车运行及限位 试验(不少于 5 次)

4 起升机构运行及限位 试验(不少于 5 次)

5 吊钩下放到最低位置时卷筒上钢丝绳圈数

6 各制动器工作状态

大车

小车

起升机构

7 电缆导电放缆和收缆速度与相应机构的速度

8 各运行机构联动状况

9 安全联锁试验(不少 于 5 次)

10 滑触线安全防护

11 减速器工作状况

12 联轴器工作状况

13 手动盘车至运动系统中最后一根轴旋转一周

结论 :

建设 /监理单位 总 承 包 单位 施工单位

专业工程师:





日期: 年 月 日

专业工程师:





日期: 年 月 日

施工班组长:

质量检查员:

专业工程师:

日期: 年 月 日

SH/T 3503— 2017

216

SH/T 35033503— J814 起重机械负荷试验记录

工程名称:



单位工程名称:

设备名称 设备位号 产品编号

规格型号 起重量 t 跨度 m

执行标准

试验状态与试验程序 试验要求 试验结果 备 注











1 起重机停在立柱位置,小车全行程运行、吊钩升降运行各不少于 3 次,检查机构运转状况 无异常

2

小车停在起重机跨中,逐渐加负荷进行起升运行,加至

额定负荷后,小车在桥架上全程往返运行,检查各部结



无异常

3

小车停在跨中,起升额定重量 1.25 倍负荷,在离地面

200mm 处停留 10min,然后卸去负荷,小车开到跨端,

检 查桥架 金属结构

无异常

4 在 1.25 倍额定负荷下,吊钩起升 3 次,卸去负荷后,小车停到端部,检查桥架上拱度 大于0.7S/1000

5 小车停在跨中,起升额定起重量,离地 200mm, 在跨度中间 S/10 的范围内测量桥架 上拱度 实地测量

6 检查起重机桥架静刚度 (即 5 项与第 4 项之差) S/700~S/1000











1 起重机停在立柱位置,小车全行程运行、吊钩升降运行各不少于 3 次,检查机构运转状况 无异常

2

小车停在起重机跨中,逐渐加负荷进行起升运行,加至

额 定负荷后,小车在桥架上全程往返运行,检查 机 构 动



无异常

3 小车停在跨中,起升额定重量 1.1 倍 负荷, 大车在全程上运行,检查机构动作 无异常

4 在 1.1 倍额定负荷下,吊钩起升 3 次, 检查机构动作 大于0.7S/1000

5 各机构联合运作试运转,检查安全联锁装置 按设备技术 文件规定

结论:



建设 /监理单位 总 承 包 单位 施工单位

专业工程师:





日期: 年 月 日

专业工程师:





日期: 年 月 日

施工班组长:

质量检查员:

专业工程师:

日期: 年 月 日



SH/T 3503— 2017

217

附 录 A

Appendix A

(规范性附录 )

(Normative Appendix)

交工技术文件通用表

Handover Technical Documentation— General

序号

S/N

名 称

Description

编 号

No.

页次

Page No.

A.1 封面 Cover Sheet SH/T 3503— J101A 219

A.2 封面 Cover Sheet SH/T 3503— J101B 220

A.3 交工技术文件总目录 Master Index of Handover Technical Documentation SH/T 3503— J102 221

A.4 交工技术文件目录 Index of Handover Technical Documentation SH/T 3503— J103 222

A.5 交工技术文件说明 General Description on Handover Technical Documentation SH/T 3503— J104 223

A.6 工程施工 开工报告 Construction Commencement Report SH/T 3503- J105A 224

A.7 工程施工开工报告 Construction Commencement Report SH/T 3503- J105B 225

A.8 工程中间交接证书 Interim Handover Certificate SH/T 3503- J106A 226

A.9 工程中间交接证书 Interim Handover Certificate SH/T 3503— J106B 227

A.10 工程交工验收证书 Handover and Acceptance Certificate SH/T 3503— J107A 228

A.11 工程交工验收证书 Handover and Acceptance Certificate SH/T 3503— J107B 229

A.12 交工技术文件移交证书 Handover Technical Documentation Transfer Certificate SH/T 3503— J108A 230

A.13 交工技术文件移交证书 Handover Technical Documentation Transfer Certificate SH/T 3503- J108B 231

A.14 重大质量事故处理报告 Major Quality Defect Disposition Report SH/T 3503— J109 232

A.15 工程设计变更一览表 List of Design Changes SH/T 3503— J110 233

A.16 工程联络单一览表 List of Liaison Sheets SH/T 3503- J111 234

A.17 隐蔽工程验收记录 Concealed Work Acceptance Inspection Record SH/T 3503- J112 235

A.18 垫铁隐蔽记录 Shim Embedding Record SH/T 3503- J113 236

A.19 工程联络单 Liaison Sheet SH/T 3503- J114 237

A.20 合格焊工登记表 Register of Qualified Welders SH/T 3503- J115 238

A.21 无损检测人员登记表

Register of NDE Personnel SH/T 3503- J116 239

SH/T 3503— 2017

218

序号

S/N

名 称

Description

编 号

No.

页次

Page No.

A.22 开箱检验记录

Unpacking Inspection Record SH/T 3503—J117 240

A.23 防腐工程质量验收记录

Painting Quality Acceptance Inspection Record SH/T 3503—J118 241

A.24 隔热工程质量验收记录

Insulation Quality Acceptance Inspection Record SH/T 3503—J119 242

A.25 防腐绝缘层电火花检测报告

Anticorrosive Insulation Holiday Test Report SH/T 3503—J120 243

A.26 防火工程质量验收记录

Fireproofing Quality Acceptance Inspection Record SH/T 3503- J121 244

A.27 接地电阻测量记录

Ground Resistance Measurement Record SH/T 3503—J122 245

A.28 安全阀调整试验记录

Safety Valve Adjustment Test Record SH/T 3503—J123 246

A.29 安全附件安装检验记录

Safety Attachment Installation Inspection Record SH/T 3503—J124 247

A.30 材料及配件超声检测报告

Material & Fitting UT Report SH/T 3503—J125-1 248

A.31 材料及配件超声检测报告(续)

Material & Fitting UT Report (Continued) SH/T 3503—J125-2 249

A.32 材料及配件磁粉检测报告

Material & Fitting MT Report SH/T 3503—J126-1 250

A.33 材料及配件磁粉检测报告(续)

Material & Fitting MT Report (Continued) SH/T 3503—J126-2 251

A.34 材料及配件渗透检测报告

Material & Fitting PT Report SH/T 3503—J127-1 252

A.35 材料及配件渗透检测报告(续)

Material & Fitting PT Report (Continued) SH/T 3503—J127-2 253

A.36 超声测厚报告

Ultrasonic Thickness Measurement Report SH/T 3503—J128-1 254

A.37 超声测厚报告(续)

Ultrasonic Thickness Measurement Report (Continued) SH/T 3503—J128-2 255

A.38 金属材料化学成分检验报告

Metal Material Chemical Composition Test Report SH/T 3503- J129 256

A.39 硬度检测报告

Hardness Test Report SH/T 3503—J130 257

A.40 设备质量证明文件一览表

List of Equipment Quality Certificates SH/T 3503—J131-1 258

A.41 设备质量证明文件一览表(续)

List of Equipment Quality Certificates (Continued) SH/T 3503—J131-2 259

A.42 材料质量证明文件一览表

List of Material Quality Certificates SH/T 3503—J132-1 260

A.43 材料质量证明文件一览表 (续)

List of Material Quality Certificates (Continued) SH/T 3503—J132-2 261

A.44 安装检查记录

Installation Inspection Record SH/T 3503—J133 262

A.45 工程影像记录表

Project Photograph/Video Record Form SH/T 3503—J134 263



SH/T 3503— 2017

219

SH/T 3503— J101A

封 面

Cover Sheet

案卷号:

Dossier No.:









Petrochemical Project Handover Technical

Documentation







Project Name:

Volume Name:











Owner

(Seal of Project

Organization)



Project Manager:



Date:

Supervision Contractor

(Seal of Project

Organization)



Project Director:



Date:

Construction Contractor

(Seal of Project

Organization)



Project Manager:



Date:

SH/T 3503— 2017

220

SH/T 3503— J101B

封 面

Cover Sheet

案卷号:

Dossier No.:









Petrochemical Project Handover Technical

Documentation







Project Name:



Volume Name:



















Owner

(Seal of Project

Organization)







Project Manager:

Date:

Supervision

Contractor

(Seal of Project

Organization)





Project Director:

Date:

General Contractor

(Seal of Project

Organization)







Project Manager:

Date:

Construction

Contractor

(Seal of Project

Organization)





Project Manager:

Date:

SH/T 3503— 2017

221

SH/T 3503— J102

交工技术文件总目录

Master Index of Handover

Technical Documentation

工程名称:

Project Name:





S/N Volume No. Volume Description Page Number



















































Prepared by:

Date:

Reviewed by

Date:



SH/T 3503— 2017

222

SH/T 3503— J103

交工技术文件目录

Index of Handover Technical

Documentation

工程名称:

Project Name:



单位工程名称:

Unit Name:

S/N Document No. Document Description Page Number



















































Prepared by:

Date:

Reviewed by:

Date:



SH/T 3503— 2017

223

SH/T3503— J104

交工技术文件说明

General Description on Handover

Technical Documentation

工程名称:

Project Name:







Prepared by:

Date:

Reviewed by:

Date:



SH/T 3503— 2017

224

SH/T 3503— J105A

工程施工开工报告

Construction Commencement

Report

工程名称:

Project Name:





Construction Contract

No.

Engineering

Contractor

Scheduled

Commencement Date

Scheduled

Completion Date

Scope

of

Wor

k



Com

mencem

ent



Condi

tion





Revi

ew

C

om

ment

s





Qual

ity Sup

ervi

sion

Com

ment

s











Project Quality Supervision Station/Team Leader: (Seal) Date:

Owner Supervision Contractor Construction Contractor

(Seal of Project Organization)

Project Manager:





Date:

(Seal of Project Organization)

Project Director:





Date:

(Seal of Project Organization)

Project Manager:





Date:



SH/T 3503— 2017

225

SH/T 3503— J105B

工程施工开工报告

Construction Commencement

Report

工程名称:

Project Name:





Construction Contract

No.

Engineering

Contractor

Scheduled

Commencement Date

Scheduled

Completion Date

Scope

of

Wor

k



Com

mencem

en

t C

ondi

tion





Revi

ew

C

om

ment

s



Qual

ity Sup

ervi

sion

Com

ment

s











Project Quality Supervision Station/Team Leader: (Seal) Date:

Owner Supervision Contractor General Contractor Construction Contractor

(Seal of Project

Organization)

Project Manager:





Date:

(Seal of Project

Organization)

Project Director:





Date:

(Seal of Project

Organization)

Project Manager:





Date:

(Seal of Project

Organization)

Project Manager:





Date:

SH/T 3503— 2017

226

SH/T 3503— J106A 工程中间交接证书

Interim Handover Certificate

工程名称:

Project Name:





Construction

Contract No.

Handover

Date

Scope

of

Wor

k















Attached: Punch Lists: Copies.

Acce

ptance

Com

ment

s









User’s Representative: Date:

Qu

ali

ty Sup

ervi

sion C

om

me

nts



















Project Quality Supervision Station/Team Leader: (Seal) Date:

Owner Engineering Contractor Supervision Contractor Construction Contractor

(Seal of Project

Organization)

Project Manager:





Date:

(Seal of Project

Organization)

Project Manager:





Date:

(Seal of Project

Organization)

Project Director:





Date:

(Seal of Project

Organization)

Project Manager:





Date:

SH/T 3503— 2017

227

SH/T 3503— J106B 工程中间交接证书

Interim Handover Certificate

工程名称:

Project Name:





Construction

Contract No.

Handover

Date

Scope

of

Wor

k

















Attached: Punch Lists: Copies.

Acce

ptance

Com

ment

s









User’s Representative: Date:

Qual

ity Sup

ervi

sion

Com

ment

s















Project Quality Supervision Station/Team Leader: (Seal) Date:

Owner Engineering Contractor Supervision Contractor General Contractor Construction Contractor

(Seal of Project

Organization)

Project Manager:





Date:

(Seal of Project

Organization)

Project Manager:





Date:

(Seal of Project

Organization)

Project Director:





Date:

(Seal of Project

Organization)

Project Manager:





Date:

(Seal of Project

Organization)

Project Manager:





Date:



SH/T 3503— 2017

228

SH/T 3503— J107A

工程交工验收证书

Handover and Acceptance

Certificate

工程名称:

Project Name:





Construction Contract

No.

Actual

Commencement Date Handover Date

Scope of Work:

Acceptance Inspection Comments:









User’s Representative: Date:

Project Quality Supervision Comments:













Project Quality Supervision Station/Team Leader: (Seal) Date:

Owner Engineering Contractor Supervision Contractor Construction Contractor

(Seal of Project

Organization)

Project Manager:





Date:

(Seal of Project

Organization)

Project Manager:





Date:

(Seal of Project

Organization)

Project Director:





Date:

(Seal of Project

Organization)

Project Manager:





Date:

SH/T 3503— 2017

229

SH/T 3503— J107B

工程交工验收证书

Handover and Acceptance

Certificate

工程名称:

Project Name:





Construction

Contract No.

Actual

Commencement Date Handover Date

Scope of Work:

Acceptance Inspection Comments:











User’s Representative: Date:

Project Quality Supervision Comments:











Project Quality Supervision Station/Team Leader: (Seal) Date:

Owner Engineering Contractor Supervision Contractor General Contractor Construction Contractor

(Seal of Project

Organization)

Project Manager:





Date:

(Seal of Project

Organization)

Project Manager:





Date:

(Seal of Project

Organization)

Project Director:





Date:

(Seal of Project

Organization)

Project Manager:





Date:

(Seal of Project

Organization)

Project Manager:





Date:

SH/T 3503— 2017

230

SH/T 3503— J108A

交工技术文件移交证书

Handover Technical

Documentation Transfer

Certificate

工程名称:

Project Name:

合同编号:

Contract No.:











hereby transfers to handover technical documentation involumes, as-built drawings in

volumes and electronic copy indisks in accordance with the Regulations on Petrochemical

Project Handover Technical Documentation, SH/T 3503— 2017.



Attached: List of Transferred Handover Technical Documentation

Owner Supervision Contractor Contractor

(Seal of Project Organization)

Handled by:





Date:

(Seal of Project Organization)

Reviewed by:





Date:

(Seal of Project Organization)

Handled by:





Date:



SH/T 3503— 2017

231

SH/T 3503— J108B

交工技术文件移交证书

Handover Technical

Documentation Transfer

Certificate

工程名称:

Project Name:

合同编号:

Contract No.:













hereby transfers to handover technical documentation in volumes, as-built drawings in

volumes and electronic copy indisks in accordance with the Regulations on Petrochemical

Project Handover Technical Documentation, SH/T 3503— 2017.



Attached: List of Transferred Handover Technical Documentation

Owner Supervision Contractor General Contractor Construction Contractor

(Seal of Project

Organization)

Handled by:





Date:

(Seal of Project

Organization)

Reviewed by:





Date:

(Seal of Project

Organization)

Handled by:





Date:

(Seal of Project

Organization)

Handled by:





Date:

SH/T 3503— 2017

232

SH/T 3503— J109

重大质量事故处理报告

Major Quality Accident

Disposition Report

工程名称:

Project Name:



Des

cri

pti

on on

Acci

dent















Responsible Organization’s Representative: Responsible Organization (Official Seal) Date:

Di

spos

ition and

Res

ult





















Supervision Contractor’s Project Director: (Official Seal) Date:

Qual

ity Sup

ervi

sion C

om

me

nts



















Project Quality Supervision Station/Team Leader: (Official Seal) Date:

Related Organizations



(Official Seal)

Representative:



Date:



(Official Seal)

Representative:



Date:



(Official Seal)

Representative:



Date:

SH/T 3503— 2017

233

SH/T 3503— J110 工程设计变更一览表 List of Design Changes



工程名称:

Project Name:



单位工程名称:

Unit Name:

Discipline

S/N Change Order No. Cause (s) of Change Drawing No. and Main Points of Change Status of Implementation







































Note: Fill “Design Cause” or “Non-design Cause” in the column of “Cause (s) of Change”.

Owner Supervision Contractor Construction Contractor

Discipline Engineer:







Date:

Discipline Engineer:







Date:

Prepared by:



Reviewed by:



Date:

SH/T 3503— 2017

234

SH/T 3503— J111 工程联络单一览表

List of Liaison Sheets

工程名称:

Project Name:



单位工程名称:

Unit Name:

Discipline

S/N Sheet No. Cause(s) Status of Implementation







































Owner/Supervision Contractor General Contractor Construction Contractor

Discipline Engineer:







Date:

Discipline Engineer:







Date:

Prepared by:



Reviewed by:



Date:

SH/T 3503— 2017

235

SH/T 3503— J112

隐蔽工程验收记录

Concealed Work Acceptance

Inspection Record

工程名称:



单位工程名称:



Concealed

Item

Construction

Drawing No.

Des

cri

pti

on an

d Sket

ch

of

C

onceal

ed

Item

s



Inspe

cti

on R

esul

ts



















Owner/Supervision Contractor General Contractor Construction Contractor

Discipline Engineer:







Date:

Discipline Engineer:







Date:

Foreman:

Quality Inspector:

Discipline Engineer:



Date:

SH/T 3503— 2017

236

SH/T 3503— J113 垫 铁 隐 蔽 记 录 Shim Embedding Record

工程名称:

Project Name:



单位 工程 名 称:

Unit Name:

Equipment/Structure

Description Item No.

Shim Layout:











Description on Shim Conditions:

Flat Shim Size (LWH): Wedge Size (LWH of Thinner End): Gradient:

Shim Set Formation: Piece Number: Shim Set Height:

Inspection Item Installation Requirement Inspection Result

Equipment Alignment Data in conformance with the requirements of the specifications. □ Conforming □Nonconforming

Shim Size In conformance with the requirements of the method statement. □ Conforming □Nonconforming

Shim Arrangement In conformance with the requirements of the specifications. □ Conforming □Nonconforming

Number of Shims Per Set In conformance with the requirements of the specifications. □ Conforming □Nonconforming

Height of Shims Per Set In conformance with the requirements of the design documents and specifications. □ Conforming □Nonconforming

Wedge Overlapping Length In conformance with the requirements of the specifications. □ Conforming □Nonconforming

Fixing of Shims by Tack Welding In conformance with the requirements of the specifications. □ Conforming □Nonconforming

Conclusion:

Shims are verified by inspection as □Nonconforming □Conforming to design and specification requirements

□ Unacceptable for embedment □ Acceptable for embedment

Owner/Supervision Contractor General Contractor Construction Contractor

Discipline Engineer:







Date:

Discipline Engineer:







Date:

Foreman:

Quality Inspector:

Discipline Engineer:



Date:

SH/T 3503— 2017

237

SH/T 3503— J114 工程联络单 Liaison Sheet

工程名称:

Project Name:



单位工程名称:

Unit Name:

Sheet No. Addressed to

Cause(s):

Contents:









Handled by: Raised by (Seal of Project Organization)

Reviewed by: Date:



Receiving Organization’s Disposition Comments:









Handled by: Reviewed by( Seal of Project Organization)

Date: Date:

Countersignature Comments:















Representative:

Signed for and on behalf of:

(Seal of Project Organization)

Date:

Countersignature Comments:















Representative:

Signed for and on behalf of:

(Seal of Project Organization)

Date:

Countersignature Comments:















Representative:

Signed for and on behalf of:

(Seal of Project Organization)

Date:



SH/T 3503— 2017

238

SH/T 3503— J115

合格焊工登记表

Register of Qualified Welders

工程名称:

Project Name:





S/N Name Stamp No. Certificate No. Code of Qualified Item Validity Period













































Owner/Supervision Contractor General Contractor Construction Contractor

Discipline Engineer:







Date:

Discipline Engineer:







Date:

Discipline Engineer:







Date:



SH/T 3503— 2017

239

SH/T 3503— J116 无损检测人员登记表 Register of NDE Personnel

工程名称:

Project Name:





S/N Name Certificate No. Code of Qualified Item Level Validity Period













































Owner/Supervision Contractor General Contractor Inspection Agency

Discipline Engineer:







Date:

Discipline Engineer:







Date:

Discipline Engineer:



Prepared by:



Date:



SH/T 3503— 2017

240

SH/T 3503— J117

开箱检验记录

Unpacking Inspection

Record

工程名称:

Project Name:

单位工程名称:

Unit Name:

Description Item No.

Model Manufacturer

Contractor

No. Total Cases

Case No. Packing List No.

Inspe

cti

on S

tat

us

1. Package

2. Size against Packing List

3. Quantity against Packing List

4. Appearance

5. Quality Certificate

6. Technical Documents

□ No Damage

□ Conforming

□ Conforming

□ No Visible Defect

□ Yes

□ Yes

□ Damaged

□ Nonconforming

□ Nonconforming

□ Visible Defect

□ No

□ No

Exis

ting

Iss

ues

and

Di

spos

ition



Com

ment

s



Del

iver

y

At

tached

Docum

ent

ati

on



Description Copy Number Receiving Organization Recipient







Speci

al

Tool

s Description Q’ty Receiving Organization Recipient







Owner Supervision Contractor General Contractor Construction Contractor Procurement Contractor

Discipline Engineer:



Date:

Discipline Engineer:



Date:

Discipline Engineer:



Date:

Discipline Engineer:



Date:

Inspector:



Date:

SH/T 3503— 2017

241

SH/T 3503— J118

防腐工程质量验收记录

Painting Quality Acceptance

Inspection Record

工程名称:

Project Name:

单位工程名称:

Unit Name:

Pre-application

Surface Condition

Pai

nti

ng

Locat

ion





Coat

St

ruct

ure

and

Re

qu

ire

me

nt



Inspection Item and Requirement Results

Raw material shall meet the design and relevant specification requirements, and bear

relevant quality certificate and retest report.

Strength test and tightness test shall be carried out on equipment and piping. Sequence

release records shall be made available.

Surface preparation shall be made properly and up to the grade specified by the design.

Isolating course material shall be correctly applied with coat number or thickness as

required.

The mix ratio and test of anticorrosive coat materials shall meet the relevant

specification requirements. Reports shall be complete.

Primer shall be correctly applied with coat number and thickness as required.

Intermediate coat shall be correctly applied with coat number and thickness as required.

Finish shall be correctly applied with coat number and thickness as required.

Location Material Description Designation Manufacturer

Design Film

Thickness

mm

Actual Total Film

Thickness

mm

Primer





Intermediate

Coat

Finish

Conclusion:

Owner/Supervision Contractor General Contractor Construction Contractor

Discipline Engineer:







Date:

Discipline Engineer:







Date:

Foreman:

Quality Inspector:

Discipline Engineer:



Date:

SH/T 3503— 2017

242

SH/T 3503— J119

隔热工程质量验收记录

Insulation Quality

Acceptance Inspection Record

工程名称:

Project Name:



单位工程名称:

Unit Name:

Insul

ated

Locat

ions







Insul

ati

on

Str

uct

ure





Inspection Item and Requirement Inspection Result

Raw material shall meet the design and relevant specification requirements, and bear relevant

mill certificate and retest report.

Pressure test and painting shall be completed for equipment and piping.

Sequence release records shall be made available.

Insulation at pipe supports and brackets shall not affect free expansion of the moving parts.

Insul

ati

on



Prefabricated products shall be installed with joints in the same layer staggered,

joints between the outer layer and the inner layer overlapped, expansion joints

correctly arranged, and caulking filled or affixed tightly with thickness maintained

within tolerance specified in the applicable specifications.



Wrapping material shall be applied tightly in the same layer and in different

directions between the inner layer and the outer layer, with joints staggered, and with

thickness deviation maintained within tolerance specified in the applicable

specifications.



Bulk material and castable shall be installed and compacted uniformly with thickness

deviation maintained within tolerance specified in the applicable specifications.

Vapor



Bar

rier

Vapor barrier shall be applied on the insulation with surface maintained level, with

thickness as specified by the applicable specifications, and free of defects such as

peeling or bubbling.



Prot

ect

ive Layer

Metal cladding shall be overlapped with joints and surface levelness in compliance with the relevant specification requirements, and be free of defects such as peeling or

irregularity.



Protective roll shall be applied in close contact with the surface and free of defects

such as wrinkle or crack.

Finished protective layer shall be level, smooth, with trimmed corners, and free of

visible crack. Surface levelness shall meet the requirement of the applicable

specifications.



Conclusion:

Owner/Supervision Contractor General Contractor Construction Contractor

Discipline Engineer:







Date:

Discipline Engineer:







Date:

Foreman:

Quality Inspector:

Discipline Engineer:



Date:

SH/T 3503— 2017

243

SH/T 3503— J120

防腐绝缘层电火花检测报告

Anticorrosive Insulation

Holiday Test Report

工程名称:

Project Name:



单位工程名称:

Unit Name:

Test Agency Report No.

Equip. Item No. /

Piping No. (Line

No.)

Description

Anticorrosion

Grade

Applicable

Standard

Design Thickness mm Anticorrosion Type Voltage V

Test Location Test Result Test Location Test Result



































Remarks:

Tested by:



Date:

Quality Engineer:

Date:

SH/T 3503— 2017

244

SH/T 3503— J121

防火工程质量验收记录

Fireproofing Quality

Acceptance Inspection Record

工程名称:

Project Name:



单位工程名称:

Unit Name:

Fir

epr

oof

ing L

ocat

ion





Fir

epr

oof

ing S

truct

ure





Inspection Item and Requirement Inspection Result

Raw materials shall meet the design and relevant specification requirements, and

bear relevant quality certificate and retest report.

Anticorrosion coating shall be completed.

Sequence release record shall be made available.

The fireproofing surface shall be even and smooth with thickness deviation

maintained within the tolerance specified in the applicable specifications.

Conclusion:

Owner/Supervision Contractor General Contractor Construction Contractor

Discipline Engineer:







Date:

Discipline Engineer:







Date:

Foreman:

Quality Inspector:

Discipline Engineer:



Date:

SH/T 3503— 2017

245

SH/T 3503— J122

接地电阻测量记录

Ground Resistance

Measurement Record

工程名称:

Project Name:



单位工程名称:

Unit Name:

Discipline Construction Drawing No. Measuring Date

Grounding

Type

Measuring

Instrument

Model

Allowable Value Ω

Ground Resistance Measurement Record

S/N Measured Point

Actual

Value

Ω

Relative

Humidity

%

Measuring

Time

Weather Conditions of Current

Day and Last Three Days























Conclusion:

Sketch Showing Locations of Check Points:

Owner/Supervision Contractor General Contractor Construction Contractor

Discipline Engineer:







Date:

Discipline Engineer:







Date:

Foreman:

Quality Inspector:

Discipline Engineer:



Date:

SH/T 3503— 2017

246



SH/T 3503— 2017

247

SH/T 3503— J124

安全附件安装检验记录

Safety Attachment Installation

Inspection Record

工程名称:

Project Name:



单位工程名称:

Unit Name:

Pipeline/

Equipment Item No. Description Model/Size Certificate No.

Inspection

Result









































Owner/Supervision Contractor General Contractor Construction Contractor

Discipline Engineer:







Date:

Discipline Engineer:







Date:

Foreman:

Quality Inspector:

Discipline Engineer:



Date:



SH/T 3503— 2017

248

SH/T 3503— J125-1

材料及配件超声检测报告

Material & Fitting UT Report

第 页 共 页 Page of

工程名称:

Project Name:



单位工程名称:

Unit Name:

Entrusted

by

Construction

Contractor

Report

No.

Test Piece

Description

Test

Criteria

Qualified

Level

Test

Sensitivity

Acceptance

Criteria

Test

Percentage Couplant HT Status

Probe Test Coupon Test

Surface

Equipment

Model

Surface

Condition

Surface

Compensation

Scanning

Percentage S/N Model Model 1 Model 2







Quality

Certificate No.

Heat/Lot

No.

Test Piece

No.

Test Piece

Specification

Test Piece

Material

Probe

No.

Defect Description/

Sketch No.

Evaluated

Level

































Tested by:

Qualification: UT Level

Reviewed by:

Qualification: UT Level

Inspection Agency: (Official Seal)

Report Date:

SH/T 3503— 2017

249

SH/T 3503— J125-2

材料及配件超声检测报告 (续)

Material & Fitting UT

Report (Continued)

第 页 共 页 Page of

工程名称:

Project Name:



单位工程名称:

Unit Name:

Entrusted

by

Construction

Contractor

Report

No.

Quality

Certificate No.

Heat/Lot

No.

Test Piece

No.

Test Piece

Specification

Test Piece

Material

Probe

No.

Defect Description/

Sketch No.

Evaluated

Level























































SH/T 3503— 2017

250

SH/T 3503— J126-1

材料及配件磁粉检测报告

Material & Fitting MT Report

第 页 共 页 Page of

工程名称:

Project Name:



单位工程名称:

Unit Name:

Entrusted by Construction Contractor Report No.

Test Piece

Description Test Criteria

Qualified

Level

Sensitivity

Test Coupon

Acceptance

Criteria

Test

Percentage

Surface

Condition HT Status

Magnetization

Method

Current

Type

Magnetization

Time Lift/Current

Concentration

of Suspension

Magnetic

Powder

Type

Equipment Model Pole Distance

Quality

Certificate

No.

Heat/Lot

No.

Test Piece

No.

Test Piece

Specification

Test Piece

Material

Test

Surface

Defect Description/

Sketch No.

Evaluated

Level







































Tested by:

Qualification: MT Level

Reviewed by:

Qualification: MT Level

Inspection Agency: (Official

Seal)

Report Date:

SH/T 3503— 2017

251

SH/T 3503— J126-2

材料及配件磁粉检测报告 (续)

Material & Fitting MT Report

(Continued)

第 页 共 页 Page of

工程名称:

Project Name:



单位工程名称:

Unit Name:

Entrusted by Construction Contractor Report No.

Quality

Certificate No. Heat/Lot No.

Test Piece

No.

Test Piece

Specification

Test Piece

Material

Test

Surface

Defect Description/

Sketch No.

Evaluated

Level



















































SH/T 3503— 2017

252

SH/T 3503— J127-1

材料及配件渗透检测报告

Material & Fitting PT Report

第 页 共 页 Page of

工程 名称:

Project Name:



单位工程名称:

Unit Name:

Entrusted by Construction Contractor Report No.

Test Piece

Description Test Criteria

Qualified

Level

Test

Sensitivity

Acceptance

Criteria

Test

Percentage

Surface

Condition HT Status

Test Method Test Coupon Observation Method Penetrant Designation

Penetration

Temperature

Penetration

Time

Developing

Time

Application

Method

Quality

Certificate No.

Heat/Lot

No.

Test Piece

No.

Test Piece

Specification

Test Piece

Material Test Surface

Defect Description/

Sketch No.

Evaluated

Level





































Tested by:

Qualification: PT Level

Reviewed by:

Qualification: PT Level

Inspection Agency: (Official Seal)

Report Date:



SH/T 3503— 2017

253

SH/T 3503— J127-2

材料及配件渗透检测报告 ( 续)

Material & Fitting PT Report (Continued)

第 页 共 页 Page of

工程名称:

Project Name:



单位工程名称:

Unit Name:

Entrusted by Construction Contractor Report No.

Quality

Certificate No. Heat/Lot No.

Test Piece

No.

Test Piece

Specification

Test Piece

Material

Test

Surface

Defect Description/

Sketch No.

Evaluated

Level



















































SH/T 3503— 2017

254

SH/T 3503— J128-1

超声测厚报告

Ultrasonic Thickness

Measurement Report

第 页 共 页 Page of

工程名称:

Project Name:



单位工程名称:

Unit Name:

Entrusted by Construction Contractor Report No.

Test Piece

Description Test Criteria

Acceptance

Criteria

Test Piece

Specification

Test Piece

Material

Test

Percentage

Couplant Equipment Model Measurement Precision mm

Test Position No.

Nominal

Thickness

mm

Actual

Thickness

mm

Test Position No.

Nominal

Thickness

mm

Actual

Thickness

mm

































Conclusion:

Totally points are tested, where points are conforming and points are nonconforming. For specific test

positions, see the sketch.

Tested by:



Reviewed by:



Inspection Agency: (Official Seal)

Report Date:

SH/T 3503— 2017

255

SH/T 3503— J128-2

超声测厚报告 (续)

Ultrasonic Thickness Measurement

Report (Continued)

第 页 共 页 Page of

工程名称:

Project Name:



单位工程名称:

Unit Name:

Entrusted by Construction Contractor Report No.

Test Position No.

Nominal

Thickness

mm

Actual

Thickness

mm

Test Position No.

Nominal

Thickness

mm

Actual

Thickness

mm



















































SH/T 3503— 2017

256

SH/T 3503— J129

金属材料化学成分检验报告

Metal Material Chemical

Composition Test Report

第 页 共 页 Page of

工程名 称:

Project Name:



单位工程名称:

Unit Name:

Entrusted by Construction Contractor Report No.

Test Piece

Description Test Criteria

Material

Specification

Test Method Equipment Model Test Piece Material

Quality Certificate

No./Heat No. or

Lot No.

Test Position No. Specification

Element Content %







































Conclusion:

Totally points are tested, where points are conforming and points are nonconforming. For specific test

positions, see the sketch.

Tested by:

Qualification:

Reviewed by:

Qualification:

Inspection Agency: (Official Seal)

Report Date:

SH/T 3503— 2017

257

SH/T 3503— J130

硬度检测报告

Hardness Test Report

第 页 共 页 Page of

工程名称:

Project Name:



单位工程名称:

Unit Name:

Entrusted by Construction Contractor Report No.

Test Piece

Description Test Criteria

Material

Specification

Test Piece

Specification

Test Piece

Material Test Percentage

Test Method HT Status Equipment Model

Test Position No. Hardness Value Test Position No. Hardness Value Test Position No. Hardness Value



































Conclusion:

Totally points are tested, where points are conforming and points are nonconforming. For specific test

positions, see the sketch.

Tested by:

Qualification:

Reviewed by:

Qualification:

Inspection Agency: (Official Seal)

Report Date:

SH/T 3503— 2017

258



SH/T 3503— 2017

259

SH/T 3503— 2017

260

SH/T 3503— 2017

261



SH/T 3503— 2017

262

SH/T 3503— J133

安装检查记录

Installation

Inspection Record

工程名称:

Project Name:



单位工程名称:

Unit Name:

Discipline Construction Drawing No.

Inspection Items:



























Inspection Conclusion:



















Owner/Supervision Contractor General Contractor Construction Contractor

Discipline Engineer:







Date:

Discipline Engineer:







Date:

Foreman:

Quality Inspector:

Discipline Engineer:



Date:



SH/T 3503— 2017

263

SH/T 3503— J134

工程影像记录表

Project Photograph/Video

Record Form

工程名称:

Project Name:



单位工程名称:

Unit Name:

Item No. Photo/Video Recording Date

Position



Photograph/Video:



Description:











Date:

Recording Organization Confirming Organization Construction Contractor

Recorded by:







Date:

Confirmed by:







Date:

Discipline Engineer:







Date:

SH/T 3503— 2017

264

附 录 B

Appendix B

(规范性附录 )

(Normative Appendix)

交工技术文件土建工程用表

Handover Technical Documentation— Civil

序号

S/N

名 称

Description

编 号

Reference No.

页次 Page

No.

B.1

地基验槽(坑)记录

Foundation Trench/Pit Inspection Record SH/T 3503— J201 256

B.2

地基处理记录

Foundation Treatment Record SH/T 3503— J202 266

B.3

工程定位测量记录

Project Location Survey Record SH/T 3503— J203 267

B.4

设备基础复测记录

Equipment Foundation Remeasurement Record SH/T 3503- J204 268

B.5

块体式设备基础允许偏差项目复测记录

Block Type Equipment Foundation Allowable Deviation

Item Remeasurement Record

SH/T 3503- J205 269

B.6

整体框架式设备基础允许偏差项目复测记录

Frame Type Equipment Foundation Allowable Deviation

Item Remeasurement Record

SH/T 3503- J206 270

B.7

储罐基础允许偏差项目复 测记录(一)

Storage Tank Foundation Allowable Deviation Item

Remeasurement Record (I)

SH/T 3503— J207- 1 271

B.8

储罐基础允许偏差项目复测记录(二)

Storage Tank Foundation Allowable Deviation Item

Remeasurement Record (II)

SH/T 3503— J207- 2 272

B.9

球形储罐基础允许偏差项目复测记录

Spherical Tank Foundation Allowable Deviation Item

Remeasurement Record

SH/T 3503— J208 273

B.10

基础沉降观测记录

Foundation Settlement Observation Record SH/T 3503— J209 274

B.11

水池蓄水试验记录

Water Basin Impoundment Test Record SH/T 3503— J210 275

B.12

土建隐蔽工程验收记录

Concealed Civil Work Acceptance Inspection Record SH/T 3503— J211 276

B.13

防水工程试水、蓄水通用检查记录

Waterproofing Work General Water Test and Impoundment

Inspection Record

SH/T 3503— J212 277



SH/T 3503— 2017

265

SH/T 3503— J201

地基验槽(坑)记录

Foundation Trench/Pit

Inspection Record

工程名称:

Project Name:



单位 工程名称:

Unit Name:

Construction

Drawing No.

Trench/Pit

Inspection Location

Excav

ati

on





1. Dimension:________________________________________________________

2. Excavation Sketch:

Tr

ench/

Pit

Inspe

cti

on



1. The excavation of foundation trench/pit is performed to Course ______ as indicated in the survey

report. The bearing course is Course__________.

2. The absolute altitude and relative elevation of the foundation bottom are__________respectively.

3. Soil condition __________________________________________________________________.

4. Pile location_______, pile type________ and pile number________. The bearing capacity shall

meet the design requirements.

5. Others.





Attached: □ Construction Record(s); □ Pile Test Report(s).

Note: If no piling or manual shoring is involved in the civil work, Item 4 shall be crossed out.

Inspe

cti

on

Concl

usi

on











□ Normal and allowed to be released to the subsequent sequence □ Requiring foundation preparation

□ Inspection photo/video attached

Owner/Supervision

Contractor

Engineering Contractor/

General Contractor Survey Contractor Construction Contractor

Discipline Engineer:







Date:

Discipline Engineer:







Date:

Discipline Engineer:







Date:

Filled out by:

Quality Inspector:

Discipline Engineer:



Date:

SH/T 3503— 2017

266

SH/T 3503— J202

地基处理记录

Foundation Treatment

Record

工程名称:

Project Name:



单位工程名称:

Unit Name:

Construction

Date Day Month Year to Day Month Year

Treatment Basis:

Construction drawing No., design change/negotiation (No.) and current relevant national code and standards.

Treatment Method:



Treatment Location and Conditions (or Shown in Sketch):

Treatment Result:









Attached: □ Construction Record(s); □ Test Report(s)

Inspection Conclusion:







□ Acceptable and allowed to be released to the subsequent sequence

□ Unacceptable and to be re-checked after correction □ Inspection photo/video attached

Owner/Supervision

Contractor

Engineering Contractor/

General Contractor Survey Contractor Construction Contractor

Discipline Engineer:





Date:

Discipline Engineer:





Date:

Discipline Engineer:





Date:

Quality Inspector:

Discipline Engineer:



Date:

SH/T 3503— 2017

267

SH/T 3503— J203 工程定位测量记录

Project Location Survey Record

工程名称:

Project Name:



单位工程名称:

Unit Name:

Entrusted by Construction Drawing No.

Reference

Altitude

Reference Planar

Coordinate

Allowable

Deviation mm Instrument Model

Survey Date Instrument Calibration Date

Locat

ion S

urvey

Sket

ch





Surve

y C

on

clusi

on



Owner/Supervision

Contractor General Contractor Construction Contractor Survey Contractor

Discipline Engineer:







Date:

Discipline Engineer:







Date:

Discipline Engineer:







Date:

Surveyor:

Reviewer:

Discipline Engineer:



Date:

SH/T 3503— 2017

268

SH/T 3503— J204

设备基础复测记录

Equipment Foundation

Remeasurement Record

工程名称:

Project Name:



单位工程名称:

Unit Name:

Foundation

Description

Item No. Construction

Drawing No.



Derived Point

Stake No.

Derived Point

Elevation m

Elevation

±0.00 m

Measuring

Instrument

Remeasurement

Date

Instrument

Calibration Date



Remeasuring

Item

Description

Check

Point No.

Design

Coordinates

m

Coordinate

Difference

mm

Check

Point No.

Design

Coordinates

m

Actual

Elevation

m

Elevation

Difference

mm

X Y ?X ?Y + -

















Sketch Showing Numbering of Check Points:

Confirmation on Remeasurement Results:

Owner/Supervision Contractor General Contractor Construction Contractor



Discipline Engineer:







Date:

Discipline Engineer:







Date:

Surveyor:

Quality Inspection:

Discipline Engineer:



Date:



SH/T 3503— 2017

269

SH/T 3503— J205

块体式设备基础

允许偏差项目复测记录

Block Type Equipment Foundation Allowable Deviation

Item Remeasurement Record

工程名称:

Project Name:



单位工程名称:

Unit Name:

Foundation Description Equipment Item No.

Construction Drawing No. Remeasurement Date

S/N Remeasurement Item

Allowable

Deviation

mm

Actual Deviation at Check Points, mm

1 2 3 4 5 6 7 8 9 10

1 Axis Position 20

2 Elevations of Different Levels of Foundation 0, -20

3

Geometric Dimension of Foundation ±20

Geometric Dimension of Foundation’s

Convex Section 0, -20

Dimension of Foundation’s Concave Section +20, 0

4

Foundation Surface Levelness

(Incl. equipment part to be

installed on the grade)

Per Meter 5

Full Length 10

5 Lateral Foundation Plumbness Per Meter 5 Full Length 10

6 Embedded Anchor Bolt

Elevation (Top) +10, 0

Central Distance (btw. Top

and Bottom) ±2

7

Precast Hole

For Anchor

Bolt

Central Position ±10

Depth +20, 0

Hole Wall Plumbness 10

8

Embedded

Removable

Anchor

Plate for

Anchor Bolt

Elevation +20, 0

Central Position ±5

Level-

ness

Anchor Plate with

Notch 5

Anchor Plate with

Threaded Hole 2

9

Embedded

Removable

Anchor

Sleeve

Center Distance ±5

Plumbness 5

Diagonal length and Center

Circle Diameter ±5

Offset Relative to

Foundation Center 5

Confirmation on Remeasurement Results (for locations of check points, see the attached sketch):

Taking-over Party Owner/Supervision Contractor General Contractor Construction Contractor

Discipline Engineer:





Date:



Discipline Engineer:





Date:

Discipline Engineer:





Date:

Quality Inspector:

Discipline Engineer:



Date:



SH/T 3503— 2017

270

SH/T 3503— J206

整体框架式设备基础

允许偏差项目复测记录

Frame Type Equipment

Foundation Allowable Deviation

Item Remeasurement Record

工程名称:

Project Name:





单位工程名称:

Unit Name:

Foundation Description Equipment Item No.

Construction Drawing

No. Remeasurement Date

S/N Remeasurement Item

Allowable

Deviation

mm

Actual Deviation at Check Points, mm

1 2 3 4 5 6 7 8 9 10

1 Axial



Di

spl

acem

ent

Foundation 15



Independent

Foundation 10

Column/Beam 8

2

Plum

bnes

s

Int

erl

evel



5m and below 8

5m above 10

Full Height H/1 000 And ≤ 30

3

Elevat

ion



Level Height ±10

Full Height ±10

4 Sectional Dimension +8 -5

5 Surface Levelness (Checked with 2m ruler) 8

6

Di

spl

ace

me

nt

of

Em

bed

ded

Fa

cil

ity

Cent

er

Embedded Item 5

Embedded

Anchor Bolt 2

Embedded Pipe 3

7 Displacement of Precast Hole Center 10

Note: H is the full height of the structure. For locations of check points, see the attached sketch.

Confirmation on remeasurement results:

Taking-over Party Owner/Supervision Contractor General Contractor Construction Contractor

Discipline Engineer:





Date:



Discipline Engineer:





Date:

Discipline Engineer:





Date:

Quality Inspector:

Discipline Engineer:



Date:



SH/T 3503— 2017

271

SH/T 3503— J207-1

储罐基础允许偏差项目

复测记录(一)

Storage Tank Foundation Allowable Deviation Item

Remeasurement Record (I)

工程名称:

Project Name:



单位工程名称:

Unit Name:

Tank Item No. Remeasurement Date

Tank Capacity m3 Tank Diameter m

Deviation in

Elevation of

Foundation Center

mm

Allowable

Value ±20

Deviation in

Location of

Foundation Center

mm

Allowable

Value 20 Diameter Tolerance

mm

Allowable

Value

+ 30

0

Actual

Value

Actual

Value

Actual

Value



Layout

of

St

orage

Ta

nk

Con

cent

ric Cir

cles

and

Chec

k Po

int

s

Conf

irm

ati

on on

Rem

eas

urem

ent

R

esul

ts

Taking-over Party Owner/Supervision Contractor General Contractor Construction Contractor

Discipline Engineer:





Date:



Discipline Engineer:





Date:

Discipline Engineer:





Date:

Quality Inspector:

Discipline Engineer:



Date:



SH/T 3503— 2017

272

SH/T3503-J207-2

储罐基础允许偏差项目

复测记录(二)

Storage Tank Foundation

Allowable Deviation Item

Remeasurement Record (II)

工程名称:

Project Name:



单位工程名称:

Unit Name:

Tank Item

No.

Remeasurement

Date

Concentric

Circle No./

Parallel

Line No.

Calculated

Elevation

mm

Actual Check Point Elevation Difference

mm

Max. Height

Difference

btw. Any

Two Points

mm

Max. Height

Difference btw.

Two Adjacent

Points

mm



































Note: The Concentric Circle No. shall be indicated with Roman numerals while the Check Point No. shall be

shown with Arabic numerals.

Taking-over Party Owner/Supervision Contractor General Contractor Construction Contractor

Discipline Engineer:





Date:

Discipline Engineer:





Date:

Discipline Engineer:





Date:

Quality Inspector:

Discipline Engineer:



Date:

SH/T 3503— 2017

273

SH/T 3503— J208

球形储罐基础允许偏差

项目复测记录

Spherical Tank Foundation Allowable Deviation Item

Remeasurement Record

工程名称:

Project Name:



单位工程名称:

Unit Name:

Spherical Tank

No. Remeasurement Date

Spherical Tank

Diameter m

Spherical Tank

Capacity m

3

Foundat

ion

No.

Remeasurement Item Deviation in Distance btw.

Anchor Bolt

and Central

Circle of

Foundation

S1 mm

Deviation in

Distance btw.

Center of Precast

Hole and Central

Circle of

Foundation

S2 mm

Deviation in

Distance btw.

Centers of Two

Adjacent

Support

Foundations

ΔS mm

Foundation

Central Circle

Diameter

Deviation

mm

Foundation

Orientation

Deviation

(°)

Foundation

Elevation

Deviation

mm

Foundation

Levelness

Deviation

mm Inner Outer Inner Outer Inner Outer

1

2

3

4

5

6

7

8

9

10

11

12

13

14

15

16

Confirmation on Remeasurement Results (for the spherical tank foundation plan, see the attached):

Taking-over Party Owner/Supervision Contractor General Contractor Construction Contractor

Discipline Engineer:





Date:

Discipline Engineer:





Date:

Discipline Engineer:





Date:

Quality Inspector:

Discipline Engineer:



Date:



SH/T 3503— 2017

274

SH/T 3503— J209

基础沉降观测记录

Foundation Settlement

Observation Record

工程名称:

Project Name:



单位工程名称:

Unit Name:

Foundation

Description

Equipment

Item No.

Geometric

Dimension Capacity

Benchmark

No.

Benchmark

Elevation

Observation

Instrument

Instrument

Precision

Instrument

Calibration Date

Observation

Date Started at and ended at

Observation

Phase

Observation

Time

Settlement at Check Points, mm

1 2 3 4 5 6 7 8 9 10 11 12 13 14



















Foundation Check Point Plan:

Observation Result Analysis and Conclusion:

Owner/Supervision

Contractor General Contractor Construction Contractor Survey Contractor

Discipline Engineer:







Date:

Discipline Engineer:







Date:

Discipline Engineer:







Date:

Surveyor:

Reviewer:

Discipline Engineer:



Date:



SH/T 3503— 2017

275

SH/T 3503— J210

水池 蓄水试验记录

Water Basin Impoundment

Test Record

工程名称:

Project Name:



单位工程名称:

Unit Name:

Description Item No.

Construction Waterproofing Grade

Planar Dimension

(L×W) m Water Area A1 m

2

Allowable

Infiltration, q0 L/( m

2·d) Wet Area A

2 m

2

Water Depth m Test Date Started at Ended at

Measurement Record Initial Reading Final Reading Reading Difference

Water Level Reading

E, mm E1 E2 E1- E2

Evaporation Water

Basin Water Level

Reading e, mm

e1 e2 e1- e2

Water

Temperature, ℃ -

Ambient

Temperature, ℃ -

Measurement Reading

Time (Month, Day,

Hour, Minute)



Actual Infiltration q

q= A1 /A2[(E1- E2)

- ( e1- e2)]

L/( m2·d)

Ratio of Actual

Infiltration to

Allowable Infiltration

q/q0

%

Test Result:

Owner/Supervision Contractor General Contractor Construction Contractor

Discipline Engineer:





Date:

Discipline Engineer:





Date:

Quality Inspector:

Discipline Engineer:



Date:



SH/T 3503— 2017

276

SH/T 3503— J211

土建隐蔽工程验收记录

Concealed Civil Work

Acceptance Inspection

Record

工程名称:

Project Name:



单位工程名称:

Unit Name:

Inspection

Item

Inspection

Date

Inspection

Location

Level/Axis/

Elevation

Concealed Work Inspection Basis: Construction drawing No., design change/negotiation (No.) and current

relevant national standards.



Description, Specification and Type of Major Materials:



Concealed Work Inspection Coverage:





Inspection Comments:



□ Agreed to be concealed

□ Disagreed to be concealed, to be re-inspected after correction

□ Inspection photo/video attached

Re-inspection Conclusion:



Re-inspected by:Re-inspection Date:

Owner/Supervision Contractor General Contractor Construction Contractor

Discipline Engineer:





Date:

Discipline Engineer:





Date:

Quality Inspector:

Discipline Engineer:



Date:



SH/T 3503— 2017

277

SH/T 3503— J212

防水工程试水、蓄水

通用检查记录

Waterproofing Work General

Water Test and Impoundment

Inspection Record

工程名称:

Project Name:



单位工程名称:

Unit Name:

Item No. Inspection Date

Inspection Location Impoundment Time Start at End at

Inspection Basis: Construction drawing No., design change/negotiation (No.) and current relevant national

standards.



Inspection Method and Coverage:



Inspection Comment:



□ Acceptable, allowed to be released to the subsequent sequence

□ Unacceptable, to be re-inspected after correction

□ Inspection photo/video attached

Re-inspection Conclusion:





Re-inspected by:Re-inspection Date:

Owner/Supervision Contractor General Contractor Construction Contractor

Discipline Engineer:





Date:

Discipline Engineer:





Date:

Quality Inspector:

Discipline Engineer:



Date:



SH/T 3503— 2017

278

附 录 C

Appendix C

(规范 性 附录 )

(Normative Appendix)

交工技术文件设备安装工程用表

Handover Technical Documentation— Equipment Installation

序号

S/N

名 称

Description

编 号

Reference No.

页次

Page No.

C.1 机器安装检验记录 Mechanical Equipment Installation Inspection Record SH/T 3503— J301 282

C.2 轴对中记录 Shaft Alignment Record SH/T 3503— J302 283

C.3 机组轴对中记录 Machine Train Shaft Alignment Record SH/T 3503— J303 284

C.4 空冷式换热器风机安装检验记录 Air-Cooled Heat Exchanger Fan Installation Inspection Record SH/T 3503— J304 285

C.5 机器组装质量确认记录 Mechanical Equipment Assembling Quality Confirmation Record SH/T 3503- J305 286

C.6 往复式压缩机找平找正记录(卧式)

Reciprocating Compressor Leveling and Alignment Record

(Horizontal)

SH/T 3503- J306 287

C.7 往复式压缩机找平找正记录(立式) Reciprocating Compressor Leveling and Alignment Record (Vertical) SH/T 3503- J307 288

C.8 往复式压缩机曲柄臂间距检查记录 Reciprocating Compressor Crank Spread Inspection Record SH/T 3503— J308 289

C.9

往复式压缩机主轴轴线与中体滑道轴线垂直度检查记录

Reciprocating Compressor Main Shaft and Intermediate Frame

Guide Axial Plumbness Inspection Record

SH/T 3503— J309 290

C.10

往复式压缩机主轴瓦与推力轴瓦间隙检查记录

Reciprocating Compressor Mainshaft Bearing Liner and

Thrust Bearing Liner Clearance Inspection Record

SH/T 3503— J310 291

C.11

往复式压缩机十字头与中体滑道间隙检查记录(卧式)

Reciprocating Compressor Crosshead and Intermediate Frame

Guide Clearance Inspection Record (Horizontal)

SH/T 3503— J311 292

C.12

往复式压缩机十字头与中体滑道间隙检查记录(立式)

Reciprocating Compressor Crosshead & Intermediate Frame

Guide Clearance Inspection Record (Vertical)

SH/T 3503— J312 293



SH/T 3503— 2017

279

序号

S/N

名 称

Description

编 号

Reference No.

页次

Page No.

C.13 往复式压缩机连杆组装记录 Reciprocating Compressor Connecting Rod Assembling Record SH/T 3503— J313 294

C.14 往复式压缩机气缸余隙检查记录 Reciprocating Compressor Cylinder Clearance Inspection Record SH/T 3503— J314 295

C.15

往复式压缩机活塞与气缸圆周间隙检查记录

Reciprocating Compressor Piston and Cylinder

Circumferential Clearance Inspection Record

SH/T 3503— J315 296

C.16 往复式压缩机活塞环安装记录 Reciprocating Compressor Piston Ring Installation Record SH/T 3503— J316 297

C.17

往复式压缩机填料函各部间隙检查记录

Reciprocating Compressor Stuffing Box Clearance Inspection

Record

SH/T 3503— J317 298

C.18 机器单机试车记录 Mechanical Equipment Solo Test Run Record SH/T 3503— J318-1 299

C.19 ____设备单机试车记录 ____Equipment Solo Test Run Record SH/T 3503— J318-2 300

C.20 机组试车条件确认记录 Machine Train Readiness for Test Run Confirmation Record SH/T 3503— J319 301

C.21 往复式压缩机试车记录 Reciprocating Compressor Test Run Record SH/T 3503— J320- 1 302

C.22 往复式压缩机试车记录(续) Reciprocating Compressor Test Run Record (Continued) SH/T 3503— J320- 2 303

C.23 离心式压缩机试车记录 Centrifugal Compressor Test Run Record SH/T 3503— J321- 1 304

C.24 离心式压缩机试车记录(续 1) Centrifugal Compressor Test Run Record (Continued 1) SH/T 3503— J321- 2 305

C.25 离心式压缩机试车记录(续 2) Centrifugal Compressor Test Run Record (Continued 2) SH/T 3503— J321- 3 306

C.26 汽轮机 /燃气轮机试车记录 Steam/Gas Turbine Test Run Record SH/T 3503— J322- 1 307

C.27 汽轮机 /燃气轮机试车记录(续) Steam/Gas Turbine Test Run Record (Continued) SH/T 3503— J322- 2 308

C.28 电动机试车记录 Motor Test Run Record SH/T 3503— J323 309

C.29 变速器试车记录 Transmission Test Run Record SH/T 3503— J324 310

C.30 釜类设备安装检验记录 Kettle Type Equipment Installation Inspection Record SH/T 3503— J325 311

SH/T 3503— 2017

280

序号

S/N

名 称

Description

编 号

Reference No.

页次

Page No.

C.31 立式设备安装检验记录 Vertical Equipment Installation Inspection Record SH/T 3503— J326 312

C.32 卧式设备安装检验记录 Horizontal Equipment Installation Inspection Record SH/T 3503— J327 313

C.33 塔盘安装检验记录 Tray Installation Inspection Record SH/T 3503— J328 314

C.34 设备填充检验记录 Equipment Packing Inspection Record SH/T 3503— J329 315

C.35 反应 /沉降器附件安装检验记录 Reactor/Settler Attachment Installation Inspection Record SH/T 3503— J330 316

C.36 再生器附件安装检验记录 Regenerator Attachment Installation Inspection Record SH/T 3503— J331 317

C.37

立式圆筒形储罐组装质量检验记录

Vertical Cylindrical Storage Tank Assembling Quality

Inspection Record

SH/T 3503— J332 318

C.38 立式圆筒形 储罐罐底真空试验记录 Vertical Cylindrical Storage Tank Bottom Vacuum Test Record SH/T 3503— J333-1 319

C.39

立式圆筒形储罐开孔补强圈气密性试验记录

Vertical Cylindrical Storage Tank Opening Reinforcing Ring

Tightness Test Record

SH/T 3503— J333-2 320

C.40

立式圆筒形储罐浮顶/船舱严密性试验记录

Vertical Cylindrical Storage Tank Floating Roof/Pontoon

Tightness Test Record

SH/T 3503— J333-3 321

C.41 立式圆筒形储罐总体试验记录 Vertical Cylindrical Storage Tank Integral Test Record SH/T 3503— J333-4 322

C.42 湿式气柜组装质量检验记录 Wet Gas Holder Assembling Quality Inspection Record SH/T 3503— J334 323

C.43 湿式气柜底板严密性试验记录 Wet Gas Holder Bottom Plate Tightness Test Record SH/T 3503— J335-1 324

C.44 湿式气柜开孔补强圈气密性试验记录 Wet Gas Holder Opening Reinforcing Ring Tightness Test Record SH/T 3503— J335-2 325

C.45 湿式气柜水槽严密性试验记录 Wet Gas Holder Water Tank Tightness Test Record SH/T 3503— J335-3 326

C.46 湿式气柜整体试验记录 Wet Gas Holder Integral Test Record SH/T 3503— J335-4 327

C.47 干式气柜组装质量检验记录 Dry Gas Holder Assembling Quality Inspection Record SH/T 3503— J336 328

C.48

干式气柜底板/活塞板/壁板严密性试验记录

Dry Gas Holder Bottom Plate/Piston Plate/Shell Plate

Tightness Test Record

SH/T 3503— J337-1 329

SH/T 3503— 2017

281

序号

S/N

名 称

Description

编 号

Reference No.

页次

Page No.

C.49 干式气柜开孔补强圈气密性试验记录 Dry Holder Opening Reinforcing Ring Tightness Test Record SH/T 3503— J337-2 330

C.50 干式气柜总体试验记录 Dry Holder Integral Test Record SH/T 3503— J337-3 331

C.51 火炬塔架和管筒安装检验记录 Flare Derrick and Stack Installation Inspection Record SH/T 3503— J338 332

C.52

隔热耐磨衬里质量检验记录

Thermal-insulating and Abrasion-resistant Lining Quality

Inspection Record

SH/T 3503— J339 333

C.53 热 交换 设备耐压和严密性试验记录 Heat Exchanger Pressure and Tightness Test Record SH/T 3503— J340 334

C.54 设备耐压 /严密性试验记录 Equipment Pressure/Tightness Test Record SH/T 3503— J341 335

C.55 设备热处理报告 Equipment Heat Treatment Report SH/T 3503— J342 336

C.56 管式炉炉体钢结构安装 检验记录 Tube Furnace Structural Steel Installation Inspection Record SH/T 3503— J343 337



C.57

炉管通球试验记录

Furnace Tube PIG Inspection Record SH/T 3503— J344 338

C.58 管式 炉附件安装质量检验记录 Tube Furnace Attachment Installation Quality Inspection Record SH/T 3503— J345 339

C.59 耐火砖砌筑炉衬质量检验记录 Refractory Brick Furnace Lining Quality Inspection Record SH/T 3503— J346 340

C.60 耐火浇注料炉衬质量检验记录 Refractory Castable Furnace Lining Quality Inspection Record SH/T 3503— J347 341

C.61 耐火纤维模块炉衬质量检验记录 Refractory Fiber Module Lining Quality Inspection Record SH/T 3503— J348 342

C.62 设备及构件焊缝射线检测报告 Equipment and Structure Weld RT Report SH/T 3503— J349-1 343

C.63 设备及构件焊缝射线检测报告( 续 ) Equipment and Structure Weld RT Report (Continued) SH/T 3503— J349-2 344

C.64 设备及构件焊缝超声检测报告 Equipment and Structure Weld UT Report SH/T 3503— J350-1 345

C.65 设备及构件焊缝超声检测报告( 续 ) Equipment and Structure Weld UT Report (Continued) SH/T 3503— J350-2 346

C.66 设备及构件焊缝磁粉检测报告 Equipment and Structure Weld MT Report SH/T 3503— J351-1 347

C.67 设备及构件焊缝磁粉检测报告( 续 ) Equipment and Structure Weld MT Report (Continued) SH/T 3503— J351-2 348

C.68 设备及构件焊缝渗透检测报告 Equipment and Structure Weld PT Report SH/T 3503— J352-1 349

C.69 设备及构件焊缝渗透检测报告( 续 ) Equipment and Structure Weld PT Report (Continued) SH/T 3503— J352-2 350



SH/T 3503— 2017

282

SH/T 3503— J301

机器安装检验记录

Mechanical Equipment

Installation Inspection

Record

工程名称:

Project Name:



单位工程名称:

Unit Name:

Equipment

Description

Equipment

Item No.

Equipme

nt Model

Item Allowable Value Actual Value

Deviation in Elevation, mm

Deviation in Central Line Location, mm

Longitudinal

Transversal

Vertical Deviation, mm

0°/180°

90°/270°

Horizontal Deviation, mm/m

Longitudinal

Transversal





Remarks or Attached Drawing:

Inspection Conclusion:

Owner/Supervision Contractor General Contractor Construction Contractor

Discipline Engineer:







Date:

Discipline Engineer:







Date:

Foreman:

Quality Inspector:

Discipline Engineer:



Date:

SH/T 3503— 2017

283

SH/T 3503— J302

轴对中记录

Shaft Alignment

Record

工程名称:

Project Name:



单位工程名称:

Unit Name:

Equipment

Description

Equipmen

t Item No.

Type of

Coupling

Measurin

g Method

□Bi-meter □Tri-meter

□others



Sketch Showing Locations of Check Points Unit: mm

Coupl

ing

N

o. Radial Displacement Axial Inclination End Clearance Dial

Gauge

Fixed

Position

Al

low

abl

e

Val

ue

Actual Value

Al

low

abl

e

Val

ue

Dial Gau

ge

Swiv

el

Dia.

Actual Value

Al

low

abl

e

Val

ue



Act

ual



Val

ue



a1 a2 a3 a4 b1 b2 b3 b

4









Notes: 1. Couplings shall be numbered in sequence, starting from the driver side.

2. □Yes □No. Actual shaft alignment measurement curve shall be attached.

Conclusion:

Owner/Supervision Contractor General Contractor Construction Contractor

Discipline Engineer:







Date:

Discipline Engineer:







Date:

Foreman:

Quality Inspector:

Discipline Engineer:



Date:

SH/T 3503— 2017

284

SH/T 3503— J303

机组轴对中记录

Machine Train Shaft

Alignment Record

工程名称:

Project Name:



单位工程名称:

Unit Name:

Equipment

Description

Equipment

Item No.

Driver Shaft Side



Sketch Showing Locations of Check Points Unit: mm

Coupling No. A1-B1 A2-B2 A3-B3

Type of Coupling

End

Distance

L1, L2, L3

Allowable Value

Actual

Value

Check Point Location A1 B1 A2 B2 a

1 a2 a3 a4 b1 b2 b3 b4 a1 a2 a3 a4 b1 b2 b3 b4

Allowable Value

Actual Value

Check Point Location A3 B3 a

1 a2 a3 a4 b1 b2 b3 b4 a1 a2 a3 a4 b1 b2 b3 b4

Allowable Value

Actual Value

Notes: 1. Couplings shall be numbered in sequence, starting from the driver side.

2. □Yes □No. Actual shaft alignment measurement curve shall be attached.

Conclusion:

Owner/Supervision Contractor General Contractor Construction Contractor Equipment Manufacturer

Discipline Engineer:







Date:

Discipline Engineer:







Date:

Foreman:

Quality Inspector:

Discipline Engineer:



Date:

Site Representative:







Date:

SH/T 3503— 2017

285

SH/T 3503— J304

空冷式换热器风机安装检验

记录

Air-cooled Heat Exchanger

Fan Installation Inspection

Record

工程名称:

Project Name:



单位工程名称:

Unit Name:

Equipment

Description

Equipment

Item No.

Equipment

Model

Plenum

Diameter mm

Blade

Number Belt Model

Item Allowable Value Actual Value 1 2 3 4 5 6

Blade Installation Angle, o

Bland Tip Circumferential Level

Difference, mm

Deviation in Plumbness of Fan

Shaft, mm

Offset in Central Plane of Drive and

Driven Shaft Pulley, mm

Parallelism of Drive and Driven Shaft

Pulley

Belt Tension

Applied Load W, kN

Side Cut Length L, mm

Central Deflection f, mm

Distance between Inner Wall of Plenum and

Tip of Fan Blade, mm

Actual Value

0? 45? 90? 135? 180? 225? 270? 315?







Note: Number 1 to 6 in the Column “Actual Value” of this form indicate the fan blade numberings.

Inspection Conclusion:

Owner/Supervision Contractor General Contractor Construction Contractor

Discipline Engineer:







Date:

Discipline Engineer:







Date:

Foreman:

Quality Inspector:

Discipline Engineer:



Date:

SH/T 3503— 2017

286

SH/T 3503— J305

机器组装质量确认记录

Mechanical Equipment

Assembling Quality

Confirmation Record

工程名称:

Project Name:



单位工程名称:

Unit Name:

Equipment

Description

Equipment

Item No.

Inspe

cti

on on I

nter

nal

A

sse

mbl

ing





Ma

jor

D

efect

(s)

an

d D

isp

osi

tion

Res

ult





Conf

irm

ati

on C

om

ment

s



Owner/Supervision

Contractor General Contractor

Construction

Contractor Equipment Manufacturer

Discipline Engineer:





Date:

Discipline Engineer:





Date:

Foreman:

Quality Inspector:

Discipline Engineer:

Date:

Site Representative:





Date:

SH/T 3503— 2017

287



SH/T 3503— 2017

288



SH/T 3503— 2017

289

SH/T 3503— J308

往复式压缩机

曲柄臂间距检查 记录

Reciprocating Compressor Crank

Spread Inspection Record

工程名 称:

Project Name:



单位工程名称:

Unit Name:

Equipment

Description

Equipment

Item No.



1



1— Inside Micrometer

Sketch Showing Locations of Check Points( Unit: mm)

Cylinder

Row No.

Allowable

Value

Actual Value

Max. Deviation/Stroke

0° 90° 180° 270°













Remarks:

Conclusion:

Owner/Supervision

Contractor General Contractor Construction Contractor Equipment Manufacturer

Discipline Engineer:







Date:

Discipline Engineer:







Date:

Foreman:

Quality Inspector:

Discipline Engineer:



Date:

Site Representative:







Date:



SH/T 3503— 2017

290

SH/T3503-J309

往复式压缩机主轴轴线与中体

滑道轴线垂直度检查记录

Reciprocating Compressor Main

Shaft and Intermediate Frame Guide

Axial Plumbness Inspection Record

工程名称:

Project Name:



单位工程名称:

Unit Name:

Equipment

Description

Equipment

Item No.



1— Inside Micrometer; 2— Steel Wire

Sketch Showing Locations of Check Points

Cylinder

Row No.

Measurement

mm

Deviation in Plumbness

mm/m

Axial Movement

mm

A B C D E F G H Allowable Value Actual Value Allowable Value Actual Value















Remarks:



Conclusion:



Owner/Supervision

Contractor General Contractor Construction Contractor Equipment Manufacturer

Discipline Engineer:





Date:

Discipline Engineer:





Date:

Foreman:

Quality Inspector:

Discipline Engineer:

Date:

Site Representative:





Date:

SH/T 3503— 2017

291

SH/T 3503— J310

往复式压缩机主轴瓦与推力轴

瓦间隙检查记录

Reciprocating Compressor Mainshaft

Bearing Liner and Thrust Bearing

Liner Clearance Inspection Record

工程名称:

Project Name:



单位工程名称:

Unit Name:

Equipment

Description

Equipment

Item No.



Sketch Showing Locations of Check Points( Unit: mm)

No.

Main Bearing Thrust Bearing

Top Clearance a Lateral Clearance b1/ b2

No. Allowable Value

Actual Value

Allowable

Value

Actual

Value

Allowable

Value

Actual Value A B

b1 b2











Remarks:

Conclusion:

Owner/Supervision

Contractor General Contractor Construction Contractor Equipment Manufacturer

Discipline Engineer:







Date:

Discipline Engineer:







Date:

Foreman:

Quality Inspector:

Discipline Engineer:



Date:

Site Representative:







Date:



SH/T 3503— 2017

292

SH/T 3503— J311

往复式压缩机十字头与中体滑

道间隙检查 记录(卧式)

Reciprocating Compressor

Crosshead and Intermediate

Frame Guide Clearance

Inspection Record (Horizontal)

工程名称:

Project Name:



单位工程名称:

Unit Name:

Equipment

Description

Equipment

Item No.



Sketch Showing Locations of Check Points( Unit: mm)

Cylinder

Stage

No.

Allowable

Value

Actual Value

A1 A2 A3 A4 A5 A6 A7 A8











Remarks:



Conclusion:



Owner/Supervision

Contractor General Contractor Construction Contractor Equipment Manufacturer

Discipline Engineer:







Date:

Discipline Engineer:







Date:

Foreman:

Quality Inspector:

Discipline Engineer:



Date:

Site Representative:







Date:

SH/T 3503— 2017

293

SH/T 3503— J312

往复式压缩机十字头与中体滑

道间隙检查 记录(立式)

Reciprocating Compressor Crosshead

& Intermediate Frame Guide

Clearance Inspection Record (Vertical)

工程名称:

Project Name:



单位工程名称:

Unit Name:

Equipment

Description

Equipment

Item No.







Sketch Showing Locations of Check Points( Unit: mm)

Cylinder

Stage No.

Allowable

Value

Actual Value

A1 A2 A3 A4 A5 A6 A7 A8 A9 A10 A11 A12













Remarks:



Conclusion:



Owner/Supervision

Contractor General Contractor Construction Contractor Equipment Manufacturer

Discipline Engineer:







Date:

Discipline Engineer:







Date:

Foreman:

Quality Inspector:

Discipline Engineer:



Date:

Site Representative:







Date:



SH/T 3503— 2017

294

SH/T 3503— J313

往复式压缩机连杆

组装 记录

Reciprocating Compressor

Connecting Rod Assembling Record

工程名称:

Project Name:



单位工程名称:

Unit Name:

Equipment

Description

Equipment

Item No.



Crank Pin End Bearing Liner Piston Pin End Bearing Liner

Sketch Showing Locations of Check Points( Unit: mm)

Cylinder

Stage

No.

Crank Pin End Bearing Liner Clearance Piston Pin End Bearing Liner Clearance

A B C A B C

Allowable

Value

Actual

Value

Allowable

Value

Actual

Value

Allowable

Value

Actual

Value

Allowable

Value

Actual

Value

Allowable

Value

Actual

Value

Allowable

Value

Actual

Value









Connecting Rod Bolt Connection

Cylinder

Stage

No.

Bolt

Dia.

mm

Bolt Extension (mm) Torque Wrench

Tightening Torque

(N/m)

Hydraulic

Wrench Pressure

(MPa) Allowable

Value

1 2

Pre-tight

Length

After-ti

ght

Length

Actual

Extension

Pre-

tight

Length

After-

tight

Length

Actual

Extension

Allowable

Value

Actual

Value

Allowable

Value

Actual

Value









Remarks:

Conclusion:

Owner/Supervision

Contractor General Contractor Construction Contractor Equipment Manufacturer

Discipline Engineer:







Date:

Discipline Engineer:







Date:

Foreman:

Quality Inspector:

Discipline Engineer:



Date:

Site Representative:







Date:

SH/T 3503— 2017

295

SH/T 3503— J314

往复式压缩机气缸余隙检查 记录

Reciprocating Compressor Cylinder

Clearance Inspection Record

工程名称:

Project Name:



单位工程名称:

Unit Name:

Equipment

Description

Equipment

Item No.





Sketch Showing Locations of Check Points( Unit: mm)

Cylinder

Stage No.

L1 L2

Allowable Value Actual Value Allowable Value Actual Value









Remarks:



Conclusion:



Owner/Supervision

Contractor General Contractor Construction Contractor Equipment Manufacturer

Discipline Engineer:







Date:

Discipline Engineer:







Date:

Foreman:

Quality Inspector:

Discipline Engineer:



Date:

Site Representative:







Date:



SH/T 3503— 2017

296

SH/T 3503— J315

往复式压缩机活塞与气缸

圆周间隙检查 记录

Reciprocating Compressor Piston

and Cylinder Circumferential

Clearance Inspection Record

工程名称:

Project Name:



单位工程名称:

Unit Name:

Equipment

Description

Equipment

Item No.



Sketch Showing Locations of Check Points( Unit: mm)

Cylinder

Stage No.

A B C D

Allowable

Value

Actual

Value

Allowable

Value

Actual

Value

Allowable

Value

Actual

Value

Allowable

Value

Actual

Value













Remarks:



Conclusion:



Owner/Supervision

Contractor General Contractor Construction Contractor Equipment Manufacturer

Discipline Engineer:







Date:

Discipline Engineer:







Date:

Foreman:

Quality Inspector:

Discipline Engineer:



Date:

Site Representative:







Date:

SH/T 3503— 2017

297



SH/T 3503— J316

往复式压缩机活塞环安装 记录

Reciprocating Compressor

Piston Ring Installation Record

工程名称:

Project Name:



单位工程名称:

Unit Name:

Equipment

Description

Equipment

Item No.



Piston Ring Side Clearance Piston Ring Sink-in Clearance

Sketch Showing Locations of Check Points( Unit: mm)

Cylinder

Stage No.

Piston Ring Working Position ( C) Side Clearance ( A) Sink-in Clearance( B)

No. Material Allowable Value Actual Value Allowable Value Actual Value Allowable Value Actual Value















Note: When piston rings in cast iron are used, inspection shall be made on chamfered and rounded corners in

accordance with the design documents prior to installation.

Remarks:

Conclusion:

Owner/Supervision

Contractor General Contractor Construction Contractor Equipment Manufacturer

Discipline Engineer:







Date:

Discipline Engineer:







Date:

Foreman:

Quality Inspector:

Discipline Engineer:



Date:

Site Representative:







Date:

SH/T 3503— 2017

298



SH/T3503-J317

往复式压 缩机

填料函各部间 隙检查记 录

Reciprocating Compressor Stuffing

Box Clearance Inspection Record

工程名称:

Project Name:



单位工程名称:

Unit Name:

Equipment

Description

Equipment

Item No.

Packing Type □ Conical □ Flat



Conical Packing Flat Packing

Sketch Showing Locations of Check Points( Unit: mm)

Check Point

Location A B C D

Allowable Value

Act

ual

Val

ue



1st Stage

Cylinder

2nd Stage

Cylinder

3rd Stage

Cylinder

4th Stage

Cylinder

Remarks:



Conclusion:



Owner/Supervision

Contractor General Contractor Construction Contractor Equipment Manufacturer

Discipline Engineer:







Date:

Discipline Engineer:







Date:

Foreman:

Quality Inspector:

Discipline Engineer:



Date:

Site Representative:







Date:

SH/T 3503— 2017

299

SH/T 3503— J318-1

机器单机试车记录

Mechanical Equipment Solo

Test Run Record

工程名称:

Project Name:



单位工程名称:

Unit Name:

Equipment

Description

Equipment

Item No.

Operating

Medium

Driver Type Revolution r/min Test Run Medium

Test Run Type □ No-Load □ Loaded Ambient Temperature ℃ Test Run Date

Continuous

Running Time h

Start-up

Current A Start-up Timing

Inspection Item Design/ Allowable

Value

Actual Value

Running Recording Time

Pressure,

MPa

Inlet

Outlet

Bearing

Temperature



Coupling Side

Non-coupling Side

Dr

iver



Bearing

Temp.



Coupling Side

Non-coupling Side

Voltage, V

Current, A

Steam Pressure, MPa

Steam Flow, kg/h

Lube Oil Pressure, MPa Temperature,℃

Cooling

Water

Pressure, MPa

Temperature,℃

Vibration

Velocity

(Amplitude)

mm/s(μm)

Axial

Horizontal

Vertical

Test on the protective interlock system:

Conclusion:

Owner/Supervision

Contractor General Contractor Construction Contractor Equipment Manufacturer

Discipline Engineer:









Date:

Discipline Engineer:









Date:

Foreman:

Quality Inspector:

Discipline Engineer:





Date:

Site Representative:









Date:

SH/T 3503— 2017

300

SH/T 3503— J318-2

________设备单机试车记录

Equipment Solo Test

Run Record

工程名称:

Project Name:



单位工程名称:

Unit Name:

Equipment

Description

Equipment

Item No.

Operating

Medium

Driver Type Revolution r/min Test Run Medium

Test Run Type □ No-Load □ Loaded Ambient Temperature ℃ Test Run Date

Continuous

Running Time h

Start-up

Current A Start-up Timing

Inspection Item Design /

Allowable

Value

Actual Value

Running Recording Time

































Test on the protective interlock system:

Conclusion:

Owner/Supervision

Contractor General Contractor Construction Contractor Equipment Manufacturer

Discipline Engineer:







Date:

Discipline Engineer:







Date:

Foreman:

Quality Inspector:

Discipline Engineer:



Date:

Site Representative:







Date:



SH/T 3503— 2017

301

SH/T 3503— J319

机组试车条件确认记录

Machine Train Readiness for

Test Run Confirmation

Record

工程名称:

Project Name:



单位工程名称:

Unit Name:

Equipment

Description

Equipment

Item No.

Model Capacity

Driver Type Revolution r/min

Item Technical Requirement

Confirmed by

Date Owner/

Supervision

Contractor

General

Contractor

Construction

Contractor

Equipment

Manufacturer

Equipment

Dismantling

Inspection

Dismantling inspection and

restoration shall be completed

and recorded as per specification

requirements.





Auxiliary

System

The system shall be verified as

acceptable.

Oil Piping

System

Flushing and pressure test shall

be completed and recorded as

per specification requirements.



Circulating or

Lube Oil

Applicable requirements shall

be met.

Electrical

Facility

Installation shall be completed,

testing qualified, and records

made in accordance with the

specification requirements.



Instrument

Interlock and

Control System

Installation shall be completed,

system testing qualified, and

records made as per

specification requirements.



Process Piping

System

Installation shall be completed,

pressure test and purging

(cleaning) qualified, and

records made as per

specification requirements.



Machine Train

Test Run Plan

Specific and clear test run

procedure, measures and

quality acceptance

requirements shall be available.



Supporting

Operation

Process and

Conditions

Preparation shall be completed

as required by the test run plan.

Owner’s Responsible Person for Test Run:

Confirmation

on Test Run

Conditions

Ready for test run.

General Responsible Person for Test Run:

SH/T 3503— 2017

302



SH/T 3503— J320- 1

往复式压缩机试车记录

Reciprocating Compressor

Test Run Record

共()页 第()页 Page of

工程名称:

Project Name:



单位工程名称:

Unit Name:

Equipment

Description

Equipment

Item No.

Model Operating Medium

Test Run Type □No-load □Loaded Test Medium Ambient Temperature ℃

Driver Type Revolution r/min Start-up Current A

Continuous

Running Time h Test Run Date Start-up Timing

Inspection Item Design / Allowable

Value

Actual Value

Running Recording Time

Lube

Oil

Inlet Pressure, MPa

Inlet Temperature,℃

Outlet Temperature,℃

Co

oli

ng



Wa

ter

Inlet Pressure, MPa

Inlet Temperature,℃

Outlet Temperature,℃

Vibration

Speed

(Amplitude)

mm/s(μm)

Axial

Horizontal

Vertical

Bearing

Temperature



Front Bearing

Rear bearing

Thrust Bearing

1st

St

age



Inlet Pressure, MPa Temperature,℃

Outlet Pressure, MPa Temperature℃

Packing Box

Temperature,℃



Owner/Supervision

Contractor General Contractor Construction Contractor Equipment Manufacturer

Discipline Engineer:







Date:

Discipline Engineer:







Date:

Foreman:

Quality Inspector:

Discipline Engineer:



Date:

Site Representative:







Date:



SH/T 3503— 2017

303

SH/T 3503— J320-2

往复式压缩机试车记录 (续)

Reciprocating Compressor

Test Run Record (Continued)

工程名称:

Project Name:



单位工程名称:

Unit Name:

Inspection Item Design/ Allowable

Value

Actual Value

Running Recording Time

Stage



Inlet

Pressure, MPa

Temperature℃

Outlet

Pressure, MPa

Temperature,℃

Packing Box

Temperature,℃





Stage



Inlet

Pressure, MPa

Temperature,℃

Outlet

Pressure, MPa

Temperature,℃

Packing Box

Temperature,℃





Stage



Inlet

Pressure, MPa

Temperature,℃

Outlet

Pressure, MPa

Temperature,℃

Packing Box

Temperature,℃





Test on the protective interlock system:

Inspection after test run:

Conclusion:



SH/T 3503— 2017

304

SH/T 3503— J321-1

离心式压缩机试车记录

Centrifugal Compressor

Test Run Record

共()页 第()页 Page of

工程名称:

Project Name:



单位工 程名称:

Unit Name:

Equipment

Description

Equipment

Item No.

Model Operating Medium Test Medium

Driver Type Revolution r/min Starting Current A

Test Run Type □No-load □ Loaded Ambient Temperature ℃ Test Run Date

Continuous

Running Time h Idling Time s

Starting

Timing

Inspection Item Design/ Allowable

Value

Actual Value

Running Recording Time

1st

St

age



Inlet

Flow, Nm3/h

Pressure, MPa

Temperature,℃

Outlet

Pressure, MPa

Temperature,℃

Bear

ing

Te

mp

era

tur

e,℃



Front Bearing

Rear Bearing

Thrust Bearing

Vi

brat

ion S

peed

(A

mpl

itude)

,

mm

/s (

μm

)

Front

B

ear

ing



Horizontal

Vertical

Axial

Rear

be

ari

ng

Horizontal

Vertical

Axial

Shaft Displacement, mm

Owner/Supervision

Contractor General Contractor Construction Contractor Equipment Manufacturer

Discipline Engineer:







Date:

Discipline Engineer:







Date:

Foreman:

Quality Inspector:

Discipline Engineer:



Date:

Site Representative:







Date:

SH/T 3503— 2017

305



SH/T 3503— J321-2

离心式压缩机试车记录 (续 1)

Centrifugal Compressor Test

Run Record (Continued 1)

工程名称:

Project Name:



单位工程名称:

Unit Name:

Inspection Item

Design/

Allowabl

e Value

Actual Value

Running Recording Time

S

tage



Inlet

Flow,Nm3/h

Pressure, MPa

Temperature,℃

Outlet Pressure, MPa Temperature,℃

Bear

ing

Tem

per

atur

e,℃

Front Bearing

Rear bearing

Thrust Bearing

Vi

brat

ion S

peed

(A

mpl

itude)

, m

m/

s (

μm

)

Fro

nt

Be

ari

ng

Horizontal

Vertical

Axial

Rear



bear

ing

Horizontal

Vertical

Axial

Shaft Displacement, mm





















Sta

ge



Inlet

Flow,Nm3

Pressure, MPa

Temperature,℃

Outlet Pressure, MPa Temperature,℃

Bear

ing

Tem

per

a-

tur

e,





Front Bearing Rear bearing

Thrust Bearing

Vi

brat

ion S

peed

(A

mpl

itude)

, m

m/

s (

μm

)

Fro

nt

Be

ari

ng

Horizontal

Vertical

Axial

Rear



bear

ing

Horizontal

Vertical

Axial

Shaft Displacement, mm



SH/T 3503— 2017

306

SH/T 3503— J321-3

离心式压缩机试车记录 (续 2)

Centrifugal Compressor Test

Run Record (Continued 2)

工程名称:

Project Name:



单位工程名称:

Unit Name:

Inspection Item

Design/

Allowable

Value

Actual Value

Running Recording Time

Lube

Oil

Pressure, MPa

Inlet

Temperature, ℃

Outlet

Temperature, ℃

Seal Oil Pressure, MPa

Power Oil Pressure, MPa

Air Seal Pressure, MPa

Oi

l C

ool

er Oil Inlet

Temperature, ℃

Oil Outlet

Temperature, ℃



















Test on the protective interlock system:







Inspection after test run:









Conclusion:









SH/T 3503— 2017

307

SH/T 3503— J322-1

汽 轮机 /燃气轮机试车记录

Steam/Gas Turbine Test Run

Record

共()页 第()页 Page of

工程名称:

Project Name:



单位工程名称:

Unit Name:

Equipment

Description

Equipment

Item No.

Model Revolution r/min

Test Run Type □No-load □ Loaded Test Run Date Starting Time

Continuous

Running Time h

Ambient

Temperature ℃

Test

Medium

Minimum

Operating Speed



r/min Rated Speed r/min

Critical

Speed r/min

Overspeed Trip Setting r/min Idling Time s

Inspection Item

Design/

Allowable

Value

Actual Value

Running Recording Time

Speed, r/min

Inlet Pressure, MPa Temperature,℃

Outlet Pressure, MPa Temperature,℃

Condenser’s Vacuum

Degree, MPa

Bear

ing

Tem

per

atu

re



Front Bearing Rear bearing

Thrust Bearing

Vi

brat

ion S

peed

(A

mpl

itude)

, m

m/

s

(μm

) Front



Bear

ing

Axial

Horizontal

Vertical

Rear



bear

ing

Axial

Horizontal

Vertical

Shaft Displacement, mm

Control Oil Pressure, MPa

Owner/Supervision

Contractor General Contractor Construction Contractor Equipment Manufacturer

Discipline Engineer:







Date:

Discipline Engineer:







Date:

Foreman:

Quality Inspector:

Discipline Engineer:



Date:

Site Representative:







Date:



SH/T 3503— 2017

308

SH/T 3503— J322-2

汽轮机 /燃气轮机试车记录 (续 )

Steam/Gas Turbine Test Run

Record (Continued)

工程名称:

Project Name:



单位工程名称:

Unit Name:

Inspection Item Design/

Allowable

Value

Actual Value

Running Recording Time

Lube

Oil

Inlet Pressure,

MPa

Inlet

Temperature, ℃

Outlet

Temperature, ℃

Cooler

Water Inlet

Pressure, MPa

Return Water

Pressure, MPa

Water Inlet

Temperature, ℃

Return Water

Temperature, ℃













Sketch showing locations of check points:









Overspeed trip test:



Test on the protective interlock system:



Inspection after test run:



Conclusion:





SH/T 3503— 2017

309

SH/T 3503— J323

电动机试车记录

Motor Test Run Record

工程名称:

Project Name:



单位工程名称 :

Unit Name:

Equipment

Description

Equipment

Item No.

Motor Type Speed r/min Test Run Type □No-load □Loaded

Test Run Date Startup Time Ambient Temperature ℃

Continuous

Running Time h Idling Time s

Startup

Current A

Inspection Item Design/

Allowable

Value

Actual Value

Running Recording Time

Voltage, V

Current, A

Bearing

Temp.



Coupling Side

Noncoupling Side

Vi

brat

ion S

peed

(A

mpl

itude)

, m

m/

s

(μm

) Coupl

ing

Side Bear

ing

Axial

Horizontal

Vertical

Nonc

oupl

-

ing Si

de

Bear

ing

Axial

Horizontal

Vertical

Lube

Oil

Inlet Pressure, MPa

Inlet Temperature, ℃

Outlet Temperature, ℃

Cooling

Water

Inlet Pressure, MPa

Inlet Temperature, ℃

Outlet Temperature, ℃

Conclusion:

Owner/Supervision

Contractor General Contractor Construction Contractor Equipment Manufacturer

Discipline Engineer:







Date:

Discipline Engineer:







Date:

Foreman:

Quality Inspector:

Discipline Engineer:



Date:

Site Representative:







Date:

Note: This form is used to record the running of the motor of 200kW and above.



SH/T 3503— 2017

310

SH/T 3503— J324 变速器试车记录 Transmission Test Run Record

工程名称:

Project Name:



单位工程名称:

Unit Name:

Equipment

Description

Equipment

Item No.

Equipment

Model

Transmission

Type

Ambient

Temperature ℃

Test Run

Type □No-load □Loaded

Continuous

Running Time h

Test Run

Date

Start-up

Time

Inspection Item Design/

Allowable

Value

Actual Value

Running Recording Time

Bear

ing

Tem

per

atur

e





Input Shaft Front Bearing Rear Bearing

Intermediate

Shaft 1

Front Bearing

Rear Bearing

Intermediate

Shaft 2

Front Bearing

Rear Bearing

Output

Shaft

Front Bearing

Rear Bearing

Vi

brat

ion S

peed

(A

mpl

itude)

, m

m/

s (

μm

)

Input

Shaf

t

Fro

nt

Be

ari

ng



Horizontal

Vertical

Re

ar

Be

ari

ng



Horizontal

Vertical

Out

put



Shaf

t Fro

nt

Be

ari

ng



Horizontal

Vertical

Re

ar

Be

ari

ng



Horizontal

Vertical





Conclusion:

Owner/Supervision

Contractor General Contractor Construction Contractor Equipment Manufacturer

Discipline Engineer:







Date:

Discipline Engineer:







Date:

Foreman:

Quality Inspector:

Discipline Engineer:



Date:

Site Representative:







Date:



SH/T 3503— 2017

311



SH/T 3503— J325

釜类设备安装检验记录

Kettle Type Equipment

Installation Inspection Record

工程名称:

Project Name:



单位工程名称:

Unit Name:

Equipment

Description

Equipment

Item No.

Item Allowable Value mm Actual Value mm

Deviation in Elevation of Kettle Body

Deviation in Orientation of Kettle body

Vertical Deviation of Kettle

body

0o/180 o

90o/270o

Deviation in Levelness of

Top Opening Flange Face

of Kettle Body

0o/180o

90o/270o

Vertical Deviation of

Stirring Shaft

0o/180o

90o/270o

End Radial Runout of Stirring Shaft

Axial Movement of Stirring Shaft

Radial Displacement Deviation of Stirring

Shaft at Shaft Seal

Confirmation on the inside cleanness of the gearbox:

Confirmation on the lube system:

Confirmation on the cooling system:

Confirmation on the sealing system:

Conclusion:











Owner/Supervision Contractor General Contractor Construction Contractor

Discipline Engineer:







Date:

Discipline Engineer:







Date:

Foreman:

Quality Inspector:

Discipline Engineer:



Date:





SH/T 3503— 2017

312

SH/T 3503— J326

立式设备安装检验记录

Vertical Equipment

Installation Inspection Record

工程名称:

Project Name:



单位工程名称:

Unit Name:

Equipment

Description

Equipment

Item No.

Specification





Note: h is the distance between two check points, taking mm.

Unit: mm

Item Check Point Location Allowable Value Actual Value Item Check Point Location Allowable Value Actual Value

Deviation

in

Elevation

0o

Deviation in Central

Position of Support

0o

90o 90o

180o 180o

270o 270o

Vertical

Deviation

0o/180o Deviation in

Orientation 0o 90o/270o

Conclusion:

Owner/Supervision Contractor General Contractor Construction Contractor

Discipline Engineer:







Date:

Discipline Engineer:







Date:

Foreman:

Quality Inspector:

Discipline Engineer:



Date:



SH/T 3503— 2017

313



SH/T 3503— J327

卧式设备安装检验记录

Horizontal Equipment

Installation Inspection Record

工程名称:

Project Name:



单位工程名称:

Unit Name:

Equipment

Description

Equipment

Item No.

Specification





Note 1: B、 C、 D、 E shown in the sketch are bench marks for measuring the equipment shell levelness.

Note 2: The elevation of equipment installed shall be measured from the baseline on the equipment foundation to the lower

surface of the base plate of the equipment support.

Note 3: The deviation in axial levelness shall be in line with the drain direction.

Note 4: L is the distance between two end check points, taking mm.

Unit: mm

Item Check Point Location Allowable Value Actual Value Item Check Point Location Allowable Value Actual Value

Deviation in

Central

Position of

Support

Longitudinal Deviation in

Longitudinal

Levelness

B-C

Horizontal D-E

Deviation in

Elevation of

Support

Sliding Side Deviation in

Horizontal

Levelness

B-D

Fixed Side C-E

Sliding Tolerance of Saddle

at Sliding Side

Verified Loosening Status of

Nut at Sliding Side

Note: The double nut for the anchor bolt at the sliding side shall be loosened after the installation of the

equipment piping, and then tightened with a certain clearance maintained from the support plate.

Conclusion:

Owner/Supervision Contractor General Contractor Construction Contractor

Discipline Engineer:







Date:

Discipline Engineer:







Date:

Foreman:

Quality Inspector:

Discipline Engineer:



Date:

SH/T 3503— 2017

314



SH/T 3503— J328

塔盘安装检验记录

Tray Installation Inspection

Record

工程名称:

Project Name:



单位工程名称:

Unit Name:

Equipment

Description

Equipment

Item No.

Specification Tray Type

Inspection

Item, mm

Tray

Levelness

Deviation

Tray Support Overflow Weir Downcomer and Seal Pan Others

Spacing Levelness Horizontal Deviation Height Deviation Vertical Distance Horizontal Distance

Allowable

Value



Tray No. Actual Value Actual Value Actual Value Actual Value Actual Value Actual Value Actual Value

1











2















Conclusion:



Remarks:



Owner/Supervision Contractor General Contractor Construction Contractor

Discipline Engineer:







Date:

Discipline Engineer:







Date:

Foreman:

Quality Inspector:

Discipline Engineer:



Date:

SH/T 3503— 2017

315

SH/T 3503— J329

设备填充检验记录

Equipment Packing

Inspection Record

工程名称:

Project Name:



单位工程名称:

Unit Name:

Equipment

Description

Equipment

Item No.

Specification

Section No. Packing Description Packing Specification

Packing Height, m Packing Volume, m3

Remarks Design

Value

Actual

Value

Design

Value

Actual

Value

































Conclusion:









Owner/Supervision Contractor General Contractor Construction Contractor

Discipline Engineer:







Date:

Discipline Engineer:







Date:

Foreman:

Quality Inspector:

Discipline Engineer:



Date:



SH/T 3503— 2017

316



SH/T 3503— J330

反应 /沉降器附件安装检验记录

Reactor/Settler Attachment

Installation Inspection Record

工程名称:

Project Name:



单位工程名称:

Unit Name:

Equipment

Description

Equipment

Item No.

Item Allowable Value Max. Actual Value

Co

llec

tio

n

Ch

am

ber



Deviation in Concentricity

with Shell, mm

Deviation in Opening

Orientation, mm

Horizontal Deviation, mm

Riser Plumbness, mm

Spent Catalyst Standpipe

Plumbness, mm

Cyclone Separator System Allowable Value Separator 1 2 3 4 5 6 7 8

1st Stage Separator Inlet Elevation

Deviation, mm

Separator Plumbness,

mm

1st Stage

2nd Stage

Deviation in

Installation Angle of

Flange Valve

1st Stage Allowable Value Actual Value

2nd Stage Allowable Value Actual Value

Inspection Item Installation Requirements Inspection Result

Feed Nozzle Installation angle and dimensions shall meet the design requirements. Oil injector shall not be blocked.

Hanger Nut and Maintenance

Platform Supporting Angle Nut

Gap for expansion shall be reserved. Lock nut shall be

tightened securely.

Backing Strip for Tie Rod Blowhole shall be reserved.

Separator’s Dipleg and Flange Valve They shall be smooth and free from foreign matters.

Herringbone Patterned Baffle or

Doughnut Baffle Applicable design requirements shall be met.

Conclusion:

Owner/Supervision Contractor General Contractor Construction Contractor

Discipline Engineer:







Date:

Discipline Engineer:







Date:

Foreman:

Quality Inspector:

Discipline Engineer:



Date:

SH/T 3503— 2017

317

SH/T 3503— J331

再生器附件安装检验记录

Regenerator Attachment

Installation Inspection Record

工程名称:

Project Name:



单位工程名称:

Unit Name:

Equipment

Description

Equipment

Item No.

Item Allowable Value Max. Actual Value

Ring

Distributor

Horizontal Deviation, mm

Deviation in Spacing btw.

Two Adjacent Coils, mm

Branch

Distributor

Deviation in Elevation, mm

Levelness, mm

Air Ring Center Deviation, mm Levelness, mm

Collection

Chamber

Deviation in Concentricity

with Shell, mm

Deviation in Opening

Orientation, mm

Cyclone Separator System Allowable Value Separator/Flange Valve 1 2 3 4 5 6 7 8

1st Stage Separator Inlet Elevation Deviation

mm

Separator Plumbness

mm

1st Stage

2nd Stage

Deviation in

Installation Angle of

Flange Valve

1st Stage Allowable Value Actual Value

2nd Stage Allowable Value Actual Value

Inspection Item Installation Requirements Inspection Result

Nut for Hanger and for Supporting Angle

for Maintenance Platform

Gap for expansion shall be reserved. Lock nut

shall be tightened securely.

Welds at Dipleg’s Tie Rod or Backing Strip Blowhole shall be reserved.

Separator’s Dipleg and Flange Valve They shall be smooth and free of foreign matters.

Conclusion:



Owner/Supervision Contractor General Contractor Construction Contractor

Discipline Engineer:







Date:

Discipline Engineer:







Date:

Foreman:

Quality Inspector:

Discipline Engineer:



Date:

SH/T 3503— 2017

318

SH/T 3503— J332

立式圆筒形储罐

组装质量检验记录

Vertical Cylindrical Storage Tank

Assembling Quality Inspection Record

工程名称:

Project Name:



单位工程名称:

Unit Name:

Equipment

Description

Equipment

Item No.

Structure

Type

Specification Volume m3 Material

Item Allowable Value, mm Max. Actual Value, mm Check Point Number Qualified Point Number Qualified Rate, %

Shell

Geometric

Dimensions

Height Deviation

Bottom Course Horizontal

Radius Deviation

Plumbness

Shell

Guide Support

Dipping Tube

Inner Floating Roof Rim

Local

Irregularity

Deviation

Tank Bottom

Shell Inside Surface

Dome Roof

Floating

Roof

Inner Floating Roof

Inner Floating Deck

Center Deck Plate

Remarks:



Inspection Item and Requirements Inspection Result

Nozzle elevation shall meet the requirements of the design documents.

Deviation in nozzle orientation shall meet the requirements of the design

documents and specifications.

Deviation in size of flange and nozzle and in extended length of connecting

pipe shall meet the requirements of the design documents and pecifications.

Conclusion:





Owner/Supervision Contractor General Contractor Construction Contractor

Discipline Engineer:







Date:

Discipline Engineer:







Date:

Foreman:

Quality Inspector:

Discipline Engineer:



Date:

SH/T 3503— 2017

319

SH/T 3503— J333-1

立式圆筒形储罐

罐底真空试验记录

Vertical Cylindrical Storage Tank

Bottom Vacuum Test Record

工程名称:

Project Name:



单位工程名称:

Unit Name:

Equipment

Description

Equipment

Item No.

Structure

Type

Specification Volume m3 Material

Test Date

Test Method:



Vacuum degree: kPa.



Test Record:





















Conclusion:









Owner/Supervision Contractor General Contractor Construction Contractor

Discipline Engineer:







Date:

Discipline Engineer:







Date:

Foreman:

Quality Inspector:

Discipline Engineer:



Date:

SH/T 3503— 2017

320

SH/T 3503— J333-2

立式圆筒形储罐开孔

补强圈气密性试验记录

Vertical Cylindrical Storage Tank

Opening Reinforcing Ring

Tightness Test Record

工程名称:

Project Name:



单位工程名称:

Unit Name:

Equipment

Description

Equipment

Item No.

Structure

Type

Specification Volume m3 Material

Test Date:

Test Nozzle No.:



Test Method:

Fill with air kPa, and check with soapsuds.



Test Record:





















Conclusion:





Owner/Supervision Contractor General Contractor Construction Contractor

Discipline Engineer:







Date:

Discipline Engineer:







Date:

Foreman:

Quality Inspector:

Discipline Engineer:



Date:



SH/T 3503— 2017

321



SH/T 3503— J333-3

立式圆筒形储罐浮顶 /船舱

严密性试验记录

Vertical Cylindrical Storage Tank

Floating Roof/Pontoon Tightness

Test Record

工程名称:

Project Name:



单位工程名称:

Unit Name:

Equipment

Description

Equipment

Item No.

Structure

Type

Specification Volume m3 Material

Test Date

Test Item: □ Pontoon Weld Tightness Test □ Pontoon Bottom Deck Tightness Test

□ Pontoon Tightness Test □ Center Deck Plate Tightness Test





Test Method: □ Vacuum Degree kPa; □ Check with Soapsuds, Fill with air kPa;

□ Check with Soapsuds; □ Water Filling Test





Test Record:















Conclusion:





Owner/Supervision Contractor General Contractor Construction Contractor

Discipline Engineer:







Date:

Discipline Engineer:







Date:

Foreman:

Quality Inspector:

Discipline Engineer:



Date:



SH/T 3503— 2017

322



SH/T 3503— J333-4

立式圆筒形储罐总体试验记录

Vertical Cylindrical Storage

Tank Integral Test Record

工程名称:

Project Name:



单位工程名称:

Unit Name:

Equipment

Description

Equipment

Item No.

Structure

Type

Specification Volume m3 Material

Item Test Method Description

Bottom Tightness test

Shell Tightness test and strength test

Fixed

Roof

Tightness test and strength test Positive pressure kPa, check with soapsuds

Stability test Negative pressure kPa, observe

Floating Roof/Inner Floating Roof

Flotation Test Water filling test method

Central Drain Pipe Leak Test Making observation and inspection during water filling

Test Record:











Conclusion:













Owner/Supervision Contractor General Contractor Construction Contractor

Discipline Engineer:







Date:

Discipline Engineer:







Date:

Foreman:

Quality Inspector:

Discipline Engineer:



Date:

SH/T 3503— 2017

323

SH/T 3503— J334

湿式气柜组装质量检验记录

Wet Gas Holder Assembling

Quality Inspection Record

工程名称:

Project Name:



单位工程名称:

Unit Name:

Equipment

Description

Equipment

Item No.

Structure

Type

Specification Volume m3 Material

Item Allowable Value, mm Max. Actual Value, mm Remarks

Bottom Plate Local Irregularity

Bell Dome

Angle Ring

Deviation in Diameter

Horizontal Deviation

Bell Shell Deviation in Diameter Local Irregularity

Water Tank

Wall

Diameter Difference between Top Course

and Bottom Course

Upper &

Lower Water

Seal

Vertical Deviation of Vertical Plate

Deviation in Diameter of Vertical Plate

Levelness of Horizontal Plate

Inspection Item and Requirements Inspection Result

Diameter deviation and local irregularity of the intermediate course of shell shall

meet the requirements of the design documents and specifications.

Circumferential deviation of post centers and deviation in distance between two

posts shall meet the requirements of the design documents and specifications.

Radial and tangential deviation of straight guide rails shall meet the requirements of

the design documents and specifications.

Deviation in circumferential distance between two adjacent straight guide rails shall

meet the requirements of the design documents and specifications.

Deviation in parallelism of two adjacent helical guide rails and radial deviation from

the reference circle shall meet the requirements of the design documents and

specifications.



Conclusion:







Owner/Supervision Contractor General Contractor Construction Contractor

Discipline Engineer:







Date:

Discipline Engineer:







Date:

Foreman:

Quality Inspector:

Discipline Engineer:



Date:

SH/T 3503— 2017

324

SH/T 3503— J335-1

湿式气柜底板严密性试验记录

Wet Gas Holder Bottom Plate

Tightness Test Record

工程名称:

Project Name:



单位工程名称:

Unit Name:

Equipment

Description

Equipment

Item No.

Structure

Type

Specification Volume m3 Material

Test Date

Test Method: Vacuum Degree kPa, check with soapsuds.







Test Record:



























Conclusion:











Owner/Supervision Contractor General Contractor Construction Contractor

Discipline Engineer:







Date:

Discipline Engineer:







Date:

Foreman:

Quality Inspector:

Discipline Engineer:



Date:

SH/T 3503— 2017

325

SH/T 3503— J335-2

湿式气柜开孔

补强圈气密性试验记录

Wet Gas Holder Opening Reinforcing

Ring Tightness Test Record

工程名称:

Project Name:



单位工程名称:

Unit Name:

Equipment

Description

Equipment

Item No.

Structure

Type

Specification Volume m3 Material

Test Date:

Test Nozzle No.:







Test Method:

Fill with air kPa, check with soapsuds.

Test Record:



















Conclusion:







Owner/Supervision Contractor General Contractor Construction Contractor

Discipline Engineer:







Date:

Discipline Engineer:







Date:

Foreman:

Quality Inspector:

Discipline Engineer:



Date:

SH/T 3503— 2017

326

SH/T 3503— J335-3

湿式气柜水槽严密性试验记录

Wet Gas Holder Water Tank

Tightness Test Record

工程名称:

Project Name:



单位工程名称:

Unit Name:

Equipment

Description

Equipment

Item No.

Structure

Type

Specification Volume m3 Material

Test Date:

Test Method: Water filling test method.









Test Record:

























Conclusion:













Owner/Supervision Contractor General Contractor Construction Contractor

Discipline Engineer:







Date:

Discipline Engineer:







Date:

Foreman:

Quality Inspector:

Discipline Engineer:



Date:

SH/T 3503— 2017

327

SH/T 3503— J335- 4

湿式气柜整体试验记录

Wet Gas Holder Integral

Test Record

工程名称:

Project Name:



单位工程名称:

Unit Name:

Equipment

Description

Equipment

Item No.

Structure

Type

Specification Volume m3 Material

Item Test Method Test Date Result

Lowering Test

and Tightness

Test On Bell and

Intermediate

Section

Shell Tightness Fill with air kPa, and check with soapsuds

Lifting/Lowering of

Each Section Observe and check

Gas Holder

Rapid Lifting/

Lowering Test

Match-up of Upper

and Lower Water Seal Observe and check

Tightness of Top Bell

Plate

Fill with air kPa, and

check with soapsuds

Contact between

Sheave and Guide Rail Observe and check

Balance of

Counterweight Observe and check

Lifting/Lowering

Number Count and check

Lifting/Lowering Rate Measure and check

Safety Limit Test Observe and check

Remarks:







Conclusion:











Owner/Supervision Contractor General Contractor Construction Contractor

Discipline Engineer:







Date:

Discipline Engineer:







Date:

Foreman:

Quality Inspector:

Discipline Engineer:



Date:

SH/T 3503— 2017

328

SH/T 3503— J336

干式气柜组装质量检验记录

Dry Gas Holder Assembling

Quality Inspection Record

工程名称:

Project Name:



单位工程名称:

Unit Name:

Equipment

Description

Equipment

Item No.

Structure

Type

Specification Volume m3 Material

Item Allowable Value, mm Max. Actual Value, mm Remarks

Column

Deviation in Elevation

Deviation in Spacing

Plumbness Circumferential Radial

Holder

Body

Plumbness

Roundness

Deviation in Dimension btw. Top Outer Shape of Piston

Barrier and Bottom Inner Shape of T-barrier

Deviation in Dimension btw. Outer Edge of Top Shape of

T-barrier and Shell Plate

Roof of

Holder

Annular

Plate

Deviation in Levelness of Horizontal Plate

Deviation in Plumbness of Vertical Plate

Deviation in Distance btw. Column and

Annular Plate

Girder

Axial Deviation of Girder

Deviation in Height of Girder at Dome

Deviation in Curvature Radium of Dome

Inspection Item and Requirements Inspection Result

The overlapping length of bottom plates, piston plates and roof plates of gas holder shall

meet the requirements of the design documents.

The plumbness of posts of piston barrier and height of piston barrier after assembling

shall meet the requirements of the design documents.

The plumbness and levelness of the top and bottom end of T-barrier shall meet the

requirements of the design documents.

The surface of any weld in contact with rubber sealing membrane shall be ground smooth

as specified in the applicable specifications.

Guide device, leveling device and release device shall be installed in accordance with the

requirements of the design documents. Sheave shall move freely.

Conclusion:

Owner/Supervision Contractor General Contractor Construction Contractor

Discipline Engineer:







Date:

Discipline Engineer:







Date:

Foreman:

Quality Inspector:

Discipline Engineer:



Date:



SH/T 3503— 2017

329



SH/T 3503— J337-1

干式气柜底板/活塞板/

壁板严密性试验记录

Dry Gas Holder Bottom Plate/Piston

Plate/Shell Plate Tightness Test Record

工程名称:

Project Name:



单位工程名称:

Unit Name:

Equipment

Description

Equipment

Item No.

Structure

Type

Specification Volume m3 Material

Test Date

Test Item: □Gas Holder Bottom Plate □Piston Plate □Shell of Gas Storage Section □Bottom of T-barrier







Test Method: □Vacuum Degree kPa, check with soapsuds;

□Fill with air kPa, check with soapsuds;

□ Leak test with kerosene.





Test Record:

Conclusion:



Owner/Supervision Contractor General Contractor Construction Contractor

Discipline Engineer:







Date:

Discipline Engineer:







Date:

Foreman:

Quality Inspector:

Discipline Engineer:



Date:

SH/T 3503— 2017

330

SH/T 3503— J337-2

干式气柜开孔

补强圈气密性试验记录

Dry Gas Holder Opening Reinforcing

Ring Tightness Test Record

工程名称:

Project Name:



单位工程名称:

Unit Name:

Equipment

Description

Equipment

Item No.

Structure

Type

Specification Volume m3 Material

Test Date:

Test Nozzle No.:







Test Method: Fill with air kPa, check with soapsuds.







Test Record:









Conclusion:











Owner/Supervision Contractor General Contractor Construction Contractor

Discipline Engineer:







Date:

Discipline Engineer:







Date:

Foreman:

Quality Inspector:

Discipline Engineer:



Date:

SH/T 3503— 2017

331

SH/T 3503— J337-3

干式气柜总体试验记录

Dry Gas Holder Integral

Test Record

工程名称:

Project Name:



单位工程名称:

Unit Name:

Equipment

Description

Equipment

Item No.

Structure

Type

Specification Volume m3 Material

Item Test Method Test Date Result

Gas Holder

Test Run

and

Adjustment

Slow Lifting/Lowering Test

on Piston Observe and check

Rapid Lifting/Lowering Test

on Piston Observe and check

Gas Holder

Tightness

Test

Tightness of Shell of Storage

Section

Fill with air kPa,

and check with soapsuds.

Tightness of Piston Plate Fill with air kPa, and check with soapsuds.

Tightness of Welds of Shapes

for Sealing and Erection of

Piston Barrier and T-barrier

Fill with air kPa,

and check with soapsuds.

Tightness of Sealing Device Fill with air kPa, and check with soapsuds.

Integral Indirect Tightness

Test

Capacity measurement

method

Lifting/Lowering Rate Measure and check

Remarks:









Conclusion:









Owner/Supervision Contractor General Contractor Construction Contractor

Discipline Engineer:







Date:

Discipline Engineer:







Date:

Foreman:

Quality Inspector:

Discipline Engineer:



Date:



SH/T 3503— 2017

332



SH/T 3503— J338

火炬塔架和管筒安装检验记录

Flare Derrick and Stack

Installation Inspection Record

工程名称:

Project Name:



单位工程名称:

Unit Name:

Equipment

Description

Equipment

Item No.

Actually Measured Item Allowable Value mm Actual Value mm

Stack

Max. Deviation in Cross

Sectional Width

Max. Deviation in Pitch

Deviation in Elevation

Height Deviation

Vertical

Deviation

0o

90o

Shaft

Deviation in Elevation

Deviation in Height

Vertical

Deviation

0o

90o

Inspection Item and Requirement Inspection Result

Stack

Two cross webs shall be in the same plane.

Bar members shall be intersected at joints.

Appearance quality of welds shall meet the requirements of the

design documents and specifications.

NDT on welds shall meet the requirements of the design

documents and specifications.

The maximum deviation in straightness of main structure shall

meet the requirement of the specifications.

Diagonal difference in vertical plane shall meet the requirement of

the specifications.

Shaft

Appearance quality of welds shall meet the requirements of the

design documents and specifications.

NDT on shaft welds shall meet the requirements of the design

documents and specifications.

Refractory lining shall meet the requirements of the design

documents and specifications.

Conclusion:

Owner/Supervision Contractor General Contractor Construction Contractor

Discipline Engineer:







Date:

Discipline Engineer:







Date:

Foreman:

Quality Inspector:

Discipline Engineer:



Date:

SH/T 3503— 2017

333

SH/T 3503— J339

隔热耐磨衬里质 量检验记录

Thermal-insulating and

Abrasion-resistant Lining

Quality Inspection Record

工程名称:

Project Name:



单位工程名称:

Unit Name:

Equipment

Description

Equipment

Item No.

Lining Structure

S/N Inspection Item Inspection Result Inspection Date

Inspector

Owner/Supervision

Contractor

General

Contractor

Construction

Contractor

I Lining Material Certificate and Retest Report

II Equipment Wall Surface Preparation

III Stud Anchor



1 Stud Anchor Layout

2 Stud Anchor Welding

3 Plumbness of Stud Anchor to Equipment Wall

4 Welding of Stud Anchor with End Plate

IV Hex Mesh



1 Hex Mesh Splicing and Installation

2 Welding of Hex Mesh with End Plate and Baffle

3 Welding of Hex Mesh with Insert Pipe

V Metal Insert and Ceramic Fiber Paper Wrapped outside Insert Pipe

VI Double-Layered Lining with Hex Mesh

1 Quality of Concrete in Thermal-Insulating Layer

2 Quality of Concrete in Abrasion-Resistant Layer

VII

Quality of Concrete in Highly

Abrasion-Resistant Layer of

Single-Layered Lining with Hex Mesh



VIII

Quality of Concrete in Thermal-Insulating

and Abrasion-Resistant Layer of

Single-Layered Lining without Hex Mesh



IX Double-Layered Lining with Side Ring Type Stud Anchor

1 Quality of Concrete in Thermal-Insulating Layer

2 Quality of Concrete in Abrasion-Resistant Layer

X

Quality of Concrete in Highly

Abrasion-Resistant Layer of

Single-Layered Lining with Side Ring

Type Stud Anchor



XI Test Cube

Remarks:

SH/T 3503— 2017

334



SH/T 3503— J340

热 交 换设备耐压和 泄漏 试验记录

Heat Exchanger Pressure and

Leak Test Record

工程名称:

Project Name:



单位工程名称:

Unit Name:

Equipment

Description

Equipment

Item No.

Product

No.

Model Operating Medium Tube Side: MPa Shell Side: MPa

Design

Pressure

Tube Side: MPa

Shell Side: MPa

Design

Temperature

Tube Side: ℃

Shell Side: ℃

Pressure Gage

No.

Pressure Gage

Precision Level

Pressure Gage

Calibration Date

Pressure Gage

Span MPa

Test Medium

Temperature ℃

Ambient

Temperature ℃

Chlorine Ion Content of Test Water for

Austenitic Stainless Steel Equipment mg/L

Test Procedure:







Test

Type Test Location

Test

Medium

Medium

Temp.



Test

Pressure

MPa

Holding

Time

min.

Test

Date

Test

Result

Inspected by

Owner/

Supervision

Contractor

General

Contractor

Construction

Contractor

Pre

ssur

e

Tes

t



Leak

Tes

t





Additional Test:

















SH/T 3503— 2017

335

SH/T 3503— J341

设备耐压 和泄漏 试验记录

Equipment Pressure Test and

Leak Test Record

工程名称:

Project Name:



单位工程名称:

Unit Name:

Test Type Product No.

Equipment

Description

Equipment Item

No.

Design Pressure MPa Operating Medium

Design

Temperature ℃

Pressure Gage

No.

Pressure Gage

Precision Level

Pressure Gage

Span MPa

Pressure Gage

Calibration Date

Pressure Gage

Dial Diameter mm

Ambient

Temperature ℃

Test Medium

Temperature ℃

Chlorine Ion Content of Test Water for

Austenitic Stainless Steel Equipment mg/L

Pressure Test

Test

Location Test Medium

Test

Pressure MPa Holding Time min

Test

Conclusion

□ Leak □ Free of Leak

□ Visible Abnormal Deformation □ Free of Visible Abnormal Deformation

□ Abnormal Noise □ Free of Abnormal Noise

□ Unacceptable □ Acceptable

Leak Test

Test

Location

Test

Medium

Test

Pressure MPa

Holding

Time min

Test

Conclusion

□ Leak □ Free of Leak

□ Visible Abnormal Deformation □ Free of Visible Abnormal Deformation

□ Abnormal Noise □ Free of Abnormal Noise

□ Unacceptable □ Acceptable

Additional Test













Owner/Supervision Contractor General Contractor Construction Contractor

Discipline Engineer:







Date:

Discipline Engineer:







Date:

Foreman:

Quality Inspector:

Discipline Engineer:



Date:

SH/T 3503— 2017

336



SH/T 3503— J342

设备热处理报告

Equipment Heat Treatment

Report

工程名称:

Project Name:



单位工程名称:

Unit Name:

Equipment

Description

Equipment

Item No. Product No.

HT

Location Material Report No.

Heat

Treatment

Method

Test Specimen Heat

Treatment Status

Test

Specimen

Number

Heat Treatment Process Requirements

Heating

Rate

℃ /h

Holding

Temperature



Holding

Time

h

Cooling

Rate

℃ /h

Cooling

Method and

Time

□ HT in Same Furnace □ No Specimen

Heat Treatment Temperature-Time Curve



















Attached: Heat treatment temperature-time curve recorded by automatic recorder.

Description on Heat Treatment Method (including information on main HT equipment, quantity of instruments

and thermocouples to be used, insulation layer, etc.)









Conclusion:







Owner/Supervision

Contractor General Contractor Construction Contractor Heat Treatment Contractor

Discipline Engineer:







Date:

Discipline Engineer:







Date:

Foreman:

Quality Inspector:

Discipline Engineer:



Date:

Foreman:

Quality Inspector:

Discipline Engineer:



Date:

SH/T 3503— 2017

337



SH/T 3503— J343

管式炉炉体钢结构安装

检验记录

Tubular Furnace Structural Steel

Installation Inspection Record

工程名称:

Project Name:



单位工程名称:

Unit Name:

Equipment

Description

Equipment

Item No. Structure Type

Item

Allowable

Value

mm

Checked

Points

Qualified

points

Max.

Deviation

mm

Result Remarks

Column

Central

Position

Deviation

Horizontal

Longitudinal

Vertical Deviation

Deviation in Elevation of

Column Bottom

Column Distortion

Deviation

Deviation in Straightness

Beam

Deviation in Elevation

Horizontal Deviation

Central Position Deviation

Frame Diagonal Difference

Cylindrical

Furnace

Inner Radius Deviation

Roundness

Furnace

Shell

Plumbness

Levelness

Inspection Item & Requirement Result

Appearance quality of main furnace structural welds shall meet the requirements of

the design documents and applicable specifications.

Appearance quality of furnace shell welds shall meet the requirements of the

applicable specifications.

Appearance quality of stair and platform plate welds shall meet the requirements of

the applicable specifications.

Remarks:





Owner/Supervision Contractor General Contractor Construction Contractor

Discipline Engineer:







Date:

Discipline Engineer:







Date:

Foreman:

Quality Inspector:

Discipline Engineer:



Date:

SH/T 3503— 2017

338

SH/T 3503— J344

炉管通球试验记录

Furnace Tube PIG Inspection

Record

工程名称:

Project Name:



单位工程名称:

Unit Name:

Equipment

Description

Equipment Item

No.

Furnace Tube

Specification

Furnace Tube

Material

PIG Inspection

Location

PIG Inspection

Method

Furnace Tube

Inner Radius mm PIG Material mm

Furnace Tube

Bending Radius mm

Actual PIG

Outer Radius mm

PIG Design

Radius mm

Applied PIG

Number

Sketch showing the structure of the furnace tube subject to the PIG inspection and the inspection method:

















Conclusion:













Owner/Supervision Contractor General Contractor Construction Contractor

Discipline Engineer:







Date:

Discipline Engineer:







Date:

Foreman:

Quality Inspector:

Discipline Engineer:



Date:



SH/T 3503— 2017

339



SH/T 3503— J345

管式炉附件安装质量检验记录

Pipe Heater Attachment Installation

Quality Inspection Record

工程名称:

Project Name:



单位工程名称:

Unit Name:

Equipment

Description

Equipment

Item No.

S/N Inspection Item Inspection Requirement Inspection Result Inspection Date

1 Burner Internal Cleaning and Assembling Conforming to the requirements of the applicable specifications.

2 Burner Elevation, Central Position and Levelness/Plumbness Conforming to the requirements of the design documents and specifications.

3 Access Door Elevation and Central Position Conforming to the requirements of the design documents and specifications.

4 Explosion Door Elevation and Central Position Conforming to the requirements of the design documents and specifications.

5 Peep Hole Elevation and Central Position Conforming to the requirements of the design documents and specifications.

6 Cleanout Elevation and Central Position Conforming to the requirements of the design documents and specifications.

7 Soot Blower Elevation, Central Position and Levelness Conforming to the requirements of the design documents and specifications.

8 Soot Blower Testing Conforming to the requirements of the applicable specification.

9 Air Duct System Installation Conforming to the requirements of the applicable specification.

10 Flue System Installation Conforming to the requirements of the applicable specification.

Conclusion:







Remarks:







Owner/Supervision Contractor General Contractor Construction Contractor

Discipline Engineer:







Date:

Discipline Engineer:







Date:

Foreman:

Quality Inspector:

Discipline Engineer:



Date:

SH/T 3503— 2017

340

SH/T 3503— J346

耐火砖砌筑炉衬质量检验记录

Refractory Brick Furnace Lining

Quality Inspection Record

工程名称:

Project Name:



单位工程名称:

Unit Name:

Equipment

Description

Equipment

Item No.

Item Allowable Value, mm Max. Actual Value, mm

Actual

Measured

Points

Qualified

Points

Qualified

Rate, %

Wall

Plumbness

Per Meter

Full Height

Wall

Flatness

Brick Masonry Wall Surface

Hanging Brick Wall Surface

Top Surface of Wall under Skew

Brick

Wall

Levelness

Per Meter

Full Length

Linear

Dimension

Deviation

Length of Box-Type Furnace

Width of Box-Type Furnace

Diagonal Difference of

Box-Type Furnace

Inner Radius of Cylindrical

Furnace

Span of Dome

Height and Width of Stack

Roundness of Wall of Cylindrical Furnace

Deviation in Width of Expansion Joint

Deviation in Width of Masonry Joints

Deviation in Central Position of Burner Tile

Concentricity Deviation between Upper and

Lower Burner Tile Course

Deviation in Size of Expansion Joint

between Burner and Masonry

Inspection Item Inspection Requirement Inspection Result Inspection Date

Refractory Product Certificate

Conforming to the requirements of the

design documents and specifications

and verified as acceptable by retest.



Brick Masonry Joint Arrangement, Dome Roof

Lock Brick Arrangement and Piece Number

Conforming to the requirements of the

applicable specifications.

Surface Levelness, Smoothness and Fullness

of Mortar

Conforming to the requirements of the

applicable specifications.

Conclusion:

Owner/Supervision Contractor General Contractor Construction Contractor

Discipline Engineer:





Date:

Discipline Engineer:





Date:

Foreman:

Quality Inspector:

Discipline Engineer:

Date:

SH/T 3503— 2017

341

SH/T 3503— J347

耐火浇注料炉衬质量检验记录

Refractory Castable Lining

Quality Inspection Record

工程名称:

Project Name:



单位工程名称:

Unit Name:

Equipment

Description

Equipment

Item No.

Item

Allowable

Value

mm

Actual

Maximum Value

mm

Actually

Measured

Points

Qualified

Points

Qualified Rate

%

Lining Thickness Deviation

Lining Surface Levelness

Lining Surface Plumbness

Deviation in Width of Expansion

Joint

Deviation in Geometrical

Dimension of Box-Type Furnace

Cylindrical Furnace Lining

Roundness

Deviation in Inner Radius of

Cylindrical Furnace Lining

Inspection Item Inspection Requirement Inspection Result Inspection Date

Material Certificate and Retest

Report

Conforming to the requirements of design

documents and specifications and verified

as acceptable by retest



Shell Surface Preparation Conforming to the requirements of the applicable specifications.

Stud Anchor Layout, Spacing

and Welding

Conforming to the requirements of the

design documents and specifications.

Timing for Adding Steel Fiber

and Quantity

Conforming to the requirements of the

applicable specifications.

Type of Construction Joint Conforming to the requirements of the applicable specifications.

Curing Temperature and Time Conforming to the requirements of the design documents and specifications.

Surface Quality Conforming to the requirements of the applicable specifications.

Test Cube Conforming to the requirements of the design documents and specifications.

Remarks:

Conclusion:

Owner/Supervision Contractor General Contractor Construction Contractor

Discipline Engineer:







Date:

Discipline Engineer:







Date:

Foreman:

Quality Inspector:

Discipline Engineer:



Date:

SH/T 3503— 2017

342



SH/T 3503— J348

耐火纤维模块炉衬

质量检验记录

Refractory Fiber Module Lining

Quality Inspection Record

工程名称:

Project Name:



单位工程名称:

Unit Name:

Equipment

Description

Equipment

Item No.

Item

Allowable

Value

mm

Actually

Measured

Points

Qualified

Points

Qualified

Rate

%

Max. Actual

Value

mm

Deviation in Thickness of

Module Lining

Lining Surface Levelness

Lining Surface Plumbness

Inspection Item Inspection Requirement Inspection Result Inspection Date

Material Certificate and Retest Report

Conforming to the requirements of the

design documents and specifications

and verified as acceptable by retest.



Stud Anchor Layout, Spacing and

Welding

Conforming to the requirements of the

design documents and specifications.

Module Arrangement Conforming to the requirements of the design documents and specifications.

Connection of Module with Other

Refractory Lining in Nonfolding Direction

Conforming to the requirements of the

design documents and specifications.

Timing for Removal of Bandaging and

Packing for Modules

Conforming to the requirements of the

design documents and specifications.

Remarks:











Conclusion:







Owner/Supervision Contractor General Contractor Construction Contractor

Discipline Engineer:







Date:

Discipline Engineer:







Date:

Foreman:

Quality Inspector:

Discipline Engineer:



Date:



SH/T 3503— 2017

343



SH/T 3503— J349-1

设备及构件焊缝射线检测报告

Equipment and Structure

Weld RT Report

第 页 共 页 Page of

工程名称:

Project Name:



单位工程名称:

Unit Name:

Entrusted

by Construction Contractor Report No.

Test Piece

No.

Test Piece

Description Test Criteria

Qualified

Level

Test Piece

Material

Welding

Process

Technique

Level

Test

Percentage %

Test

Timing

Developing

Temperature ℃

Developing

Time min Film Density

Weld Size

mm×mm

Radi

ogr

ap

hy



Me

thod



Wire

Dia.

No.

Focal

D

ist

ance



mm



Ef

fect

ive Fi

lm



Lengt

h Tube Voltage/

Source

Energy

Tube

Current/

Source

Activity

Exposure

Time

Equipment

Model/

Source

Type

Focus

Size

Intensifying

Method

Film

Designation







Test Lot

No. Weld No.

Welder’s

Stamp No. Weld Size

Film

No.

Defect

Nature

Defect

Quantity

Evaluated

Level Remarks



























Evaluated by:



Qualification: RT Level

Reviewed by:



Qualification: RT Level

Inspection Agency: (Seal)



Report Date:



SH/T 3503— 2017

344



SH/T 3503— J349-2

设备及构件

焊缝射线检测报告 (续)

Equipment and Structure

Weld RT Report (Continued)

第 页 共 页 Page of

工程名称:

Project Name:



单位工程名称:

Unit Name:

Entrusted

by

Construction

Contractor Report No.

Test Lot

No. Weld No.

Welder’s

Stamp No. Weld Size

Film

No.

Defect

Nature

Defect

Quantity

Evaluated

Level Remarks



















































SH/T 3503— 2017

345

SH/T 3503— J350-1

设备及构件焊缝超声检测报告

Equipment and Structure

Weld UT Report

第 页 共 页 Page of

工程名称:

Project Name:



单位工程名称:

Unit Name:

Entrusted

by

Construction

Contractor

Report

No.

Test Piece

No.

Test Piece

Description

Test

Criteria

Qualified

Level

Test Piece

Material

Welding

Process

Technique

Level

Test

Percentage

Test Timing Groove Type Couplant Test Sensitivity

Probe Test Coupon Test

Surface

Equipment

Model

Surface

Condition

Surface

Compensation

Scanning

Percentage S/N Model Model 1 Model 2







Test Lot

No. Weld No.

Welder’s

Stamp No. Weld Size

Probe

No.

Defect or Defect

Sketch No.

Evaluated

Level Remarks































Tested by:



Qualification: UT Level

Reviewed by:



Qualification: UT Level

Inspection Agency: ( Seal)



Report Date:



SH/T 3503— 2017

346

SH/T 3503— J350-2

设备及构件

焊缝超声检测报告 (续)

Equipment and Structure

Weld RT Report (Continued)

第 页 共 页 Page of

工程名称:

Project Name:



单位工程名称:

Unit Name:

Entrusted

by

Construction

Contractor Report No.

Test Lot

No. Weld No.

Welder’s

Stamp No. Weld Size

Probe

No.

Defect or Defect

Sketch No.

Evaluated

Level Remarks



















































SH/T 3503— 2017

347

SH/T 3503— J351-1

设备及构件

焊缝磁粉检测报告

Equipment and Structure

Weld MT Report

第 页 共 页 Page of

工程名称:

Project Name:



单位工程名称:

Unit Name:

Entrusted by Construction Contractor Report No.

Test Piece

No.

Test Piece

Description Test Criteria

Qualified

Level

Test Piece

Material

Welding

Process

Test

Percentage

Heat Treatment

Status

Test Timing Surface Condition Current Type Magnetization Method

Equipment

Model Pole Distance Lift/Current

Magnetization

Time

Magnetic

Powder Type

Suspension

Density

Application

Method

Sensitivity

Test Coupon

Test Lot

No. Weld No.

Welder’s

Stamp No. Weld Size

Test

Surface

Defect

Description/

Sketch No.

Evaluated

Level Remarks



































Tested by:



Qualification: MT Level

Reviewed by:



Qualification: MT Level

Inspection Agency: ( Seal)



Report Date:



SH/T 3503— 2017

348



SH/T 3503— J351-2

设备及构件

焊缝磁粉检测报告 (续)

Equipment and Structure

Weld MT Report (Continued)

第 页 共 页 Page of

工程名称:

Project Name:



单位工程名称:

Unit Name:

Entrusted

by

Construction

Contractor Report No.

Test Lot

No. Weld No.

Welder’s

Stamp No. Weld Size

Test

Surface

Defect

Description/

Sketch No.

Evaluated

Level Remarks





















































SH/T 3503— 2017

349

SH/T 3503— J352-1

设备及构件焊缝渗透检测报告

Equipment and Structure

Weld PT Report

第 页 共 页 Page of

工程名称:

Project Name:



单位工程名称:

Unit Name:

Entrusted by Construction Contractor Report No.

Test Piece

No.

Test Piece

Description Test Criteria

Qualified

Level

Test Piece

Material

Welding

Process

Test

Percentage

Heat Treatment

Stat

Test Timing Surface Condition Test Method Test Sensitivity

Penetration

Temperature

Observation

Method

Application

Method Test Coupon

Penetration

Time

Developing

Time

Penetrant

Designation

Test Lot

No. Weld No.

Welder’s

Stamp No. Weld Size

Test

Surface

Defect

Description/

Sketch No.

Evaluated

Level Remarks



































Tested by:



Qualification: PT Level

Reviewed by:



Qualification: PT Level

Inspection Agency: ( Seal)



Report Date:

SH/T 3503— 2017

350



SH/T 3503— J352-2

设备及构件

焊缝渗透检测报告 (续)

Equipment and Structure Weld

PT Report (Continued)

第 页 共 页 Page of

工程名称:

Project Name:



单位工程名称:

Unit Name:

Entrusted

by

Construction

Contractor Report No.

Test Lot

No. Weld No.

Welder’s

Stamp No. Weld Size

Test

Surface

Defect Description/

Sketch No.

Evaluated

Level Remarks





















































SH/T 3503— 2017

351

附 录 D

Appendix D

(规范性附录)

(Normative Appendix)

交工技术文件 管道安装工程用表

Handover Technical Documentation — Piping Installation

序号

S/N

名 称

Description

编 号

No.

页次

Page No.

D.1

管道组成件验证性和补充性检验记录

Piping Components Verification Inspection & Additional

Inspection Record

SH/T 3503- J401 353

D.2 阀门试验确认表 Valve Test Confirmation Form SH/T 3503- J402 354

D.3 弹簧支 /吊架安装检验记录 Spring Support/Hanger Installation Inspection Record SH/T 3503- J403 355

D.4 滑动 /固定管托安装检验记录 Sliding/Fixed Pipe Shoe Installation Inspection Record SH/T 3503- J404 356

D.5

管道补偿器安装检验记录

Pipe Compensator Installation Inspection Record SH/T 3503- J405 357

D.6 管道系统压力试验条件确认记录 Piping System Pressure Test Condition Confirmation Record SH/T 3503- J406- 1 358

D.7 管道系统压力试验记录 Piping System Pressure Test Record SH/T 3503- J406- 2 359

D.8

管道系统泄漏性 /真空试验条件确认与试验记录

Piping System Leak/Vacuum Test Condition Confirmation and

Test Record

SH/T 3503- J407 360

D.9 管道吹扫 /清洗检验记录 Piping Purging/Cleaning Inspection Record SH/T 3503- J408 361

D.10

给排水压力 流 管道压力试验条件确认与试验记录

Water Supply & Drainage (Pressure Flow) Piping Pressure Test

Condition Confirmation and Test Record

SH/T 3503- J409A 362

D.11

给排水压力 流 管道放水法试验记录

Water Supply & Drainage (Pressure Flow) Piping Dewatering

Test Record

SH/T 3503- J409B 363

D.12

给排水压力 流 管道注水法试验记录

Pressure Water Supply & Drainage (Pressure Flow) Piping Water

Filling Test Record

SH/T 3503- J409C 364

SH/T 3503— 2017

352

序号

S/N

名 称

Description

编 号

No.

页次

Page No.

D.13

给排水无压力管道闭水试验条件确认与试 验记录

Water Supply & Drainage (Non-pressure) Piping Closed Water

Test Condition Confirmation and Test Record

SH/T 3503- J410 365

D.14 管道焊接接头热处理报告 Piping Welded Joint Heat Treatment Report SH/T 3503- J411- 1 366

D.15 管道焊接接头热处理报告(续) Piping Welded Joint Heat Treatment Report SH/T 3503- J411- 2 367

D.16 管道无损检测结果汇总表 Summary of Piping NDT Results SH/T 3503- J412- 1 368

D.17 管道无损检测结果汇总表(续) Summary of Piping NDT Results (Continued) SH/T 3503- J412- 2 369

D.18 管道无损检测数量统计表 Piping NDT Quantity Statistical Form SH/T 3503- J413- 1 370

D.19 管道无损 检测数量统计表(续) Piping NDT Quantity Statistical Form (Continued) SH/T 3503- J413- 2 371

D.20 管道试压包一览表 List of Piping Pressure Test Packages SH/T 3503- J414 372

D.21 管道焊接工作记录 Piping Welding Record SH/T 3503- J415- 1 373

D.22 管道焊接工作记录(续) Piping Welding Record (Continued) SH/T 3503- J415- 2 374

D.23 管道静电接地测试记录 Piping Electrostatic Grounding Test Record SH/T 3503- J416 375



SH/T 3503— 2017

353

SH/T 3503— 2017

354



SH/T 3503— 2017

355



SH/T 3503— J403 弹簧支 /吊架安装检验记录

Spring Support/Hanger

Installation Inspection Record

工程名称:

Project Name:



单位工程名称:

Unit Name:

Piping No./Line No. Support/Hanger Item No. Structure Type Displacement Direction Design Cold Load Installation Cold Load Inspection Result







































Remarks:









Owner/Supervision Contractor General Contractor Construction Contractor

Discipline Engineer:







Date:

Discipline Engineer:







Date:

Foreman:

Quality Inspector:

Discipline Engineer:



Date:

SH/T 3

503



20

××



SH/T 3

503



20

××



SH/T 3503— 2017

356

SH/T 3503— J404

滑动 /固定管托安装检验 记录

Sliding/Fixed Pipe Shoe

Installation Inspection Record

工程名称:

Project Name:



单位工程名称:

Unit Name:

Piping No./

Line No. Pipe Shoe No. Type

Displacement

Direction

Design

Displacement

Installation

Displacement

Inspection

Result







































Note: This form is applicable to the installation inspection on sliding/fixed pipe shoes with displacement

requirement used in piping at a design temperature above 350℃ and in piping at a design temperature below

-29℃ .

Remarks:





Owner/Supervision Contractor General Contractor Construction Contractor

Discipline Engineer:







Date:

Discipline Engineer:







Date:

Foreman:

Quality Inspector:

Discipline Engineer:



Date:

SH/T 3503— 2017

357



SH/T 3503— 2017

358

SH/T 3503— J406-1

管道系统压力试验条件

确认记录

Piping System Pressure Test

Condition Confirmation Record

工程名称:

Project Name:



单位工程名称:

Unit Name:

System Description System No.

Inspection Item and Requirement Inspection Result

Piping shall be installed in accordance with the requirements of the

design documents and applicable specifications.

Piping components shall be re-inspected and verified as acceptable.

Welding records shall be complete.

NDT results shall be in compliance with the requirements of the design

documents and applicable specifications.

PWHT results shall be in compliance with the requirements of the design

documents and applicable specifications.

Supports and hangers shall be correctly installed.

Alloy steel piping shall bear clear identification marks on material.

Safety attachments and instruments not to be tested shall be dismantled

or isolated as required. All valves in the test system shall be opened.

Temporary reinforcements, blind positions and markings shall meet the

requirements in the construction plan.

Welded joints and parts subject to the test shall not be covered.

The scale, accuracy and calibration state of the pressure gauges to be used in

the test shall meet the requirements of the applicable specifications.

Test water to be used in stainless steel piping shall meet the requirements of the

applicable specifications and a water quality analysis report shall be attached.

Remarks:















Owner/Supervision Contractor General Contractor Construction Contractor

Discipline Engineer:







Date:

Discipline Engineer:







Date:

Foreman:

Quality Inspector:

Discipline Engineer:



Date:

SH/T 3503— 2017

359

SH/T 3503— J406-2

管道系统压力试验记录

Piping System Pressure Test

Record

工程名称:

Project Name:



单位工程名称:

Unit Name:

System Description System No.

Test Record

Piping No./

Line No.

Design

Pressure

MPa

Design

Temperature



Test

Ambient

Temperature



Test

Medium

Test

Medium

Temperature



Test

Pressure

MPa

Holding

Time

min



































Conclusion:

Owner/Supervision Contractor General Contractor Construction Contractor

Discipline Engineer:







Date:

Discipline Engineer:







Date:

Foreman:

Quality Inspector:

Discipline Engineer:



Date:



SH/T 3503— 2017

360



SH/T 3503— J407

管道系统泄漏性 /真空

试验条件确认与试验记录

Piping System Leak/Vacuum

Test Condition Confirmation

and Test Record

工程名称:

Project Name:



单位工程名称:

Unit Name:

System

Description System No.

Inspection Item and Requirement Inspection Result

The piping system shall pass the pressure test.

Temporary flanges, bolts and gaskets used in the pressure test shall be

replaced.

Safety attachments and instruments not involved in the pressure test shall be

reinstalled.

All valves in the piping system to be tested shall be opened.

The scale, accuracy and calibration state of the pressure gauges to be used in

the test shall meet the requirements of the applicable specifications.

Test Record

Piping No./

Line No.

Design

Pressure

MPa

Design

Temperature



Test

Ambient

Temperature



Test

Medium

Temperature



Leak Test Vacuum Test

Pressure

MPa Medium

Pressure

MPa Medium



















Conclusion:

Owner/Supervision Contractor General Contractor Construction Contractor

Discipline Engineer:







Date:

Discipline Engineer:







Date:

Foreman:

Quality Inspector:

Discipline Engineer:



Date:

SH/T 3503— 2017

361

SH/T 3503— J408

管道吹扫 /清洗检验记录

Piping Purging/Cleaning

Inspection Record

工程名称:

Project Name:



单位工程名称:

Unit Name:

System Description System No.

Inspection Item and Requirement Inspection Result

The piping system shall pass the pressure test.

Safety attachments and instruments not subject to purging and cleaning

shall be dismantled or isolated.

All valves in the piping system shall be opened.

Water to be used in stainless steel piping shall meet the requirements of

the applicable specifications.

Piping No./Line No. Material Operating Medium Purging Medium Cleaning Medium



























Note: For water to be used in stainless steel piping, a water quality analysis report shall be attached.

Inspection Method and Conclusion:

Owner/Supervision Contractor General Contractor Construction Contractor

Discipline Engineer:







Date:

Discipline Engineer:







Date:

Foreman:

Quality Inspector:

Discipline Engineer:



Date:



SH/T 3503— 2017

362

SH/T 3503— J409A

给排水压力 流 管道压力试验

条件确认与试验记录

Water Supply & Drainage (Pressure

Flow) Piping Pressure Test Condition

Confirmation and Test Record

工程名称:

Project Name:



单位工程名称:

Unit Name:

System Description System No.

Test Ambient

Temperature ℃

Test Medium

Temperature ℃

Inspection Item and Requirement Inspection Result

Piping installation shall be completed and pipe trench shall be backfilled except

positions where connections exist.

Piping attachments and ancillary structures shall be inspected and verified as acceptable.

Piping connections shall be inspected and verified as acceptable.

The strength of concrete for pipe sleepers and anchoring facilities shall meet the

requirements of the design documents.

The axial position, elevation and gradient of the underground piping, as well as its

foundation and cushion, shall be reinspected and verified as acceptable.

The ends and openings of the tested pipe section shall be sealed.

Piping components not involved in the test shall be dismantled or isolated.

All valves in the test system shall be opened.

The scale, accuracy, calibration state and disc diameter of the pressure gauges to be

used in the test shall meet the requirements of the applicable specifications.

Test Record

Piping No.

Design

Pressure

MPa

Design

Temperature



Test Pressure

MPa Medium

Holding Time

min











Note: The sketch showing the location of the tested piping section shall be attached.

Conclusion:



Owner/Supervision Contractor General Contractor Construction Contractor

Discipline Engineer:







Date:

Discipline Engineer:







Date:

Foreman:

Quality Inspector:

Discipline Engineer:



Date:

SH/T 3503— 2017

363

SH/T 3503— J409B

给排水压力 流 管道放水法

试验记录

Water Supply & Drainage

(Pressure Flow) Piping

Dewatering Test Record

工程名称:

Project Name:



单位工程名称:

Unit Name:

Piping No./

Line No.

Applicable

Standard

Stake Mark &

Location

Tes

t C

ondi

tion

Piping Inner Diameter mm Piping Material Connection Type Test Section Length m



Operating Pressure

MPa

Test Pressure

MPa

10min Pressure Drop

MPa

Allowable Seepage

Quantity

L/(min·km)



Seepage

Q

uant

ity



Me

asur

em

ent

R

ecor

d

Times

Time Used for Test

Pressure Drop of

0.1MPa, T1

min

Time vs. Pressure

Drop of 0.1MPa Due

to Dewatering, T2

min

Dewatering Volume

vs. Pressure Drop of

0.1MPa, W

L

Actual Seepage

Quantity, q

L/(min·km)

1

2

3

Average Actual Seepage Quantity: L/(min·km)

Appearance Inspection:







Conclusion:







Owner/Supervision Contractor General Contractor Construction Contractor

Discipline Engineer:







Date:

Discipline Engineer:







Date:

Foreman:

Quality Inspector:

Discipline Engineer:



Date:

SH/T 3503— 2017

364

SH/T 3503— J409C

给排水压力 流 管道注水法

试验 记录

Water Supply & Drainage

(Pressure Flow) Piping Water

Filling Test Record

工程名称:

Project Name:



单位工程名称:

Unit Name:

Piping No./

Line No.

Applicable

Standard

Stake Mark &

Location

Tes

t C

ondi

tion

Piping Inner Diameter mm Piping Material Connection Type Test Section Length m



Operating Pressure

MPa

Test Pressure

MPa

10min Pressure Drop

MPa

Allowable Seepage

Quantity

L/min·km



Seepage

W

ater

Vol

um

e

Me

asur

em

ent

R

ecor

d

Times

Time to Reach

Test Pressure, T1

min

Holding Ending

Time, T2

min

Holding Time, T

min

Water Added during

Holding Time, W

L

Actual Seepage

Quantity, q

L/(min·km)

1

2

3

Average Actual Seepage Quantity: L/(min·km)

Appearance Inspection:









Conclusion:





Owner/Supervision Contractor General Contractor Construction Contractor

Discipline Engineer:







Date:

Discipline Engineer:







Date:

Foreman:

Quality Inspector:

Discipline Engineer:



Date:



SH/T 3503— 2017

365



SH/T 3503— J410

给排水无压力管道闭水试

验条件确认与试验记录

Water Supply & Drainage

( Non-pressure) Piping Closed

Water Test Condition

Confirmation and Test Record

工程名称:

Project Name:



单位工程名称:

Unit Name:

System Description System No.

Test Ambient

Temperature ℃

Test Medium

Temperature ℃

Inspection Item and Requirement Inspection Result

Piping and manhole shall be completed and meet the quality requirements

of the applicable specifications.

Backfill shall be completed for piping in accordance with requirements of

the applicable code except positions where connections exist.

Pipe trench shall be free from accumulated residual water.

All held openings shall be plugged.

Blanking plates at ends of piping shall meet the requirements of the

construction technical measures.

The axial position, elevation, slope of piping, as well as its foundation and

cushion, shall be reinspected and verified as acceptable.

Test Record

Piping No./

Line No.

Tested Piping Section Test

Head

m

Test

Time

h

Allowable

Seepage

m3/(24·km)

Actual

Seepage

L/ (min·m) Inner Dia., mm Length m Material Nozzle Type

Head of

Upstream

m









Seepage

Quantity

Measurement

Record

Times

Observation

Starting Time, T1

min

Observation

Ending Time, T2

min

Observation Time,

T

min

Water Added

during Holding

Time, W

L

Actual Seepage

Quantity, q

L/(min·m)

1

2

3

Average Actual Seepage Quantity: m3/24h·km

Remarks: The sketch showing the location of the tested pipe section is attached.

Conclusion:

Owner/Supervision Contractor General Contractor Construction Contractor

Discipline Engineer:







Date:

Discipline Engineer:







Date:

Foreman:

Quality Inspector:

Discipline Engineer:



Date:

SH/T 3503— 2017

366



SH/T 3503— 2017

367



SH/T 3503— 2017

368



SH/T 3503— 2017

369



SH/T 3503— 2017

370



SH/T 3503— 2017

371



SH/T 3

503



20

××



SH/T 3

503



20

××



369



SH/T 3

503



20

××



SH/T 3

503



20

××



SH/T 3

503



20

××



SH/T 3

503



20

××



370



SH/T 3503— 2017

372





SH/T 3503— J414

管道试压包一览表

List of Piping Pressure

Test Packages

工程名称:

Project Name:



单位工程名称:

Unit Name:

S/N Piping No./Line No. Test Package No. S/N Piping No./Line No. Test Package No.













































Remarks:







Discipline Engineer:



Date:

Quality Inspector:



Date:

Filled out by:



Date:



SH/T 3503— 2017

373



SH/T 3503— 2017

374

SH/T 3503— 2017

375



SH/T 3503— J416

管道静电接地测试记录

Piping Electrostatic

Grounding Test Record

工程名称:

Project Name:



单位工程名称:

Unit Name:

Piping No./Line No.

Flanged or Threaded Connection Ground Lead

Connection

Type

Bridging Lead Resistance

Value

< 0.03Ω

Specification Material

Resistance

to Ground

< 100Ω Specification Material











































Owner/Supervision Contractor General Contractor Construction Contractor

Discipline Engineer:







Date:

Discipline Engineer:







Date:

Foreman:

Quality Inspector:

Discipline Engineer:



Date:



374



SH/T 3

503



20

××



SH/T 3

503



20

××



SH/T 3503— 2017

376

附 录 E

Appendix E

(规范 性 附录 )

(Normative Appendix)

交工技术文件电气安装工程用表

Handover Technical Documentation — Electrical Installation

序号

S/N

名 称

Description

编 号

No.

页次

Page No.

E.1 变电所受电条件确认表 Substation Energization Condition Confirmation Form SH/T 3503- J501 377

E.2

盘、柜基础型钢安装质量验收记录

Panel/Cabinet Foundation Structural Steel Installation Quality

Acceptance Inspection Record

SH/T 3503- J502 378

E.3 电缆桥架安装检查记录 Cable Tray Installation Inspection Record SH/T 3503- J503 379

E.4 电缆敷设与绝缘检测记录 Cable Laying and Insulation Test Record SH/T 3503- J504 380

E.5 电缆安装质量验收记录 Cable Installation Quality Acceptance Inspection Record SH/T 3503- J505 381

E.6 交流电动机安装检验与空载运行记录 AC Motor Installation Inspection and No-load Running Record SH/T 3503- J506 382

E.7 变压器安装检验记录 Transformer Installation Inspection Record SH/T 3503- J507 383

E.8 高 /低压开关柜安装检验记录 HV/LV Switchgear Installation Inspection Record SH/T 3503- J508 384

E.9 保护 /控制盘(屏)安装检验记录 Protection/Control Panel Installation Inspection Record SH/T 3503- J509 385

E.10 直流系统 /UPS/EPS 安装检验记录 DC System/UPS/EPS Installation Inspection Record SH/T 3503- J510 386

E.11 火灾自动报警系统安装检验记录 Fire Alarm System Installation Inspection Record SH/T 3503- J511 387





SH/T 3503— 2017

377



SH/T 3503— J501

变电所受电条件确认表

Substation Energization

Condition Confirmation Form

工程名称:

Project Name:



单位工程名称:

Unit Name:

S/N Inspection Item and Requirement Inspection Result

1 Panels and cabinets shall be firmly installed, reliably grounded and complete in electrical elements within their enclosure.

2 All electrical equipment shall be clean inside and outside.

3 Electrical equipment shall be complete and free from damage, and bear intact paint and correct and striking color code.

4 Insulated sleeve shall be well insulated and sealed to meet the design and procedure requirements.

5 The substation and transformer room shall be provided with complete indoor firefighting facilities.

6 Cable shall have specification required by the design requirements and bear complete and correct labels. Cable tray shall be free from debris and residual water inside.

7 Cable entry and exit to and from the cabinet shall be blocked tightly for fire protection.

8 The area of energization shall be isolated as required and provided with live safety warning signs, lighting and communications necessary for energization.

9 All primary and secondary electrical equipment within the area of energization shall be tested and provided with complete test report.

10 The testing shall be completed on the corresponding control, protection and system signals within the area of energization of the substation.

11 The DC control power supply shall be reliably and correctly connected and well insulated. The corresponding monitoring meters shall be accurate in indication.

12 The secondary circuit shall be correctly and reliably connected, bear correct and legible numbering, and be completed with interlock testing.

13 All meters in the substation shall be normal in indications and alarm free.

14 The energization plan shall be approved and all organizational, technical and safety measures shall be finalized.

15 The substation shall be provided with complete operating and maintenance tools.

16 The substation shall be provided with adequate facilities for protection against small animals.

Remarks:





Conclusion:



Owner’s Representative:







Date:

Supervision Contractor’s

Representative:





Date:

Contractor’s

Representative





Date:

Related Organization’s

Representative





Date:

SH/T 3503— 2017

378

SH/T 3503— J502

盘、柜基础型钢

安装质量验收记录

Panel/Cabinet Foundation

Structural Steel Installation Quality

Acceptance Inspection Record

工程 名称:

Project Name:



单位工程名称:

Unit Name:

Location Applicable Standard

S/N Inspection Item Quality Criteria Inspection Result

1 Specification and Size of Structural Steel

The specification and installed size of the

structural steel shall meet the requirements of

the design documents.



2 Fixing and Painting of Structural Steel

The structural steel shall be securely welded

and be painted in accordance with the

requirements of the design documents.



3 Grounding of Structural Steel

There are at least two points of reliable

grounding and the connection shall meet the

requirements of the applicable specification.



4 Top Elevation of Structural Steel

The top of the structural steel is preferred to be

10mm above the ground. The handcart cabinet

shall meet the product technical specification.



Foun

datio

n

Struc

tural

Steel

Insta

llatio

n

Reco

rd

Inspection Item Allowable Deviation Actual Deviation

Non-straightness, mm mm/m 1 mm/full length 5

Roughness, mm mm/m 1 mm/full length 5

Position Deviation and

Non-parallelism, mm mm/full length 5

Attached: Sketch showing location of check points for foundation structural steel.





Remarks:



Conclusion:



Owner/Supervision Contractor General Contractor Construction Contractor

Discipline Engineer:







Date:

Discipline Engineer:







Date:

Foreman:

Quality Inspector:

Discipline Engineer:



Date:

SH/T 3503— 2017

379



SH/T 3503— J503

电缆桥架安装检查记录

Cable Tray Installation

Inspection Record

工程名称:

Project Name:



单位工程名称:

Unit Name:

Description Drawing No.

S/N Inspection Item and Requirement Inspection Result Inspection Date

1

Cable tray shall be installed with levelness, verticality, gradient and

direction in compliance with the design requirements. For multi-layer

cable tray, layers shall be evenly spaced with the same curvature and the

bending radius in line with the required bending radius for cable laying.



2 Anticorrosive coat shall be intact.

3

Cable tray shall be firmly connected with the support. Connections

shall be firm, free from burrs, and provided with expansion gap.

Stiffeners shall be installed at bolt connections, bolts tightened, and

nuts located in the outside of the slot board.



4

Expansion joints of at least 20mm shall be installed for steel cable

tray with straight section length over 30m and for aluminum alloy or

glass steel cable tray with straight section length over 15m.



5 Cable tray shall be provided with expansion joint at the position crossing over the deformation joint of any building.

6 The minimum clearance between cable tray and heating piping shall meet the requirements of the applicable specifications.

7 The inside of cable tray shall be flat, smooth and free from debris and burrs.

8 Cable tray separators shall be firmly fixed.

9 Cable tray covers shall be firmly fixed.

10 Cable tray supports shall be reasonably spaced and well welded.

11 Cable tray shall be well grounded.

12 Openings in cable tray for conduit shall be mechanically cut out at 2/3 of the cable tray side wall height or above.

13 Aluminum alloy cable tray, when fixed on steel support/hanger, shall be properly protected against electrochemical corrosion.

Remarks:



Conclusion:



Owner/Supervision Contractor General Contractor Construction Contractor

Discipline Engineer:







Date:

Discipline Engineer:







Date:

Foreman:

Quality Inspector:

Discipline Engineer:



Date:

SH/T 3503— 2017

380



SH/T 3503— 2017

381

SH/T 3503— J505

电缆安装质量验收记录

Cable Installation Quality

Acceptance Inspection Record

工程名称:

Project Name:



单位工程名称:

Unit Name:

S/N Inspection Item and Requirement Inspection Result Inspection Date

1 Cable type and specification shall be in line with the design requirements. Protective layer shall be free from mechanical damage.

2 Cable fixing, bend radius and metal sheath connection for single-core power cables shall meet the requirements of the applicable specifications.

3

The minimum clearances between cables, between cable and other piping,

roads, buildings, etc., either running parallel to or crossing each other, shall

meet the requirements of the applicable specifications.



4 Cables shall be arranged neatly without cross but with allowance.

5

All the grounding contacts of the cable line shall be in good contact with the

grounding electrode, and the grounding resistance shall meet the design

requirements.



6 Cable termination shall be done in accordance with the design or manufacturer''s requirements.

7

Cable terminals and cable connectors shall fixed firmly. Cable terminal shall be

in good contact with the terminal of the connected equipment. The connection

point of the cross connection grounding box and the cross-connection box

should be in good and reliable contact.



8 The phase color code of cable terminals shall be correct, the coating of cable support and other metal parts intact, and the ends of cable conduit tightly sealed.

9 Markers installed shall be complete, correct and legible.

10 Cable trench shall be free from debris and accumulated water and complete with cover plate.

11 Tunnel shall be free from debris and provided with lighting, ventilation, drainage and other facilities in compliance with the design requirements.

12 Route markers of directly buried cable shall be true. Route marks shall be legible and properly secured.

13 Markers and night lighting devices along the sides of underwater cable line and within the anchorage prohibited area shall meet the design requirements.

14 Cable connection and sealing in areas with explosion hazard shall meet the requirements of the applicable specifications.

15 The phase sequence of cable shall be in consistent with the connection phase sequence of equipment, and meet the design requirements.

16 Fire protections shall meet the design requirements and completed in good quality.

Remarks:

Conclusion:

Owner/Supervision Contractor General Contractor Construction Contractor

Discipline Engineer:







Date:

Discipline Engineer:







Date:

Foreman:

Quality Inspector:

Discipline Engineer:



Date:

SH/T 3503— 2017

382

SH/T 3503— J506

交流电动机安装检验与

空载运行记录

AC Motor Installation Inspection

and No-load Running Record

工程名称:

Project Name:



单位工程名称:

Unit Name:

Item No. Drive Description

Nam

epl

ate



Model Rated Power kW Bearing Designation

Stator

Voltage V Rotor Voltage V Standard No.

Stator

Current A Rotor Current A Serial No.

Rotating

Speed r/min Insulation Class

Date of

Manufacture

Protection

Rating IP Explosionproof Mark Manufacturer

Inspection Item and Requirement Inspection Result

Mot

or and

Wi

ring



The name plate parameters, type and class of explosion proofing, as well as categorization

shall meet the requirements of the design documents.

Junction box shall be corrected wired, well fastened and insulated. The electrical

clearance and creepage distance shall be arranged as per specification requirements.

The explosion-proof surface and inlet gland of the explosion-proof junction box shall comply

with relevant requirements. Bolts and locking devices shall be complete and reliable.

Motor and other startup equipment shall be grounded as per requirements.

The insulation resistance of the stator winding shall be measured. MΩ

The surface of collector ring shall be clean and smooth. Brush supporter, brush holder and

electric brush shall be installed as per specification requirements.

Bearing grease (oil) and filling amount shall meet the requirements of the product

technical specification.

Rotor can be turned smoothly without obstruction.

Ci

rcui

t

Short-circuit protective equipment setting

Over-load protective equipment setting

Main circuit insulation resistance MΩ

Control circuit insulation resistance MΩ

Simulation operation of the control, protection and interlock circuit whose function shall

meet the requirements of the design documents.

No-lo

ad

Runn

ing

Stator Current A Rotor Current A Vibration Measurement mm/s (mm)

Motor Temp. ℃ Bearing Temp. Load End: ℃ ; No-load End: ℃

Running Time h Ambient Temp. ℃ Date of Running

Remarks:

Owner/Supervision Contractor General Contractor Construction Contractor

Discipline Engineer:







Date:

Discipline Engineer:







Date:

Foreman:

Quality Inspector:

Discipline Engineer:



Date:

SH/T 3503— 2017

383



SH/T 3503— J507

变压器安装检验记录 Transformer Installation

Inspection Record

工程名称:

Project Name:



单位工程名称:

Unit Name:

Item No. Description

Nam

epl

ate

Model Rated Capacity kVA Manufacturer

Rated

Voltage kV

Cooling

Method

Date of

Manufacture

Rated

Current A

Gross

Weight kg Serial No.

Inspection Item and Requirement Inspection Result

1 The installed central line and elevation of transformer body shall meet the requirements of the design documents.

2 Transformer shall be firmly and reliably installed and fixed.

3 Radiator shall be installed in accordance with the requirements of the product technical specification.

4 All valves in the oil line can be operated easily and shall be in correct opening or closed position. Flanges shall be properly sealed without leakage.

5 Oil conservator shall be installed in accordance with the requirements of the product technical specification and with accurate oil level indication.

6 The surface of porcelain bushing shall be free from cracks or scratches and wiped clean.

7 Oil filled bushing shall be properly installed and sealed with accurate oil level indication.

8 Pressure relief valve shall be properly installed and connected.

9 Emergency pressure protective/relief device shall be properly installed.

10 Moisture absorber shall have unblocked piping, be loaded with dry absorbent and properly oil sealed.

11 Gas relay and thermometer shall be tested and verified as acceptable, properly installed and wired.

12 Fan motor and blades shall be firmly fixed and rotating easily in correct direction without vibration and overheating.

13 Electrical circuits shall be arranged orderly and oil proofed. Junction box shall be properly sealed.

14 Insulation oil shall be acceptable and filled in to the specified level.

15 Grounding wire shall have specification in compliance with the design requirement and be firmly connected.

16 Tap switch shall be put in position of .

17 An overall inspection shall be made on seals for detection of any oil leakage or seepage.

18 Electrical equipment shall be tested and verified as acceptable.

Conclusion:





Owner/Supervision Contractor General Contractor Construction Contractor

Discipline Engineer:







Date:

Discipline Engineer:







Date:

Foreman:

Quality Inspector:

Discipline Engineer:



Date:

SH/T 3503— 2017

384



SH/T 3503— J508

高 /低压开关柜安装检验记录

HV/LV Switchgear

Installation Inspection Record

工程名称:

Project Name:



单位工程名称:

Unit Name:

Description Manufacturer

Construction

Drawing No.

Switchgear

No. Quantity pcs

Inspection Item and Requirement Inspection Result

1 Building work shall be ready for installation of panels and accepted.

2 Foundation structural steel shall be installed and accepted.

3 Appearance and coating shall be in good condition. Installation parts, spare parts and technical documents shall be complete.

4 Electrical elements inside switchgear shall be complete, in good condition, and properly and firmly installed in correct position, whose model and specification shall meet the design requirements.

5 The specification, material, and distance to the ground and phased distance of busbar inside switchgear shall meet the requirements of the design documents and applicable specifications.

6 Busbar shall be installed and connected in accordance with the code requirements. Connecting bolt shall be tightened with proper torque in compliance with the specification requirements.

7 Grounding busbar of switchgear shall be connected reliably with the main grounding network.

8 Drawer in Drawer type switchgear shall have good contact with switchgear. Switchgear body and frame shall be well grounded.

9 Drawer and hand truck type breaker shall be easy to operate. Main contact and secondary circuit connecting plug-in shall have good contact.

10 Switchgear shall be provide with complete protective devices against electrical maloperation. Such devices shall be reliable and easy to operate.

11 Primary and secondary circuit shall be properly and firmly connected, and complete with marks.

12 The opening for panels, cabinets and cable conduits shall be tightly covered and blocked. Appropriate measures shall be taken against freezing of residual water inside cable conduit in icing areas.

13 The inside of switchgear shall be wiped clean.

Swit

chge

ar

Insta

llatio

n

Reco

rd

Inspection Item Allowable Deviation Actual Max. Deviation

Verticality (per meter) 1.5

Horizontal

Deviation, mm

Two adjacent switchgear tops 2

Tops of lined switchgears 5

Face

Deviation, mm

Two adjacent switchgear edges 1

Faces of lined switchgears 5

Joint between Switchgears, mm 2

Conclusion:

Owner/Supervision Contractor General Contractor Construction Contractor

Discipline Engineer:







Date:

Discipline Engineer:







Date:

Foreman:

Quality Inspector:

Discipline Engineer:



Date:



SH/T 3503— 2017

385

SH/T3503— J509

保护 /控制盘(屏)

安装检验记录

Protection/Control Panel

Installation Inspection Record

工程名称:

Project Name:



单位工程名称:

Unit Name:

Description Manufacturer

Construction Drawing

No. Panel No. Quantity pcs

Inspection Item and Requirement Inspection Result

1 Building work shall be ready for installation of panels and accepted.

2 Foundation structural steel shall be installed and accepted.

3 Appearance and coating shall be in good condition. Installation parts, spare parts and technical documents shall be complete.

4

Electrical elements inside panel shall be complete, in good condition, and properly and

firmly installed in correct position, whose model and specification shall meet the

requirements of the design documents.



5 Mini-busbar shall be firmly installed and complete with marks.

6 Secondary circuit shall be properly and firmly connected, and complete with marks.

7 Grounding shall be complete, firm and reliable.

8 Relay test shall be inspected and confirmed as acceptable.

9 Electrical measuring instruments shall be inspected and verified as acceptable.

10 Electrical simulation test shall be inspected and confirmed as acceptable.

11 Cabinet inside shall be wiped clean.

12 Insulation resistance shall meet the requirements of the design documents.

Panel

Inst

all

ati

on R

ecor

d Inspection Item Allowable Deviation Max. Actual Deviation

Verticality (per meter) 1.5

Horizontal

Deviation, mm

Two adjacent panel tops 2

Tops of lined panels 5

Panel Face

Deviation, mm

Two adjacent panel edges 1

Faces of lined panels 5

Joint between Panels, mm 2

Conclusion:





Owner/Supervision Contractor General Contractor Construction Contractor

Discipline Engineer:







Date:

Discipline Engineer:







Date:

Foreman:

Quality Inspector:

Discipline Engineer:



Date:

SH/T 3503— 2017

386

SH/T3503— J510

直流系统 /UPS/EPS

安装检验记录

DC System/UPS/EPS

Installation Inspection Record

工程名称:

Project Name:



单位工程名称:

Unit Name:

Description Item No. Construction Drawing No.

Model Input Voltage V Manufacturer

Rated Capacity kVA Output Voltage V Serial Number

Inspection Item and Requirement Inspection Result

1 Building work shall be ready for installation of panels and cabinets and accepted.

2 Foundation structural steel shall be installed and accepted.

3 Appearance and coating shall be in good condition. Installation parts, spare parts and technical documents shall be complete.

4 Electrical elements inside cabinet shall be firmly installed, securely and correctly wired and complete with identification marks.

5 Secondary circuit shall be calibrated. Plugs shall be installed in correct position with free insertion and extraction and reliable contact.

6 Appearance inspection shall be made on storage battery for detection of any deformation or liquid leakage.

7 Storage battery shall be correctly and firmly assembled and wired.

8 The cabinet body shall be securely, firmly and reliably grounded.

9 Electrical equipment adjustment test shall be inspected and confirmed as acceptable.

10 Electrical measuring instruments shall be inspected and confirmed as acceptable.

11 Storage battery charging and discharging conditions shall be inspected and confirmed as acceptable.

12 Electrical simulation test shall be inspected and confirmed as acceptable.

13 Cabinet inside shall be wiped clean.

14 Insulation resistance shall meet the requirements of the design documents.

Pane

l/Ca

binet

Insta

llati

on

Rec

ord

Inspection Item Allowable Deviation Max. Actual Deviation

Verticality (per meter) 1.5

Horizontal

Deviation, mm

Two adjacent panel tops 2

Tops of lined panels 5

Panel Face

Deviation, mm

Two adjacent panel edges 1

Faces of lined panels 5

Joint between Panels, mm 2

Conclusion:

Owner/Supervision Contractor General Contractor Construction Contractor

Discipline Engineer:







Date:

Discipline Engineer:







Date:

Foreman:

Quality Inspector:

Discipline Engineer:



Date:



SH/T 3503— 2017

387

SH/T3503— J511

火灾自动报警系统

安装检验记录

Fire Alarm System Installation

Inspection Record

工程名称:

Project Name:



单位工程名称:

Unit Name:

Description Construction Drawing No. Applicable Standard

Inspection Item and Requirement Inspection Result

1 The nameplate of alarm controller (panel), detector, alarm button and control equipment shall meet the requirements of the design documents.

2 The model and specification of wire and cable shall meet the requirements of the design documents.

3 Piping and cable duct shall be firmly installed. The position and interval of supports or hangers shall meet the requirements of the applicable specifications.

4 Circuits in different systems, voltage levels and current types shall not be arranged in the same slot of the same conduit or cable duct.

5 Wiring in terminal box shall be firm and reliable and well insulated.

6 The insulation resistance of the circuit shall be measured and filled in Form J504 by loops.

7 Explosion protection and protection seal shall meet the requirements of the applicable specifications.

8 Detector, alarm button and control equipment shall be firmly installed with positions and elevations in compliance with the requirements of the design documents and applicable specifications.

9 Alarm controller (panel) shall be firmly installed and orderly wired. Terminations shall be legibly marked and reliably grounded.

10

Automatic switching between main power supply and stand-by power supply shall be

correct and reliable. The capacity of such power supplies shall meet the requirements of

the applicable standards.



11 All functions of alarm controller (panel) shall be checked after energization and in compliance with the requirement of the applicable specifications and design documents.

12 Detectors and alarm buttons shall be checked one by one by using specific testing apparatus for correct actions.

13 The control functions and linking functions of the alarm system shall be checked by using main power supply and stand-by power supply separately for correctness and reliability.





The system runs continuously for 120 hours from to without any failure.

Conclusion:

Remarks:

Owner/Supervision Contractor General Contractor Construction Contractor

Discipline Engineer:







Date:

Discipline Engineer:







Date:

Foreman:

Quality Inspector:

Discipline Engineer:



Date:



SH/T 3503— 2017

388

附录 F

Appendix F

(规范性附录)

(Normative Appendix)

交工技术文件仪表安装工程用表

Handover Technical Documentation — Instrumentation Installation

序号

S/N

名 称

Description

编 号

No.

页次

Page No.

F.1 仪表设备校验 确认表 Instrument Equipment Calibration Confirmation Form SH/T 3503- J601 389

F.2 节流装置检查记录 Throttle Device Inspection Record SH/T 3503- J602 390

F.3 仪表管道压力试验记录 Instrument Piping Pressure Test Record SH/T 3503- J603 391

F.4

仪表管道泄漏性 /真空度试验条件确认与试验记录

Instrument Piping Leak/Vacuum Test Condition Confirmation

and Test Record

SH/T 3503- J604 392

F.5

综合控制系统机柜 /仪表盘 /操作台安装检验记录

Integrated Control System Cabinet/Instrument

Panel/Operation Console Installation Inspection Record

SH/T 3503- J605 393

F.6

综合控制系统送电条件确认表

Integrated Control System Energization Condition

Confirmation Form

SH/T 3503- J606 394

F.7 综合控制系统基本功能检测记录 Integrated Control System Basic Function Test Record SH/T 3503- J607 395

F.8

报警 /联锁系统与可编程序控制系统调试记录

Alarm/Interlock System and Programmable Control System

Testing Record

SH/T 3503- J608 396

F.9 联校试验条件确认表 Integrated Calibration Test Condition Confirmation Form SH/T 3503- J609 397

F.10 联校调试记录 Integrated Calibration Record SH/T 3503- J610-1 398

F.11 联校调试记录(续) Integrated Calibration Record (Continued) SH/T 3503- J610-2 399







SH/T 3503— 2017

389



SH/T 3503— J601

仪表设备校验确认表

Instrument Equipment

Calibration Confirmation Form

工程名称:

Project Name:



单位工程名称:

Unit Name:

S/N Calibration Item Unit Q’ty Confirmation Result Confirmation Date Confirmed by

1 Transmitter/Converter Calibration

2 Control valve/Actuator/Switch Valve Calibration

3 Process Switch Calibration

4 Level Measuring Instrument Calibration

5 Local Indicator Calibration

6 Indicator/Recorder Calibration

7 Analyzer Calibration

8 Axial Displacement and Vibration Measuring Instrument Calibration

9 Safety Barrier/Distributor/Selector Calibration

10 Adjustor Calibration

11 Calculation Calibration

12 Integrator Calibration

13 Other Instrument Calibration









Note: Fill “Acceptable” or “Unacceptable” in the column of “Confirmation Result”.

Remarks:







Owner/Supervision Contractor General Contractor Construction Contractor

Discipline Engineer:







Date:

Discipline Engineer:







Date:

Quality Inspector:

Discipline Engineer:





Date:



SH/T 3503— 2017

390



SH/T 3503— J602

节流装置检查记录

Throttle Device Inspection

Record

工程名称:

Project Name:



单位工程名称:

Unit Name:

Description Item No. Measuring Medium

Throttling

Component

Diameter d, mm

Throttling

Component

Thickness δ, mm

Straight Pipe Length

Me

asu

rin

g

Tu

be

Ou

tle

t

Me

thod



Inspe

cti

o

n R

esul

t

Design Actual Design Actual Upstream Downstream

































Note: Fill “Acceptable” or “Unacceptable” in the column of “Straight Pipe Length”.



Owner/Supervision Contractor General Contractor Construction Contractor

Discipline Engineer:







Date:

Discipline Engineer:







Date:

Foreman:

Quality Inspector:

Discipline Engineer:



Date:

SH/T 3503— 2017

391



SH/T 3503— J603

仪表管道压力试验记录

Instrument Piping Pressure

Test Record

工程名称:

Project Name:



单位工程名称:

Unit Name:

Test Ambient Temperature ℃ Test Medium Temperature ℃

Item No. Piping Description Specification Material

Design

Pressure

MPa

Test

Pressure

MPa

Test

Medium Test Result Tester





































Note: Only data obtained under the same test ambient temperature and test medium temperature can be filled in.





Owner/Supervision Contractor General Contractor Construction Contractor

Discipline Engineer:







Date:

Discipline Engineer:







Date:

Foreman:

Quality Inspector:

Discipline Engineer:



Date:

SH/T 3503— 2017

392

SH/T 3503— J604

仪表管道泄漏性 /真空度

试验条件确认与试验记录

Instrument Piping Leak/Vacuum

Test Condition Confirmation

and Test Record

工程名称:

Project Name:



单位工程名称:

Unit Name:

Inspection Item and Requirement Inspection Result

Instrument piping shall be qualified by pressure test.

Instrument piping shall be connected to the tested process system.

Test Record

Item No.

Design

Pressure

MPa

Design

Temperature



Test

Ambient

Temperature



Leak Test Vacuum Test

Pressure

MPa Medium

Pressure

MPa Medium



























Conclusion:







Owner/Supervision Contractor General Contractor Construction Contractor

Discipline Engineer:







Date:

Discipline Engineer:







Date:

Foreman:

Quality Inspector:

Discipline Engineer:



Date:

SH/T 3503— 2017

393

SH/T 3503— J605

综合控制系统机柜 /仪表盘 /

操作台安装检验记录

Integrated Control System

Cabinet/Instrument Panel/ Operation

Console Installation Inspection Record

工程名称:

Project Name:



单位工程名称:

Unit Name:

Description Model Item No.

Inspection Item and Requirement Inspection Result

1 There shall be no appearance damage or deformation. The internal and external surface shall be free from peeling paint, rust or other defects.

2

The foundation structural steel shall be flat, straight and firm with exterior size compatible with

that of the cabinet, instrument panel and console, and properly prepared and coated for

protection against corrosion.



3 The position, nameplate, model, tag number, quantity, exterior size and opening size of the cabinet, panel and console shall meet the requirements of the design documents.

4

The model, specification, quantity and installation position of the internal components of the

instrument and integrated control system shall meet the requirements of the design documents,

and shall be free from damages, loosening, shedding or dampness.



5

The cabinet, panel and console in the integrated control system shall be installed in accordance

with the requirements of the design documents with verticality, levelness, inter-panel clearance,

top height difference and front flatness as required by the applicable specifications, and firmly

connected with the foundation structural steel with rust-proof bolts.



6

The model, specification and quantity of the inter-panel cable (including special cable)/optical

cable, as well as cable ends and wiring (including internal wiring) shall be correct, firm, neatly

arranged and in compliance with the requirements of the design documents and applicable

specifications. The labels shall be standardized with legible identifications. Intrinsic safety wire

and non-intrinsic safety wire shall be separately installed in different ducts.



7 The cabinet, panel, console, indoor underfloor space, cable trench and indoor cable duct shall be dry and free from dust or foreign matters. Cable outlets and inlets shall be closed.

8 The cable (wire) conduction and insulation resistance, as well as optical cable testing, shall meet the requirements of the applicable specifications.

9

The local instrument panel shall be installed in a dry and well-lit place convenient for operation

and maintenance, good in sealing and having explosion-proof performance in compliance with

the requirements of the design documents.



10 The power supply system shall meet the requirements of the design documents and specifications.

11 The working earthing system shall meet the requirements of the design documents and specifications.

12 The protective earthing system shall meet the requirements of the design documents and specifications.

13 The shielding earthing system shall meet the requirements of the design documents and specifications.

14 Technical documents attached to the delivery of panel shall be complete.

Conclusion:

Owner/Supervision Contractor General Contractor Construction Contractor

Discipline Engineer:







Date:

Discipline Engineer:







Date:

Foreman:

Quality Inspector:

Discipline Engineer:



Date:



SH/T 3503— 2017

394

SH/T 3503— J606

综合控制系统送电条件确认表

Integrated Control System

Energization Condition

Confirmation Form

工程名称:

Project Name:



单位工程名称:

Unit Name:

System Description System Model

Manufacturer

Inspection Item Confirmation Result Inspection Item Confirmation Result

Control Room

Released from Civil

to Installation

Cable

Air-conditioning

System Wiring

Ambient

Temperature System Installation

Ambient Humidity Earthing

Indoor Cleanliness Power Supply

Firefighting System Lighting













Note: Fill “Acceptable” or “Unacceptable” in the column of “Confirmation Result”.

Remarks:











Owner/Supervision

Contractor General Contractor Construction Contractor Manufacturer

Discipline Engineer:







Date:

Discipline Engineer:







Date:

Foreman:

Quality Inspector:

Discipline Engineer:



Date:

Site Representative:







Date:



SH/T 3503— 2017

395



SH/T 3503— J607

综合控制系统

基本功能检测记录

Integrated Control System Basic

Function Test Record

工程名称:

Project Name:



单位工程名称:

Unit Name:

Description Model

Manufacturer

System Basic Function Test Record

Item Judgment Test Result Tester Item Judgment Test Result Tester

Self

Diagnosis □

Communication

Function □

Program

Installation □

Alarming

Function □

Screen Test □ Redundancy Function □

Keyboard

Operation □

Recovery

Function □

Mouse

Operation □ Printing Function □

Touch

Screen

Operation

□ LED Indicator □

Pushbutton □ System Power Supply □

Test Basis

Others



Notes: 1. Put “√” in the column of “Judgment” to indicate there is such function. Put “×” in the column of “Judgment” to

indicate there is no such function.

2. Fill “Acceptable” or “Unacceptable” in the column of “Test Result”.

Owner/Supervision Contractor General Contractor

Construction Contractor/

Testing & Construction

Contractor/Testing Contractor

Discipline Engineer:







Date:

Discipline Engineer:







Date:

Foreman:

Quality Inspector:

Discipline Engineer:



Date:

SH/T 3503— 2017

396

SH/T 3503— J608

报警 /联锁系统与可编程序

控制系统调试记录

Alarm/Interlock System and

Programmable Control System

Testing Record

工程名称:

Project Name:



单位工程名称:

Unit Name:

Tester

No. Interlock/Loop No. Logic Diagram No. Confirmation Reset Calibration Result



































Notes: 1. Fill “Normal” or “Abnormal” in the column of “Confirmation” and “Reset”.

2. Fill “Acceptable” or “Unacceptable” in the column of “Calibration Result”.

Remarks:







Owner/Supervision Contractor General Contractor

Construction Contractor/Testing &

Construction Contractor/Testing

Contractor

Discipline Engineer:







Date:

Discipline Engineer:







Date:

Foreman:

Quality Inspector:

Discipline Engineer:



Date:

SH/T 3503— 2017

397



SH/T 3503— J609

联校试验条件确认表

Integrated Calibration Test

Condition Confirmation Form

工程名称:

Project Name:



单位工程名称:

Unit Name:

System

Description System Model

Confirmation Item Judgment Confirmation Result Confirmation Item Judgment Confirmation Result

Test plan □ Instrument Piping Pressure Test □

Tester □ Instrument Piping Leak Test □

Test Equipment □ Instrument Piping Vacuum Test □

Instrument Equipment

Installation □ Degreasing □

Isolated Instrument

Equipment Calibration □ Pickling □

Instrument & Electrical

Loop Check □ Earthing System □

Cable Laying and

Insulation Test □ Air Supply System □

Panel/Cabinet/Console

Installation □ Power Supply System □

Cable Tray Installation □ Control System Testing □



Notes: 1. Put “√” in the column of “Judgment” to indicate that there is such item. Put “×” in the column of “Judgment” to

indicate that there is no such item.

2. Fill “Acceptable” or “Unacceptable” in the column of “Confirmation Result”.

Remarks:

Owner/Supervision Contractor General Contractor Construction Contractor

Discipline Engineer:







Date:

Discipline Engineer:







Date:

Foreman:

Quality Inspector:

Discipline Engineer:



Date:

SH/T 3503— 2017

398



SH/T 3503— 2017

399



SH/T 3503— 2017

400

附 录 G

Appendix G

( 规范 性附录)

(Normative Appendix)

压力容器现场组焊安装工程用表

Handover Technical Documentation — Pressure Vessel Site Assembly Welding and Installation

序号

S/N

名 称

Description

编 号

No.

页次

Page No.

G.1 现场组装记录 Site Assembling Record SH/T 3503- J701 401

G.2 球壳板 /支柱到货检验报告 Shell Plate/Support Receiving Inspection Report SH/T 3503- J702 402

G.3

球形储罐预制件检查记录 赤道带 /温带板

Spherical Tank Prefabricated Item Inspection

Record— Equator/Temperate Zone Plate

SH/T 3503- J703 403

G.4

球形储罐预制件检查记录 极板 /极中板

Spherical Tank Prefabricated Item Inspection

Record— Crown/Central Crown Plate

SH/T 3503- J704 404

G.5

球形储罐预制件检查记录 支柱

Spherical Tank Prefabricated Item Inspection Record

Record— Support

SH/T 3503- J705 405

G.6 球形储罐组装尺寸检查记录 Spherical Tank Assembling Dimension Inspection Record SH/T 3503- J706 406

G.7

球形储罐组装尺寸检查记录(续)

Spherical Tank Assembling Dimension Inspection Record

(Continued)

SH/T 3503- J707 407

G.8 球形储罐支柱检查记录 Spherical Tank Support Inspection Record SH/T 3503- J708 408

G.9

球形储罐焊后几何尺寸检查记录

Spherical Tank Post-weld Geometric Dimension Inspection

Record

SH/T 3503- J709 409

G.10

封头 /过渡段组装尺寸检查记录

Head/Transition Section Assembling Dimension Inspection

Record

SH/T 3503- J710 410

G.11 设备 焊接施工记录 Equipment Welding Record SH/T 3503- J711-1 411

G.12 设备 焊接施工记录(续) Equipment Welding Record (Continued) SH/T 3503- J711-2 412

G.13 焊缝返修施工记录 Weld Repair Record SH/T 3503- J712 413





SH/T 3503— 2017

401



SH/T 3503— J701

现场组装记录

Site Assembling Record

工程名称:

Project Name:



单位工程名称:

Unit Name:

Description Item No. Product No.

Specification Assembling Method □Vertical □Horizontal

Check

Posi

tion



Outer

Perimeter

Deviation

mm

Shell Top

Levelness

Deviation

mm

Shell Section

Vertical

Deviation

mm

Difference

btw. Max. &

Min. Shell

Diameter

mm

Orientation

Deviation

mm

Root Gap

mm

Misalignment

mm

Angular

Deformation

mm

Al

low

abl

e

Va

lue

Actual

Al

low

abl

e

Val

ue



Act

ual

Val

ue



Al

low

abl

e

Val

ue



Actual

Value

Al

low

abl

e

Val

ue



Act

ual

Val

ue



Al

low

abl

e

Val

ue



Act

ual

Val

ue



Al

low

abl

e

Val

ue



Ma

x. A

ctu

al

Va

lue



Al

low

abl

e

Val

ue



Ma

x. A

ctu

al

Va

lue



Al

low

abl

e

Val

ue



Ma

x. A

ctu

al

Va

lue



Top



Bot

tom



0? 90?















Overall Dimension and Form/Position

Deviation, mm

Allowable

Value

Actual Value

0?/ 180? 90?/ 270?

Shell Straightness

Shell Perpendicularity

Shell Total Length (Height)

Conclusion:







Owner/Supervision Contractor General Contractor Construction Contractor

Discipline Engineer:







Date:

Discipline Engineer:







Date:

Foreman:

Quality Inspector:

Discipline Engineer:



Date:



SH/T 3503— 2017

402



SH/T 3503— J702

球壳板 /支柱到货检验报告

Shell Plate/Support Receiving

Inspection Report

工程名称:

Project Name:



单位工程名称:

Unit Name:

Equipment

Description

Equipment

Item No. Product No.

Nominal Capacity m3 Inner Diameter mm Thickness mm

Total Number of

Shell Plates

Total Number

of Supports Material

Inspection on Geometric Dimension of

Spherical Shell Plate

Inspected Number Qualified Number Qualified Rate, % Inspection Record No.

pcs pcs

Support

No. 1 2 3 4 5 6 7

Straightness Deviation, mm

Length, mm

No. 8 9 10 11 12 13 14

Straightness Deviation, mm

Length, mm

NDT Item Tested Number Test Result Evaluation Test Record No.

Shell Plate Perimeter UT pcs

Shell Plate Total Area UT pcs

Groove pcs

Shell Plate Thickness pcs Min. Thickness mm Max. Thickness mm

Conclusion:

Support straightness over full length, actual

value

Support length, actual value

Shell plate thickness, actual value

Shell plate perimeter UT

Shell plate total area UT

Visual inspection on groove



□Nonconforming □Conforming to specification requirements

□Nonconforming □Conforming to specification requirements

□Nonconforming □Conforming to specification requirements

□Nonconforming □Conforming to specification requirements

□Nonconforming □Conforming to specification requirements

□Nonconforming □Conforming to specification requirements

Owner/Supervision Contractor General Contractor Construction Contractor

Discipline Engineer:







Date:

Discipline Engineer:







Date:

Foreman:

Quality Inspector:

Discipline Engineer:



Date:

SH/T 3503— 2017

403

SH/T 3503— J703

球形储罐预制件检查记录

赤道带 /温带板

Spherical Tank Prefabricated

Item Inspection Record —

Equator/Temperature Zone Plate

工程名称:

Project Name:



单位工程名称:

Unit Name:

Description Item No. Product No.

Nominal

Capacity m

3 Inner

Diameter mm Thickness mm

Applicable

Criteria

Inspection

Quantity pcs

Inspection

Percentage %

Item Unit Allowable Deviation Design Value Shell Plate Numbering and Actual Value

Gap btw. Shell Plate and

Template, E mm ≤ 3

Root Face, A mm ±1.5

Groove Depth, t mm ±1.5

Groove Angle, α ° ±2.5

Chord Length

along Length

L1 mm ±2.5

L2 mm ±2.5

Chord Length

along Width

B3 mm ±2

B2 mm ±2

Diagonal

Chord Length

C1 mm ±3

C2 mm ±3

Diagonal Distance h mm 5

Equator

Zone

Plate

with

Support

Support’s

Straightness mm

Support’s axial

Displacement mm

Support’s Fracture

Circumference mm



Sketch Showing Locations of Check Points

Visual Inspection:

Conclusion:

Owner/Supervision Contractor General Contractor Construction Contractor

Discipline Engineer:







Date:

Discipline Engineer:







Date:

Foreman:

Quality Inspector:

Discipline Engineer:



Date:



SH/T 3503— 2017

404



SH/T 3503— J704

球形储罐预制件检查记录

极板 /极中板

Spherical Tank Prefabricated

Item Inspection Record

— Crown/Central Crown Plate

工程名称:

Project Name:



单位工程名称:

Unit Name:

Description Item No. Product No.

Nominal

Capacity m

3 Inner

Diameter mm Thickness mm

Applicable

Criteria

Inspection

Quantity pcs

Inspection

Percentage %

Item Unit Allowable Deviation Design Value Shell Plate Numbering and Actual Value

Gap btw. Shell Plate and

Template, E mm ≤ 3

Shell Curvature at Opening mm ≤ 3

Root Face, A mm ±1.5

Groove Depth, t mm ±1.5

Groove Angle, α ° ±2.5

Diameter, D mm ±2



Sketch Showing Locations of Check Points

Nozzle No.

Nozzle Position Deviation

mm

Nozzle Height Deviation, L

mm

Flange Levelness

mm/m

Allowable Value Actual Value Allowable

Value

Actual

Value

Allowable

Value

Actual

Value Radial Circum. Radial Circum.









Visual Inspection:

Conclusion:

Owner/Supervision Contractor General Contractor Construction Contractor

Discipline Engineer:







Date:

Discipline Engineer:







Date:

Foreman:

Quality Inspector:

Discipline Engineer:



Date:

SH/T 3503— 2017

405

SH/T 3503— J705

球形储罐预制件检查记录

支 柱

Spherical Tank Prefabricated Item

Inspection Record — Support

工程名称:

Project Name:



单位工程名称:

Unit Name:

Description Item No. Product No.

Nominal

Capacity m

3 Inner

Diameter mm Thickness mm

Applicable

Criteria

Inspection

Quantity pcs

Inspection

Percentage %

Suppor

t N

o.

Straightness over Full

Length, e

mm

Length, H

mm

Perpendicularity

btw. Support and

Base Plate

mm

Sectional Support

Fracture

Circumference

mm Remarks

Allowable

Deviation

Actual Value Allowable

Deviation

Actual

Value

Allowable

Deviation

Actual

Value

Upper

Section

Lower

Section Radial Circum.



















Sketch Showing Locations of Check Points

Visual Inspection:

Conclusion:

Owner/Supervision Contractor General Contractor Construction Contractor

Discipline Engineer:







Date:

Discipline Engineer:







Date:

Foreman:

Quality Inspector:

Discipline Engineer:



Date:





SH/T 3503— 2017

406

SH/T 3503— J706

球形储罐组装尺寸检查记录

Spherical Tank Assembling

Dimension Inspection Record

工程名称:

Project Name:



单位工程名称:

Unit Name:

Equipment

Description

Equipment Item

No. Product No.

Nominal

Capacity m

3 Inner Diameter mm Thickness mm

Template Inner Radius RTemplate mm Template Chord Length L mm

Inspection

Item

Allowable

Value

mm

Weld No. and Actual Value, mm



Joi

nt G

ap



M

a

b

c

Mi

sal

ignm ent n

a

b

c

As

sem

bli

n

g A

ng

ula

rity



E

a

b

c



Sketch Showing Locations of Check Points

Conclusion:





Owner/Supervision Contractor General Contractor Construction Contractor

Discipline Engineer:







Date:

Discipline Engineer:







Date:

Foreman:

Quality Inspector:

Discipline Engineer:



Date:

SH/T 3503— 2017

407

SH/T 3503— J707

球形储罐组装尺寸检查记录 (续)

Spherical Tank Assembling Dimension

Inspection Record (Continued)

工程名称:

Project Name:



单位工程名称:

Unit Name:

Description Item No. Product No.

Nominal

Capacity m

3 Inner Diameter mm Thickness mm



Sketch Showing Locations

of Check Points

Inspection Item

Allowable

Value

mm

Actual

Value

mm

Difference between maximum inner diameter of equatorial

section and design inner diameter

Difference between minimum inner diameter of equatorial

section and design inner diameter

Difference between inner diameter between top crown and

bottom crown and design inner diameter

Difference between maximum and minimum inner

diameter of equatorial section

Difference between maximum inner diameter of equatorial

section and inner diameter between top crown and bottom crown

Difference between minimum inner diameter of equatorial

section and inner diameter between top crown and bottom crown

Equatorial line levelness

Minimum distance between support weld and butt weld

Minimum distance between two adjacent butt welds

Item Nozzle No.

Nozzle

Levelness

ΔH, mm

Allowable

Value

Actual

Value

Nozzle Position

mm

Allowable

Value

Actual

Value

Conclusion:





Owner/Supervision Contractor General Contractor Construction Contractor

Discipline Engineer:







Date:

Discipline Engineer:







Date:

Foreman:

Quality Inspector:

Discipline Engineer:



Date:

SH/T 3503— 2017

408

SH/T 3503— J708

球形储罐 支柱检查记录

Spherical Tank Support

Inspection Record

工程名称:

Project Name:



单位工程名称:

Unit Name:

Description Item No. Product No.

Nominal

Capacity m

3 Inner Diameter mm Thickness mm

Inspection

Timing

Suppor

t N

o. Straightness over Full Length

mm

Perpendicularity

mm

Allowable

Deviation

Actual Value Allowable

Deviation

Actual Value-Radial Actual Value-Circumferential

Radial Circum. a1 a2 a1- a2 a1 a2 a1- a2

1

2

3

4

5

6

7

8

9

10

Conclusion:



Sketch Showing Locations of Check Points

Owner/Supervision Contractor General Contractor Construction Contractor

Discipline Engineer:







Date:

Discipline Engineer:







Date:

Foreman:

Quality Inspector:

Discipline Engineer:



Date:



SH/T 3503— 2017

409



SH/T 3503— J709

球形储罐焊后几何尺寸检查记录

Spherical Tank Post-weld Geometric

Dimension Inspection Record

工程名称:

Project Name:



单位工程名称:

Unit Name:

Description Item No. Product No.

Nominal

Capacity m

3 Inner

Diameter mm Thickness mm

Inspection Item

Inspection Result

Allowable

Value

mm

Total Number

of Check

Points

Qualified

Number of

Check Points

Qualified

Rate

%

Max. Actual

Deviation

mm

Weld Width

Deviation

Inside Weld

Outside Weld

Weld

Reinforcement

Deviation

Inside Weld

Outside Weld

Weld Angularity

Fillet Weld Leg Height

Max. Inner Diameter of Equatorial

Section

Min. Inner Diameter of Equatorial

Section

Actual Inner Diameter between Top

and Bottom Crown

Difference between Max. Inner

Diameter and Min. Diameter

Difference between Max. Inner

Diameter and Design Inner Diameter

Difference between Min. Inner

Diameter and Design Inner Diameter

Conclusion:









Owner/Supervision Contractor General Contractor Construction Contractor

Discipline Engineer:







Date:

Discipline Engineer:







Date:

Foreman:

Quality Inspector:

Discipline Engineer:



Date:



SH/T 3503— 2017

410



SH/T 3503— J710

封头 /过渡段组装尺寸

检查记录

Head/Transition Section Assembling

Dimension Inspection Record

工程名称:

Project Name:



单位工程名称:

Unit Name:

Equipment

Description

Equipment

Item No. Product No.

Specification Material Applicable Criteria

Inspection Item

Allowable

Value

mm

Weld No. and Actual Value, mm



Joint Gap

M

a

b

c

Misalignment

n

a

b

c

Angularity

E

Template

Length L=

mm

a

b

c

Full Inspection on Specification of Head/Transition Section

Shape

Deviation

Inspection

with

Template

Larger Value Out-of-Ro

undness

Upper

End

Smaller Value Lower End



Sketch Showing Locations of Check Points

Conclusion:

Owner/Supervision Contractor General Contractor Construction Contractor

Discipline Engineer:







Date:

Discipline Engineer:







Date:

Foreman:

Quality Inspector:

Discipline Engineer:



Date:

SH/T 3503— 2017

411



SH/T 3503— 2017

412



SH/T 3

503



20

××



SH/T 3

503



20

××



SH/T 3503— 2017

413

SH/T 3503— J712 焊缝返修施工记录 Weld Repair Record

工程名称:

Project Name:

单位工程名称:

Unit Name:

Equipment

Description

Equipment

Item No. Product No.

Repair Position

Size

Repair Position

Material

Repair Welding

Process

Repair Welding Process

Parameter

S/N Repair Position Repair Film No. Defect Nature Repair Times Repair Size (L×W×D)mm PWHT Method Repair Date

Welder’s

Name/Stamp

No.

Repair

Result



























Remarks:



Owner/Supervision Contractor General Contractor Construction Contractor

Discipline Engineer:







Date:

Discipline Engineer:







Date:

Foreman:

Quality Inspector:

Discipline Engineer:



Date:



SH/T 3503— 2017

414

附录 H

Appendix H

(规范性附录)

(Normative Appendix)

交工技术文件起重机械安装工程用表

Handover Technical Documentation — Lifting Machinery Installation

序号

S/N

名 称

Description

编 号

No.

页次

Page No.

H.1 起重机轨道与车档安装检验记录 Crane Rail and Bumper Installation Inspection Record SH/T 3503- J801 415

H.2 手动单梁起重机安装检验记录 Hand Operated Single Beam Crane Installation Inspection Record SH/T 3503- J802 416

H.3 手动双梁起重机安装检验记录 Hand Operated Double Beam Crane Installation Inspection Record SH/T 3503- J803 417

H.4

手动单梁悬挂起重机安装检验记录

Hand Operated Single Beam Suspending Crane Installation

Inspection Record

SH/T 3503- J804 418

H.5 电动单梁起重机安装检验记录 Electric Single Beam Crane Installation Inspection Record SH/T 3503- J805 419

H.6 电动葫芦双梁起重机安装检验记录 Electric Hoist Double Beam Crane Installation Inspection Record SH/T 3503- J806 420

H.7

电动单梁悬挂起重机安装检验记录

Electric Single Beam Suspending Crane Installation Inspection

Record

SH/T 3503- J807 421

H.8 通用桥式起重机安装检验记录 General Purpose Overhead Crane Installation Inspection Record SH/T 3503- J808 422

H.9

双梁通用门式起重机和装卸桥安装检验记录

Double Girder General Purpose Gantry Crane and Transporter

Crane Installation Inspection Record

SH/T 3503- J809 423

H.10

单主梁门式起重机和装卸桥安装检验记录

Single Girder Gantry Crane and Transporter Crane Installation

Inspection Record

SH/T 3503- J810 424

H.11 臂上起重机和柱式悬臂起重机安装检验记 录 Jib Crane and Pillar Jib Crane Installation Inspection Record SH/T 3503- J811 425

H.12 起重机械负荷试验条件确认表 Lifting Machinery Load Test Condition Confirmation Form SH/T 3503- J812 426

H.13 起重机械空负荷试验记录 Lifting Machinery Empty load Test Record SH/T 3503- J813 427

H.14 起重机械负荷试验记录 Lifting Machinery Load Test Record SH/T 3503- J814 428



SH/T 3503— 2017

415

SH/T 3503— J801

起重机轨道与车 挡 安装检验记录

Crane Rail and Bumper

Installation Inspection Record

工程名称:

Project Name:



单位工程名称:

Unit Name:

Description Item No.

Specification & Model Lifting Capacity t Span m

Manufacturer Working Duty Lifting Height m

Control Mode Power Supply Working Environment

Rail Type Rail Length m Erection Position

Actually Measured Item Allowable Value mm Actual Value mm Conclusion

Positional Deviation of Actual Rail Centerline Relative to Actual

Crane Beam Centerline

Rail Span Deviation

Rail Top Longitudinal

Inclination

Every 2m

Full Length

Elevation Deviation of Rail Top Datum Point

Relative Elevation Difference btw. Two Parallel Rails in the Same Section

Bending of Rail in Horizontal Plane along Length Direction

Rail Joints

Height Difference

Lateral Misalignment

Clearance

Gap at Expansion Joints

Rail Lateral Inclination Deviation

Inspection Item Installation Requirement Inspection Result

Joint Position of Two Parallel Rails Joints shall be staggered at a distance larger than the wheel base of the crane.

Welded Joints of Rail Electrodes shall meet the relevant requirements. Top and side welds of joints shall be ground to a uniform and smooth finish.

Backing Plate at Joints of Rail The width of the backing plate (along the rail length direction) shall be twice of that at other parts.

Grouting for Concrete Crane Beam Grouting shall meet the design requirements.

Elastic Pad under Rail The specification and material of the pad shall meet the design requirements. Prior to tightening of bolts, the rail shall be in close contact with the elastic

pad.

Rail on Steel Crane Beam The rail shall be in close contact with the top of the crane beam. In case of any gaps, shim plates shall be installed as specified and properly welded.

Connecting Bolt Connecting bolts shall be free from damaged thread or loosening.

Bumper Bumpers on two rails in the same span end shall be in contact with the buffer of the crane.

Conclusion:

Owner/Supervision Contractor General Contractor Construction Contractor

Discipline Engineer:







Date:

Discipline Engineer:







Date:

Foreman:

Quality Inspector:

Discipline Engineer:



Date:

SH/T 3503— 2017

416



SH/T 3503— J802

手动单梁起重机安装检验记录

Hand Operated Single Beam Crane

Installation Inspection Record

工程名称:

Project Name:



单位工程名称:

Unit Name:

Description Item No.

Model Lifting Capacity t Span m

Manufacturer Working Duty Lifting Height m

Rail Length m Installation Position Working Environment



Sketch Showing Locations of Check Points

Unit: mm

Inspection Item Allowable Value Actual Value Conclusion

Crane Span, S

Relative Difference between Span S1 and S2,| S1- S2|

Relative Difference between Diagonal L1 and L2,| L1- L2|

Girder Camber, F

Remarks:





Conclusion:

Owner/Supervision Contractor General Contractor Construction Contractor

Discipline Engineer:







Date:

Discipline Engineer:







Date:

Foreman:

Quality Inspector:

Discipline Engineer:



Date:

SH/T 3503— 2017

417



SH/T 3503— J803

手动双梁起重机安装检验记录

Hand Operated Double Beam Crane

Installation Inspection Record

工程名称:

Project Name:



单位工程名称:

Unit Name:

Description Item No.

Specification &

Model

Lifting

Capacity t Span m

Manufacturer Working Duty Lifting Height m

Rail Length m Installation Position Working Environment



Sketch Showing Location of Check Points Unit: mm

Inspection Item Allowable Value Actual Value Conclusion

Crane Span, S

Relative Difference between Span S1 and S2,| S1- S2|

Girder Camber, F

Relative Difference between Diagonal L1 and L2,| L1- L2|

Trolley Rail Gauge, K

Relative Difference between Trolley Rail Gauge K 1 and K 2,| K1- K2|

Remarks:





Conclusion:





Owner/Supervision Contractor General Contractor Construction Contractor

Discipline Engineer:







Date:

Discipline Engineer:







Date:

Foreman:

Quality Inspector:

Discipline Engineer:



Date:



SH/T 3503— 2017

418



SH/T 3503— J804

手动单梁悬挂起重机安装

检验记录

Hand Operated Single Beam Suspending

Crane Installation Inspection Record

工程名称:

Project Name:



单位工程名称:

Unit Name:

Description Item No.

Specification &

Model Lifting Capacity t Span m

Manufacturer Working Duty Lifting Height m

Rail Length m Installation Position Working Environment



Sketch Showing Location of Check Points

Unit: mm

Inspection Item Allowable Value Actual Value Conclusion

Crane Span, S

Relative Difference between Span S1 and S2, | S1- S2|

Girder Camber, F

Relative Difference between Diagonal L1 and L2,| L1- L2|

Girder Side Deflection, f

Remarks:



Conclusion:





Owner/Supervision Contractor General Contractor Construction Contractor

Discipline Engineer:







Date:

Discipline Engineer:







Date:

Foreman:

Quality Inspector:

Discipline Engineer:



Date:

SH/T 3503— 2017

419



SH/T 3503— J805

电动单梁起重机安装检验记录

Electrical Single Beam Crane

Installation Inspection Record

工程名称:

Project Name:



单位工程名称:

Unit Name:

Description Item No.

Specification &

Model Lifting Capacity t Span m

Manufacturer Working Duty Lifting Height m

Rail Length m Installation Position Working Environment



Sketch Showing Locations of Check Points

Unit: mm

Inspection Item Allowable Value Actual Value Conclusion

Crane Span, S

Girder Camber, F

Relative Difference between Diagonal L1 and L2,| L1- L2|

Girder Side Deflection, f

Remarks:







Conclusion:





Owner/Supervision Contractor General Contractor Construction Contractor

Discipline Engineer:







Date:

Discipline Engineer:







Date:

Foreman:

Quality Inspector:

Discipline Engineer:



Date:



SH/T 3503— 2017

420

SH/T 3503— J806

电动葫芦双梁起重机安装

检验记录

Electric Hoist Double Beam Crane

Installation Inspection Record

工程名称:

Project Name:



单位工程名称:

Unit Name:

Description Item No.

Specification &

Model Lifting Capacity t Span m

Manufacturer Working Duty Lifting Height m

Rail Length m Installation Position Working Environment



Sketch Showing Locations of Check Points

Unit: mm

Inspection Item Allowable Value Actual Value Conclusion

Crane Span, S

Relative Difference between Span S1 and S2, | S1- S2|

Girder Camber, F

Relative Difference between Diagonal L1 and L2,| L1- L2|

Crane Wheel Horizontal Deflection, tgφ

Trolley Rail Gauge, K Span End Mid-span



Girder Side Deflection, f

Height Difference of Trolley Rails in the Same Section, c

Remarks:



Conclusion:





Owner/Supervision Contractor General Contractor Construction Contractor

Discipline Engineer:







Date:

Discipline Engineer:







Date:

Foreman:

Quality Inspector:

Discipline Engineer:



Date:

SH/T 3503— 2017

421



SH/T 3503— J807

电动单梁悬挂起重机安装

检验记录

Electric Single Beam Suspending

Crane Installation Inspection Record

工程名称:

Project Name:



单位工程名称:

Unit Name:

Description Item No.

Specification &

Model Lifting Capacity t Span m

Manufacturer Working Duty Lifting Height m

Control Mode Power Supply Working Environment

Rail Length m Installation Position



Sketch Showing Locations of Check Points Unit: mm

Inspection Item Allowable Value Actual Value Conclusion

Crane Span, S

Relative Difference between Span S1 and S2,| S1- S2|

Girder Camber, F

Girder Side Deflection, f

Clearance between Inner Side of Wheel Rim and Flange

of I Beam Rail, c

Remarks:





Conclusion:





Owner/Supervision Contractor General Contractor Construction Contractor

Discipline Engineer:







Date:

Discipline Engineer:







Date:

Foreman:

Quality Inspector:

Discipline Engineer:



Date:

SH/T 3503— 2017

422

SH/T 3503— J808

通用桥式起重机安装检验记录

General Purpose Overhead Crane

Installation Inspection Record

工程名称:

Project Name:



单位工程名称:

Unit Name:

Description Item No.

Specification &

Model Lifting Capacity t Span m

Manufacturer Working Duty Lifting Height m

Control Mode Power Supply Working Environment

Rail Length m Installation Position





Sketch Showing Locations of Check Points Unit: mm

Inspection Item Allowable Value Actual Value Conclusion

Girder Camber, F

Relative Difference btw. Diagonal L1 and L2,| L1- L2|

Trolley Rail Gauge, K Span End Mid-span

Height Difference of Trolley Rails in the Same Section, c

Girder Side Deflection, f

Crane Span, S

Relative Difference between Span S1 and S2, | S1- S2|

Crane Wheel Horizontal Deflection, tgφ

Misalignment of Wheels under the Same End Beam

Conclusion:

Owner/Supervision Contractor General Contractor Construction Contractor

Discipline Engineer:







Date:

Discipline Engineer:







Date:

Foreman:

Quality Inspector:

Discipline Engineer:



Date:



c

SH/T 3503— 2017

423

SH/T 3503— J809

双梁通用门式起重机和

装卸桥安装检验记录

Double Girder General Purpose

Gantry Crane and Transporter

Crane Installation Inspection Record

工程名称:

Project Name:



单位工程名称:

Unit Name:

Description Item No.

Specification &

Model Lifting Capacity t Span m

Manufacturer Working Duty Lifting Height m

Control Mode Power Supply Working Environment

Rail Length m Installation Position



Sketch Showing Locations of Check Points Unit: mm

Inspection Item Allowable Value Actual Value Conclusion

Crane Span, S

Relative Difference between Span S1 and S2,| S1- S2|

Girder Camber, F

Cantilever End Camber, F0

Relative Difference between Diagonal L1 and L2,| L1- L2|

Girder Side Deflection, f

Height Difference of Trolley Rails in the Same Section, c

Trolley Rail Gauge, K Span End Mid-span



Remarks:

Conclusion:

Owner/Supervision Contractor General Contractor Construction Contractor

Discipline Engineer:







Date:

Discipline Engineer:







Date:

Foreman:

Quality Inspector:

Discipline Engineer:



Date:



SH/T 3503— 2017

424

SH/T 3503— J810

单主梁门式起重机和

装卸桥安装检验记录

Single Girder Gantry Crane and Transporter

Crane Installation Inspection Record

工程名称:

Project Name:



单位工程名称:

Unit Name:

Description Item No.

Specification &

Model Lifting Capacity t Span m

Manufacturer Working Duty Lifting Height m

Control Mode Power Supply Working Environment

Rail Length m Installation Position



1- Articulating Device; 2- Hoisting Mechanism Frame; 3- Travelling Mechanism Trolley Frame; 4- Wheel Set

Sketch Showing Locations of Check Points Unit: mm

Inspection Item Allowable Value Actual Value Conclusion

Crane Span, S

Relative Difference between Span S1 and S2,| S1- S2|

Girder Camber, F

Cantilever End Camber, F0

Girder Side Deflection, f

Distance between

Center of Trolley

Wheel and Roller

Vertical Roller

Type Trolley

Horizontal Distance, K

Vertical Rail Gauge, K1

Horizontal Roller

Type Trolley

Hook Side, K2

Platform Side, K1

Degree of Symmetry L1 and L2 of Horizontal Guide Wheel

Axis to Main Wheel Center Distance

Conclusion:

Owner/Supervision Contractor General Contractor Construction Contractor

Discipline Engineer:







Date:

Discipline Engineer:







Date:

Foreman:

Quality Inspector:

Discipline Engineer:



Date:

SH/T 3503— 2017

425

SH/T 3503— J811

臂上起重机 和柱式悬臂

起重机安装检验记录

Jib Crane and Pillar Jib Crane

Installation Inspection Record

工程名称:

Project Name:



单位工程名称:

Unit Name:

Description Item No.

Specification &

Model Lifting Capacity t

Cantilever Length

L0 m

Manufacturer Working Duty Lifting Height m

Control Mode Installation Position Rail Length m



1—Upper Horizontal Wheel Rail; 1—Upper Horizontal Wheel; 2—Trolley;

2—Lower Horizontal Wheel Rail; 3—Lower Horizontal Wheel; 4—Main Wheel (Vertical Wheel)

3—Main Wheel Rail

Sketch Showing Locations of Check Points Unit: mm

Inspection Item Allowable Value Actual Value Conclusion

Crane Wheel Rail

Deviation of Actual Centerline Relative to

Actual Centerline of the Crane Beam

Longitudinal Inclination

Lower Horizontal

Wheel Rail

Distance between Top Surface and

Centerline of Crane Wheel Rail, a

Distance between Centerline and Top

Surface of Crane Wheel Rail, c

Distance between Centerline of Upper Horizontal Wheel Rail

and Top Surface of Crane Wheel Rail, h

Distance between Top Surface of Upper Horizontal Wheel

Rail and Lower Horizontal Wheel Rail, b

Crane Boom

Distance between the Upper Horizontal

Wheel and Lower Horizontal Wheel, H

Trolley Rail Gauge, K0

Cantilever End Camber, F0

Remarks:

Conclusion:

Owner/Supervision Contractor General Contractor Construction Contractor

Discipline Engineer:







Date:

Discipline Engineer:







Date:

Foreman:

Quality Inspector:

Discipline Engineer:



Date:

SH/T 3503— 2017

426



SH/T 3503— J812

起重机械负荷试 验条件确认表

Lifting Machinery Load Test

Condition Confirmation Form

工程名称:

Project Name:



单位工程名称:

Unit Name:

Description Item No. Product No.

Specification Lifting Capacity t Span m

Inspection Item Inspection Result

Owner/

Supervision

Contractor

General

Contractor

Construction

Contractor Date

1 Installation-related Information



2 Safety Distance

3 Metal Structure Connection

4 Crane Bridge Assembling Deviation

5 Span Deviation (Max.)

6 Trolley Rail Gauge Limit Deviation

7 Rail Joint Connection

8 Shortest Rail Length and Bumper

9 Fixing of Operator’s Cab

10 Max. Crane Rail Gauge Deviation

11 Rail Joint Gap

12 Deviation of Rail Center Relative to Beam Center

13 Rail Fixing

14 Hook Marks and Anti-releasing Device

15 Selection, Installation and End Fixing of Wire Rope

16 Safety Turns of Wire Rope

17 Adjustment of Brake

18 Connection and Fixing of Reducer

19 Oil Level of Reducer

20 Coupling Connection

21 Main Power Switch



22 Short-circuit Protection for Main Supply Circuit

23 Zero Potential Protection

24 Over-current Protection

25 Lighting

26 Signal

27 Electrical Equipment Grounding

28 Metal Structure Grounding

29 Manual Turning

30 Lubrication of Lubrication Points

31 Power Supply Sliding Contact Line Cable



SH/T 3503— 2017

427

SH/T 3503— J813

起重机械空负荷试验记录

Lifting Machinery Empty Load

Test Record

工程名称:

Project Name:



单位工程名称:

Unit Name:

Description Item No. Product No.

Specification Lifting Capacity t Span m

Applicable

Standard

Test Condition and Procedure Test Requirement Test Result Remarks

1

Operating direction of controls

and running direction of

mechanisms

Crane

Trolley

Hoisting Mechanism

2 Crane travelling and limit test (at least 5 times)

3 Trolley traversing and limit test (at least 5 times)

4 Hoisting mechanism operation and limit test (at least 5 times)

5 Number of turns of wire rope on the reel when the hook is lowered to the lowest position

6 Working condition of brake

Crane

Trolley

Hoisting Mechanism

7 Speed of conductor cable deploying and retrieving and speed of corresponding mechanism

8 Integrated operation of travelling mechanisms

9 Safety interlock test (at least 5 times)

10 Safety protection of trolley bar

11 Working condition of reducer

12 Working condition of coupling

13 Turning manually till the last shaft in the moving system completes one revolution

Conclusion:





Owner/Supervision Contractor General Contractor Construction Contractor

Discipline Engineer:







Date:

Discipline Engineer:







Date:

Foreman:

Quality Inspector:

Discipline Engineer:



Date:



SH/T 3503— 2017

428

SH/T 3503— J814

起重机械负 荷试验记录

Lifting Machinery Load Test

Record

工程名称:

Project Name:



单位工程名称:

Unit Name:

Description Item No. Product No.

Specification Lifting Capacity t Span m

Applicable Standard

Test Condition and Procedure Test Requirement Test Result Remarks

Stat

ic Load

Tes

t

1

Stop the crane at the column, move the trolley over the whole

travel, raise and lower the hook for at least 3 times respectively,

and check the operating conditions of the mechanism.

Normal

2

Stop the trolley at the mid-span of the crane, gradually load up to

the rated load for lifting operation, move the trolley to and from

over the whole travel, and check the structure of all parts. Normal

3

Stop the trolley at the mid-span of the crane, lift a load 1.25 times

of the rated load, suspend the load at a height 200mm from the ground

and hold for 10 minutes, then remove the load, move the trolley to

the end of the span, and check the metal structure of the bridge.

Normal

4

Raise and lower the hook for 3 times at a load 1.25 times of the

rated load, then remove the load, stop the trolley at the end of the

span, and check the camber of the bridge.

Larger than

0.7S/1000

5

Stop the trolley at the mid-span of the crane, lift and suspend the

rated load at a height 200mm from the ground, and measure the

camber of the bridge frame within S/10 from the middle of the span.

Site

Measurement

6 Check the static rigidity of the crane bridge (i.e. the difference between Item 5 and Item 4) S/700~S/1000

Dynam

ic

Loa

d T

est



1

Stop the crane at the column, move the trolley over the whole

travel, raise and lower the hook for at least 3 times respectively,

and check the operating conditions of the mechanism.

Normal

2

Stop the trolley at the mid-span of the crane, gradually load up for

lifting operation, move the trolley to and from over the whole travel

when the rated load is reached, and check the action of the mechanism. Normal

3

Stop the trolley in the mid-span of the crane, lift a load up to 1.1

times of the rated load, operate the crane over the whole travel,

and check the action of the mechanism. Normal

4 Raise and lower the hook for 3 times respectively under a load up to 1.1 times of the rated load, and check the action of the mechanism. Larger than 0.7S/1000

5 Test run all the mechanisms to check the safety interlock device. As per specification

Conclusion:

Owner/Supervision Contractor General Contractor Construction Contractor

Discipline Engineer:







Date:

Discipline Engineer:







Date:

Foreman:

Quality Inspector:

Discipline Engineer:



Date:



SH/T 3503— 2017

429



本标准用词说明



1 为便于在执行本规定条文时区别对待,对要求严格程度不同的用词说明如下:

1)表示很严格,非这样做不可的:

正面词采用“必须”,反面词采用“严禁”;

2)表示严格,在正常情况均应这样做的:

正面词采用“应”,反面词采用“不应”或“不得”;

3)表示允许稍有选择,在条件许可时首先应这样做的:

正面词采用“宜”,反面词采用“不宜”;

4)表示有选择,在一定条件下可以这样做的,采用“可”。

2 条文中指明应按其他有关 标准执行的写法为:“应符合……的规定”或“应按……执行”。



SH/T 3503— 2017

430

中华人民共和国石油化工行业标准





石油化工建设工程项目交工技术 文件规定



SH/T 3503— 2017



条文说明























2017 北 京

SH/T 3503— 2017

431



修订说明



《石油化工建设工程项目 交工技术文件规定 》 SH/T 3503— 2017,经工业和信息化部 2017年 7 月 7

日以第 32 号公告批准发布。

本标准是在《石油化工 建设工程项目 交工技术文件规定》( SH/T 3503— 2007)的基础上修订而成,

上一版的 主编单位是 北京燕山石化 工程质量监督站 和中 国 石化 集团 第四建设公司 ,主要起草人员是: 郭

建、汪庆华、吉章红、葛春玉、毕瑞凤、王玉兰、关慰清、袁庆水、吕铁英、石凤田、赵阳、徐春然。

本标准修订过程中,编制组进行了广泛、认真的调查研究, 总结了标准在实施过程中发现的问题 ,

在广泛征求意见的基础上,通过反复讨论、修改和完善,最后经审查定稿 。

为便于工程项目各参建单位有关人员在使用本规范 时能正确理解和执行条文规定,《石油 化工建设

工程项目 交工技术文件规定 》 编制组按章、条顺序编制了本规定的条文说明,对条文规定的目的、依据

以及执行中需注意的有关事项进行了说明。但是, 本条文说明不具备与标准正文同等的法律效力,仅供

使用者作为理解和把握规范规定的参考。

SH/T 3503— 2017

432



目次



正文使用说明 ·············································································································· 433

附录 A(规范性附录)交工技术文件通用表使用说明 ·························································· 435

附录 B(规范性附录)交工技术文件土建工程用表使用说明 ·················································· 437

附录 C(规范性附录)交工技术文件设备安装工程用表使用说明 ············································ 439

附录 D(规范性附录)交工技术文件管道安装工程用表使用说明 ··········································· 446

附录 E(规范性附录)交工技术文件电气安装工程用表使用说明 ············································ 447

附录 F(规范性附录)交工技术文件仪表安装工程用表使用说明 ············································ 448

附录 G(规范 性附录)交工技术文件压力容器现场组焊安装工程用表使用说明 ························· 449

附录 H(规范性附录)交工技术文件 起重机械 安装工程用表使用说明 ····································· 450





SH/T 3503— 2017

433

石油化工建设工程项目交工技术文件规定

本次修订中监理单位交工技术文件执行相应的监理规范,本规范不再要求。

本次修订正文中要求施工图审查记录,本规范中未约定具体格式,相关单位自行确定。

本次修订各参建单位公章改为项目章,如小项目无项目章加盖单位公章。

6.1 交工技术文件的编制

6.1.1 工程项目开工前,建设单位应组织监理、施工等单位划定工程项目的单项工程、单位( 子单位)、

分部工程和分项工程,为参建单位编制交工技术文件提供依据。

6.1.2 工程项目开工前,参建单位应根据项目具体情况和相关指导性文件编写交工技术文件编制方案,

报建设 /监理单位审批后实施,以规范交工技术文件的编制。

6.1.4 此条规定的“责任人应用符合档案要求的书写工具签字确认”,是指交工技术文件涉及责任人(设

计、施工、监理、建设等单位)签字,以及第三方签署的结论性意见,应采用碳素墨水、蓝黑墨水等耐

久性强的书写材料进行签署确认,不可采用红色墨水、纯蓝墨水、圆珠笔、复写纸、铅笔等易褪色的书

写材料。是 GB/T 50328— 2014对归档文件的书写材料的质量要求。

另外, GB/T 50328— 2014还规定:工程文件的纸张应采用能长期保存的韧力大、耐久性强的纸张。

6.2 交工技术文件的整理

6.2.1 建设工程项目交工技术文件是建设工程项目档案的重要组成部分,属于科学技术档案管理范畴,

其整理应遵循科学技术档案的整理原则和方法。此条提到的编目、装订以及案卷封面、卷内目录、备考

表,是《科学技术档案案卷构成的一般要求》 GB/T 11822—2008 对科学技术档案案卷的构成要求。

6.2.2 此条所称的 交工技术文件的“整理单位”,一般是指交工技术文件的编制单位。这符合 DA/T

28—2008 规定的“全部项目文件归档前由文件形成单位整理”的要求,也符合 GB/T 50328—2014 的相

关要求。

6.2.15 此条主要是指设备采购单位在整理动静设备出厂随机技术资料的要求:

—— 按单台或成套设备进行组卷;

—— 一个案卷内的文件装订方式,可根据文件成册实际情况灵活选择按卷装订或按件装订;

—— 一个案卷内的文件构成可简化,即案卷内容为:案卷封面、卷内目录、设备出厂技术资料、备

考表。可不填写交工技术文件封面、交工技 术文件说明。

6.2.18 此条规定了案卷编目内容及要求应符合 GB/T 11822—2008 规定。

a) 条明确了每卷交工技术文件的页号应采用打码机打印。

b) 条明确了按卷装订的交工技术文件页号的编制方法。所谓的按卷装订,就是将一个案卷内的所

有文件装订在一起。交工技术文件案卷一般采用按卷装订。

c) 条明确了按件装订的交工技术文件页号的编制方法。所谓的按件装订,就是将一个案卷的每份

(件)文件分别单独装订成册。这种方法一般用于一个案卷中的各份(件)文件已单独装订成册时。如

某设备厂家提供的某台设备出厂质量证 明文件、设备使用及维护说明书、图纸等文件已各自单独装订成

册,当将该台设备的随机技术资料组成一个案卷时,每份(件)文件可单独编写页号,已有页号的可不

再编写页号。不需要将其所有文件重新装订在一起再编写页号。

卷内目录的格式按 GB/T 11822—2008 进行,其中卷内目录可根据案卷装订方式、实际需要选择“页

数”或“页次”字段,以便于查阅利用。

SH/T 3503— 2017

434

6.3 交工技术文件的交付

—— 明确了交工技术文件的交付责任、交付时间、交付对象;

—— 明确了交工技术文件交付条件:交工技术文件应编制、整理完成后,经建设单位审查验收合 格

后才能办理移交;

—— 明确了交工技术文件正式交付时,交接双方应签署交工技术文件移交证书,办理移交手续。







SH/T 3503— 2017

435

附 录 A

(规范性附录)

交工技术文件通用表使用说明



A.1~ A.2 SH/T 3503- J101A、 B“ 封面 ” 为石油化工 建设工程项目 交工技术文件案卷 封面 。其中 “ 卷

号 ” 系根据档案管理规定编排的归档编号 。

SH/T 3503- J101A、 B 用作 综合 卷交工技术文件封面。实行工程总承包的工程项目填写表 J101B,

未实行工程总承包的工程项目填写表 J101A。

A.3 SH/T 3503- J102“ 交工技术文件总目录 ” 编列在交工技术文件 综合 卷 。 “ 文件 名称 ” 栏内应填写

各卷 名 ,表中页数系指各卷的总页数。

A.4 SH/T 3503- J103“ 交工技术文件目录 ” 为 卷 的交工技术文件目录。

A.5 SH/T 3503- J104“ 交工技术文件说明 ” 由交工技术文件编制单位填写。说明交工技术文件编制依

据、文件主要内容 与相关内容所在卷册 以及需要特别说明的事项。表中 “ 编制人 ” 为施工单位各专业技

术负责人, “ 审核人 ” 为施工单位 项目 总工程师。

A.6、 A.7 SH/T 3503- J105A、 B“工程施工 开工报告 ” 在 工程开工前由施工单位填写,交监理单位 审

查, 建设单位确认 后 签发,是考核合同工期的依据。实行工程总承包的工程项目填写表 J105B, 由施工

单位报总承包单位审核,并由总承包单位报送监理单位审查, 未实行工程总承包的工程项目填写表

J105A。

A.8、 A.9 SH/T 3503- J106A、 B“ 工程中间交接证书 ” 可作为单项工程的中间交接证书,也可作为

单元工程或 单位工程的中间交接证书。单项工程的 “工程中间 交 接 证书 ” 编入交工技术文件 综合 卷。表

中 “接 收意见 ” 栏由建设 单位 填写, “ 质量监督意见 ” 栏由工程质量监督站 或监督组 填写。 实行工程总

承包的工程项目填写表 J106B,未实行工程总承包的工程项目填写表 J106A。

A.10、 A.11 SH/T 3503- J107A、 B“ 工程交工 验收 证书 ”在 工程进行投料试车生产出合格产品,并经

过合同规定的性能考核期后签署。至此,施工承包单位完成合同规定的全部任务。实行工程总承包的工

程项目填写表 J107B,未实行工程总承包的工程项目填写表 J107A。

“ 工程接收意见 ” 栏由建设单位根据设计文件 、合同 规定的施工内容和试车情况阐明接收的意见;

“ 工程质量监督意见 ” 栏由工程质量监督站填写,内容为监督单位对工程质 量的结论评语。

A.12、 A.13 SH/T 3503- J108A、 B“ 交工技术文件移交证书 ” 为承包单位按合同规定日期向建设单

位办理交工技术文件移交时签署的文件。实行工程总承包的工程项目填写表 J108B,未实行工程总承包

的工程项目填写表 J108A。

A.14 SH/T 3503- J109“ 重大质量事故处理报告 ” 由事故责任方填写,表内各栏应简明扼要,并注明

相关附件名称,各相关单位代表均应签字。

A.15 SH/T 3503- J110“ 工程 设计 变更一览表 ”及相应 设计变更,编入各专业 工程卷、材料 /设备质

量 证明卷等 交工技术文件 的综合册 中,表中 “实施图号及 变更要点 ” 栏填写工程变更名称及简要内容。

A.16 SH/T 3503- J111“ 工程 联络 单一览表 ”和联络单 一起,编入各专业 工程卷、材料 /设备质量证明

卷等 交工技术文件 的综合册 中,表中 “联络 单编号 、 事由 、 实施情况 说明”逐一 填写简要内容。

A.17 SH/T 3503- J112“ 隐蔽工程 验收 记录 ” 为各专业的通用表格, 被后一工序覆盖的部位或被后续

作业覆盖的工序 均应填写隐蔽工程记录。 “ 检查结果 ” 栏由建设单位专业工程师或监理单位专业工程师

填写。

SH/T 3503— 2017

436

A.20 SH/T 3503- J115“ 合格焊工登记表 ” ,工程开始施焊前,施工单位填报参加该工程焊接的焊工 人

数 。 “ 合格项目代号 ” 栏应填写用于该工程焊接作业的合格项目代号。

A.21 SH/T 3503- J116“ 无损检测人员登记表 ” ,无损 检测 单位应在工程无损检测作业前填写此表, “ 合

格项目代号 ” 为用于该工程的无损检测项目代号。

A.22 SH/T 3503- J117“ 开箱检验 记 录 ” , 由采购单位填写, 实行总承包的工程项目填写 J116B,未实

行总承包的工程项目填写表 J116A。

A.23 SH/T 3503- J118“ 防腐工 程质量验收记录 ” 适用于设备、管道及钢结构等工程的内、外表面防

腐,同一防腐类型的设备、管道或钢结构等工程可填写在一张表格内。 “ 防腐前表面状态 ” 栏填写钢材

表面除锈等级; “ 防腐部位 ” 栏填写设备位号、管线号或钢结构编号; “ 防腐层结构及要求 ” 栏填写设计

文件规定的 结构形式及主要质量要求; “ 检查结果 ” 栏由施工单位质量检查员填写 “ 合格 ” 或 “ 不合格 ” ;

“ 验收结论 ” 栏由建设 /监理单位填写检查验收意见。

A.24 SH/T 3503- J119“ 隔热工程质量验收记录 ” 适用于设备、管道等工程的保温 或 保冷,同一隔热

结构类型的设备或管 道填写在同一张表格内。 “ 隔热部位 ” 栏填写设备位号或管线号; “ 隔热结构 ” 栏填

写设计 文件规定的 结构形式; “ 检查结果 ” 栏由施工单位质量检查员填写 “ 合格 ” 或 “ 不合格 ” ; “ 验收

结论 ” 栏由建设 /监理单位 专业工程师 填写。

A.27 SH/T 3503- J122“ 接地电阻测量 记 录 ” , “ 接地电阻测量 记 录 ” 栏由施工单位 测量人员 填写, “ 测

量结论 ” 栏由建设 /监理单位专业工程师填写。

A.28 SH/T 3503- J123“ 安全阀调整试验 记 录 ” ,由试验单位填写。调 整试验 时,启闭试验不得少于 3 次。

A.29 SH/T 3503- J124“ 安全附件安装检验记录 ” ,安全附件包括安全阀、爆破片装置、紧急切断装置等。

安全阀安装就位后,安全阀(爆破片装置)与压力容器之间的切断阀必须处于全开位置并加铅封锁

定, 并 将检验结果填入表中 “检查结果”栏 。

A.30~ A.35 SH/T 3503- J125~ J127“材料及配件超声检测报告”、“材料及配件磁粉检测报告”、“材

料及配件渗透检测报告”中的“ 缺陷情况或缺陷示意图编号 ” 栏存在缺陷时填写,对有缺陷示意图的要

填写示意图编号,对无缺陷示意图的要填写缺陷性质和大小。“质量证明文件编号”和“炉 /批号”栏 ,

存在时填写。

超声检测使用多种探头时,应编号并在报告中一一列出,通过探头序号与试块及检测部位相对应,

探头及其调试栏可视探头数量增减其行数。

磁粉 /渗透 检测报告中的“检测面”栏,填写内表面、外表面,对没有内表面的检件填写“表面”

以示区别。

A.36~ A.39 SH/T 3503- J128~ J130“ 超声测厚报告”、“金属材料化学成分检验报告”、“硬度检测报

告”,“检测(验)部位编号”栏所填写的内容要具有可追溯性,编号与被检测工件、检测部位要有关联

性并有唯一性 。 “验收标准”栏填写相应的产品标准(材料检测时) 或施工质量验收规范(施工过程检

测时)。对一个工件(部件)上检测多点时,要附图示意检测部位,管道设备上检测时可用轴测图、设

备图代替或在图上标示。

“金属材料化学成分检验报告” 中“ 质量证明文件编号 /炉批号 ” 栏优先填写炉批号,对无炉批号

的材料可填写质量证明文件编号,对检验管道上的焊口等类似部位时此栏空白。

A.45 SH/T 3503- J134 “工程影像记录表” 是各专业在隐蔽记录表中无法表述,为工程资料的可追溯

性设置。可以拍摄工程实体情况,也可以拍摄检查、验收人员和检查验收过程。

SH/T 3503— 2017

437

附 录 B

(规范性附 录)

交工技术文件土建工程用表使用说明

B.1 SH/T 3503- J201“ 地基验槽(坑)记录 ”。 构筑物均应进行施工验槽,检查内容包括基坑位置、

平面尺寸、持力层核查、基 底 绝对高程和相对标高、基坑土质及地下水位等,有桩支护或桩基的工程还

应填写桩的检查状况。地基验槽检查记录应由建设 /监理 、勘察、设计 和 施工单位共同验收签认 。“检验

结论”栏原则上应由勘察单位人员填写。 若勘察或设计等单位委托监理单位执行该工作, 应 有相关的书

面委托 文件 。地基验槽未通过,需要进行地基处理,应由勘察 单位人员提出 、设计单位出 具 处理意见 和

做 法 。另 ,本表格填报时应将 各方人员参检的影像资料附后作为支持 ( 文件 )。

B.2 SH/T 3503- J202“ 地基处理记录 ” 。 施工单位应依据勘察、设计单位出 具 的处理 意见或工程文件

进行地基处理,完工后填写 “ 地基处理记录 ” 报请勘察、设计单位复查,复查情况由勘察、设计在 “检

验结论” 一栏填写;若勘察或设计等单位委托监理单位执行该工作, 应由监理单位复查并签署意见 。地

基处理记录内容包括施工 日 期 、 地基处理依据 及 方式、处理部位 及状况、 处理结果 、检验结论 等,当地

基处理范围较大,内容较多,用文字描述较困难,应附简图示意。另 ,本 表格填报时应将 各方人员参检

的影像资料附后作为支持 ( 文件 )。

B.3 SH/T 3503- J203“ 工程定位测量记录 ” 是施工过程中形成的,确保建筑工程 方 位、尺寸、标高和

沉降量满足设计要求 及 规范规定的资料,属于 重要 的施工测量记录,其测量的准确性将直接影响工程施

工质量。

工程放线 大致分三个阶段,即:建构筑物定位(放线)、基础施工(放线)和主体施工(放线)。建

构筑物定位,是(建筑)工程项目开工后的第一次放线,建构筑物定位参加的人员是:规划部门或业主

所安排的专业测量单位或施工单位的专业的测量人员,根据设计总图或建构 筑图纸进行定位,最后在施

工现场形成定位桩。放线工具为“全站仪”或“比较高级的经纬仪和水准仪”;基础施工放线,建构筑

物定位桩设定后,由施工单位的专业测量人员、施工现场负责人及监理共同对基础工程进行放线及测量

复核(监理人员主要是旁站监督、验证),最后放出所有建构筑物轴线的定位桩,放线工具为“经纬仪

和水准仪”。本表主要用于该两个阶段使用。(主体施工放线,通常指建构筑物基础工程施工出正负零后

的测放线)。

B.4 SH/T 3503- J204 “ 设备基础复测记录 ” 中的测量数据为基础整体的定位数据,包括设计坐标和

标高 。 “ 复测结果确认 ” 栏由建设 /监理单位填写。

B.5~ B.8 设备基础中各部位具体定位数据的记录可根据设备基础形式的不同选用专门的表格填写,

包括 SH/T 3503- J205“ 块体式设备基础允许偏差项目复测记录 ” 、 SH/T 3503- J206“ 整体框架式设备

基础允许偏差项目复测记录 ” 、 SH/T 3503- J207“ 储罐基础允许偏差项目复测记录(一)、(二) ” 和 SH/T

3503- J208“球形储罐 基础允许偏差项目复测记录 ” 等。此类表格作为土建施工单位即 表中“施工 单位 ”

在设备基础施工完毕并符合质量要求后,交付安 装单位即 表中“ 接 收 单位 ” 的 用 表,表格中的 “ 复测结

果确认 ” 栏由建设 /监理单位填写并签认。

B.9 SH/T 3503- J209“ 基础沉降观测记录 ” 根据设计要求和规范规定,凡需进行沉降观测的工程,施

工期间可由施工单位专业测量人员 或 接受建设单位委托的专业测量单位承担沉降观测工作 ,其记录作为

正式交工技术文件归档 。

特殊需要时 , 测量人员应按照设计要求和规范规定或监理单位批准的观测方案,绘制沉降观测点布

置图,定期进行沉降观测 并填写 记录 。 专业测量单位应根据委托 最终出具沉降 观测点的沉降量 与 时间、

SH/T 3503— 2017

438

荷载关系曲线图 的 沉降观测报 告。

B.10 SH/T 3503- J210“ 水池蓄水试验记录 ” 是 水位 测针测定水位法 较精准测定水池渗漏状况所应填

写的表格,系 通过测定相关的数据 检验 水池的 工程 质量 。

B.11 SH/T 3503— J211“ 土建 隐蔽工程验收记录”是为满足建筑工程中大量隐蔽工程需要所设置的。

各有关方对隐蔽工程记录的签认既是施工期质量的认证,同时也是质量追溯性要求。 另 ,本表格填报时

应将 各方人员参检的影像资料附后作为支持 ( 文件 )。

B.12 SH/T 3503- J212“ 防水工程试水、蓄水通用检查记录 ” ,此表是防水工程和水池蓄 水试验

时采用观察法时应填写的通用性记录,检查内容包括方法、依据和蓄水时间等。 另 ,本表格填报时应将

各方人员参检的影像资料附后作为支持 ( 文件 )。





SH/T 3503— 2017

439

附录 C

(规范性附录)

交工技术文件设备安装工程用表使用说明

C.1 SH/T 3503- J301“ 机器安装检查记录”是用于各类型泵、通用离心风机、轴流风机等通用机械设

备,不适用于大中型离心压缩机、往复式压缩机、汽轮机和烟气轮机等机械设备。

表格中的每项实测数据多于一个数据时,应在备注栏中说明或用图示方式表明测量部位。

C.2 SH/T 3503- J302“ 轴对中记录 ”适用于双表(三表)法找单台设备或机组的轴对中记录。机器有

多个联轴器时,从驱动机侧联轴器开始顺序编号。采用“三表”找正时,两块轴向表的测量数值均记录

在轴向倾斜实测值内。表中“径向位移允许值”应为规范规定值或设备安装说明书中给出的规定值,“轴

向倾斜允许值”应为按规范规定值或设备安装说明书中给出的规定值在百分表回转直径处所计算出的数

据值,表格内“实测值”应为百分表的实际读数值。

C.3 SH/T 3503- J303“机组轴对中记录”适用于大型压缩机组单表法找对中时的记录。本表最多可供

4 个联轴器的机组 轴对中找正数据的填写。联轴器从驱动机侧开始顺序编号。表中允许值按规范或产品

技术文件要求填写,附实际轴对中测量曲线图。机器实际结构与本表格测点示意图不一致时,测点示意

图应根据机器实际结构绘制并编号。

C.4 SH/T 3503- J304“空冷式换热器风机安装检验记录”,“叶尖圆周水平高低差”,以一片叶片为基

准,测量各叶片尖端上部相对标高差。“风筒内壁与风扇叶尖间距”记录各叶片尖端部距风筒内壁距离

的最小值。“主、从动轴皮带轮中心面偏移量”采用拉线法在风机和电机皮带轮外端面处测量。

C.5 SH/T 3503- J305“ 机器组装质量确认记录”适用于现场组装的或经过拆检的机械设备。“ 机器内

部组装核查情况”和“主要缺陷及处理结果”由施工单位填写,“确认意见” 由建设 /监理单位、总承

包单位、设备制造厂专业工程师签署。

C.6 SH/T 3503- J306“ 往 复 式 压缩 机找平找正记录(卧式)” ,整体出厂的卧式压缩机,安装水平在机

身滑道面或其他基准面上测量。解体出厂的卧式压缩机,轴向水平在机身轴承空处测量,列向水平在滑

道的前、中、后三点测量,且均以两端数据为准,中间数据作为参考。气缸与中体滑道轴线同轴度找正

方法应根据制造厂 技术文件规定进行。机身轴向与列向水平、气缸列向水平倾向应符合设备出厂技术文

件规定。

C.7 SH/T 3503- J307“ 往 复 式 压缩 机找平找正记录(立式)” ,整体出厂的立式压缩机,安装水平应在

拆去气缸盖后的气缸顶平面上测量。解体出厂的立式压缩机安装水平应在机身与中体、机身与气缸、中

体与气缸接合面上测量。测量方法应符合规范规定。列向水平在滑道的前、中、后三点测量,且均以两

端数据为准,中间数据作为参考。气缸与中体滑道轴线同轴度找正方法应根据制造厂技术文件规定进行。

机身轴向与列向水平、气缸列向水平倾向应符合设备 出厂技术文件规定。

C.8 SH/T 3503- J308“ 往复式压缩机曲柄臂间距检查记录”,将曲柄销置于 0°、 90°、 180°、 270°四个

位置,分别测量相临曲柄臂间的距 离。

C.9 SH/T 3503- J309“ 往 复 式 压缩 机主轴轴线与中体滑道轴线垂直度检查记录”,本表用于拉丝法找

正,轴向窜量、 A、 B、 C、 D、 E、 F、 G、 H 的数值按图所示位置直接测量, “垂直度 ”通过上述测量数

据计算得出。采用其他方法检查时应在备注 栏内说明。

C.11、 C.12 SH/T 3503- J311“往复式压缩机十字头与中体滑 道间隙检查记录(卧式)”、 SH/T 3503

- J312“往复式压缩机十字头与中体滑道间隙检查记录(立式)”,应在全行程各个位置上测量,均应符

合机器技术文件规定,记录测点最小间隙数据。

SH/T 3503— 2017

440

C.13 SH/T 3503- J313“ 往 复 式压缩机连杆组装记 录”,当 连杆连接螺栓多于 2 条时,在备注中说明或

记录在下行位置。

C.14 SH/T 3503- J314“ 往 复 式压缩机汽缸余隙检查记 录”,用压铅丝法测量。

C.15 SH/T 3503- J315“ 往 复 式压缩机活塞与汽缸圆周间隙检查记 录”, 圆周间隙 用塞尺测量,卧式 压

缩机 上部间隙应比下部间隙 小 5%;立式压缩机应均匀分布,偏差不应大于平均间隙的一半 。

C.16 SH/T 3503- J316“ 往 复 式压缩机活塞环安装记 录”,工 作位置 C 值是活塞环在汽缸内的开口间

隙。当活塞环是铸铁材料时,需在安装前检查其倒角和圆角,并将 检查 结果写入备注中。

C.17 SH/T 3503- J317“ 往 复 式压缩机填料函各部间隙检查记 录”,根据设备实际情况在“填料型式”

栏内选项。

C.18 SH/T 3503- J318-1“ 机器单机试车记录”用于各类型泵、通用离心风机、轴流风机等通用机械

设备的 单机试车,根据要求选用振动速度或振动幅度之一。

C.19 SH/T 3503- J318-2“ 设备 单机试车记录”用于不适用于“ SH/T 3503- J318-1”表的通用

机械设备的单机试车。

C.20 SH/T 3503- J319“ 机组试车条件确认记录”适用于大中型离心压缩机、往复式压缩机、汽轮机

和烟气轮机等特殊结构的机械设备和成套机械设备的单机试车。

C.28 SH/T 3503- J323“ 电动机试车记录”适用于 200kW 及以上电动机驱动主机时,电动机运行情况

的记录。

C.31 SH/T 3503- J326“立式设备安装检验记录”适用钢制塔式容器整体就位检查。

C.32 SH/T 3503- J327“卧式设备安装检验记录”适用钢制卧式容器的整体就位检查,表格中“滑动

端鞍座滑动裕量”与“滑动端螺母松动核验结果”栏应在设备配管完成之后核查确认。

C.33 SH/T 3503- J328“塔盘安装检验记录”适用于塔盘、塔盘支撑件、溢流堰、降液板与受液盘及

其他项的检查验收,“其他”列根据不同的塔盘形式增加的特殊检查内容。本表涉及塔盘一次件与安装

件的检查验收,每层的检查内容参照各标准要求。其中:“ 塔盘编号”采用“ N-M”形式:表示为第 N

层塔盘,第 M 检查点,在检查表后附检查点布置图,对于一次件安装表格采用 SH/T 3503— J133 表。

C.34 SH/T 3503- J329“设备填充检验记录”适用于容器内填料的安装验收。

C.35 SH/T 3503- J330“反应 /沉降器附件安装检验记录”适用于 “ 集气室、提升管、待生催化剂立管、

旋风分离器、翼阀、喷嘴、吊杆、拉杆、挡板等的安装检查。

C.36 SH/T 3503- J331“再生器附件安装检验记录”适用于 “ 环形分布管、树状分布管、空气环、集

气室 、旋风分离器等的安装检查。

C.37、 C.42、 C.47 SH/T 3503- J332“立式圆筒形储罐组装质量检验记录”、 SH/T 3503- J334“湿式

气柜组装质量检验记录”、 SH/T 3503- J336“干式气柜组装质量检验记录”应有自检记录或安装记录

作为本表格的数据验收依据。

C.38、 C.39、 C.40、 C.41 SH/T 3503- J333-1“立式圆筒形储罐罐底真空试验记录”、 SH/T 3503- J333-2

“立式圆筒形储罐开孔补强圈气密性试验记录”、 SH/T 3503- J333-3“ 立式圆筒形储罐浮顶/船舱严密

性试验记录”、 SH/T 3503- J333-4“立式圆筒形储罐充水试验记录”按储罐制造工序进行试验,每项试

验内容附检查表。

C.43、 C.44、 C.45、 C.46 SH/T 3503- J335-1 “湿式气柜底板严密性试验记录”、 SH/T 3503- J335-2

“湿式气柜开孔补强圈气密性试验记录”、 SH/T 3503- J335-3 “湿式气柜水槽严密性试验记录”、 SH/T

3503- J335-4 “湿式气柜整体试验记录”检查同上。

C.48、 C.49、 C.50 SH/T 3503- J337-1 “干式气柜底板/活塞板/壁板严密性试验记录”、 SH/T 3503

- J337-2 “干式气柜开孔补强圈气密性试验记录”、 SH/T 3503- J337-3 “干式气柜总体试验记录”、

检查同上。

SH/T 3503— 2017

441

C.51 SH/T 3503- J338 “火炬塔架和管筒安装检验记录”适用于塔架、管筒及其整体的安装检查确认。

C.52 SH/T 3503- J339 “隔热耐磨衬里质量检验记录”是衬里施工的全过程检查表,要有各工序验收

记录或安装检查记录。

C.53 SH/T 3503- J340 “换热设备耐 压和严密性试验记录”适用于换热器的耐压及严密性试验。

C.54 SH/T 3503- J341 “设备耐压 /严密性试验记录”适用于设备的耐压及严密性试验。

C.55 SH/T 3503- J342 “设备热处理报告”,“热处理温度 -时间曲线”,按工艺要求参数和实际热处理

参数绘制成两条曲线,并给予标注。

C.56 SH/T 3503- J343 “管式炉炉体钢结构安装检验记录”适用于管式炉筒体、炉壁板、框架、立柱、

横梁等的检查验收。

C.58 SH/T 3503- J345 “管式炉附件安装质量检验记录”适用 于管式炉附件:燃烧器、作业门、防爆

门、看火孔、清理孔、吹灰器、风道、烟道等的整体验收。

C.59、 C.60、 C.61 SH/T 3503- J346 “耐火砖砌筑炉衬质量检验记录”、 SH/T 3503- J347 “耐火

浇注料炉衬质量检验记录”、 SH/T 3503- J348 “耐火纤维模块炉衬质量检验记录”适用于炉内衬里的

施工检查。

C.62 SH/T 3503- J349-1“设备及构件焊缝射线检测报告”,对不同的规格使用不同的射线源时,应按

照规格在报告中一一列出,通过规格将射线源、所使用的胶片、透照参数与 检测焊缝相对应。规格与透

照参数栏可视规格 /射线源的数量增减其行数。

C.64~ C.69 SH/T 3503- J350~ J352“设备及构件焊缝超声检测报告”、“设备及构件焊缝磁粉检测报

告”、“设备及构件焊缝渗透检测报告”,缺陷情况或缺陷示意图编号栏存在缺陷时填写,对有缺陷示意

图的要填写示意图编号,对无缺陷示意图的要填写缺陷性质和大小。

超声检测使用多种探头时,应编号并在报告中一一列出,通过探头序号与试块及检测焊缝相对应,

探头及其调试栏可视探头数量增减其行数。

磁粉 /渗透检测报告中的检测面栏,要明确是检测焊 缝的内表面还是外表面。

SH 3503—J113“ 垫铁隐蔽记录 ” 表格侧重垫铁施工验收的整体质量验收,对于每组垫铁的具体情

况,如:每组垫铁规格、数量、厚度等参数及检查情况不能体现,为规范垫铁施工过程,将每组垫铁参

数,汇总到 SH 3503- J133“ 垫铁 安装检查记录 ” 表格中,后附设备和钢结构垫铁施工记录和垫铁安装

检查记录示例。





SH/T 3503— 2017

442

示例一

SH/T 3503— J113 垫 铁 隐 蔽 记 录

工程名称: ×××××××



单位名称: ×××××××

设备 /结构名称 ××××××× 位号 ×××××××

垫铁布 置位置示意图:



每组垫铁的施工检查,填写 SH/T 3503— J133 垫铁 安装检查记录。

检查项目 安装要求 检查结果

找正 数据符合规范要求 □不符合□符合

垫铁规格 符合施工方案要求 □不符合□符合

垫铁布置位置 符合规范要求 □不符合□符合

每组垫铁块数 符合规范要求 □不符合□符合

每组垫铁高度 符合设计文件和规范要求 □不符合□符合

斜垫铁搭接长度 符合规范要求 □不符合□符合

垫铁间点焊固定 符合规范要求 □不符合□符合

结论:

经检查,□不符合□符合设计文件和规范要求,□不可以□可以隐蔽。

建设/监理单位 总承包单位 施工单位

专业工程师:









日期: 年 月 日

专业工程师:









日期: 年 月 日

施工班组长:

质量检查员:

专业工程师:





日期: 年 月 日



SH/T 3503— 2017

443



SH/T 3503— J133 垫铁 安装检查记录

工程名称: ××××××



单位工程名称: ××××××

专业工程 设备安装 施工图号 ××× -××× -×××

检查项目:







垫铁数量

块 材质 垫铁 总 高度

mm

平垫铁参数

接触

情况







厚度

mm

数量



厚度

mm

数量



厚度

mm

数量

块 斜垫铁 平垫铁

1 2 2 Q235-B 50 10 1 8 1 6 1 良好

2 2 2 42 8 2 良好























检验结论:用 0.25kg 手锤敲击检查合格。

建设/监理单位 总承包单位 施工单位

专业工程师:





日期: 年 月 日

专业工程师:





日期: 年 月 日

施工班组长:

质量检查员:

专业工程师:

日期: 年 月 日

SH/T 3503— 2017

444



SH/T 3503— J113 垫 铁 隐 蔽 记 录

工程名称: ×××××××





单位名称: ×××××××

设备 /结构名称 ××××××× 位号 ×××××××

垫铁布置位置示意图:



每组垫铁的施工检查,填写 SH/T 3503— J133 垫铁 安装检查记录。

检查项目 安装要求 检查结果

找正 数据符合规范要求 □不符合□符合

垫铁规格 符合施工方案要求 □不符合□符合

垫铁布置位置 符合规范要求 □不符合□符合

每组垫铁块数 符合规范要求 □不符合□符合

每组垫铁高度 符合设计文件和规范要求 □不符合□符合

斜垫铁搭接长度 符合规范要求 □不符合□符合

垫铁间点焊固定 符合规范要求 □不符合□符合

结论:

经检查,□不符合□符合设计文 件和规范要求,□不可以□可以隐蔽。

建设/监理单位 总承包单位 施工单位

专业工程师:





日期: 年 月 日

专业工程师:





日期: 年 月 日

施工班组长:

质量检查员:

专业工程师:

日期: 年 月 日

SH/T 3503— 2017

445



SH/T 3503— J133 垫铁 安装检查记录

工程名称:



单位工程名称:

专业工程 钢结构安装 施工图号 ××× -××× -×××

检查项目:



组号

垫铁数量

块 材









mm

平垫铁参数

接触

情况







厚度

mm

数量



厚度

mm

数量



厚度

mm

数量

块 斜垫铁 平垫铁

架 1-1-1 2 2 50 10 1 8 1 6 1 良好

架 1-1-2 2 2 42 8 2 良好























检验结论: 用 0.25kg 手锤敲击检查合格。

建设/监理单位 总承包单位 施工单位

专业工程师:





日期: 年 月 日

专业工程师:





日期: 年 月 日

施工班组长:

质量检查员:

专业工程师:

日期: 年 月 日

SH/T 3503— 2017

446

附 录 D

(规范性附录)

交工技术文件管道安装工程用表使用说明

D.1 SH/T 3503— J401“管道组成件验证性和补充性检验记录”用于相关规范中规定的对管道组成件进

行检验时所作的统计性记录,应按管道组成件名称分别填写。“检验项目”包括机械性能、无损检 测、

化学成分、几何尺寸,其中机械性能、无损检测、化学成分、几何尺寸等均有检验报告,此表只要求填

写每一类检验项的报告编号。

D.2 SH/T 3503— J402“阀门试验确认表”是按型号、规格试验的汇总表,按公称压力分类填写,“试

验项目”栏按下列说明填写:

—— “压力试验”为壳体压力试验;

—— “密封试验”为高压密封试验或低压密封试验;

—— “上密封试验”除采用波纹管密封的阀门外,进行试验的打“√”,未进行的打“×”。

—— “试验记录自编号”应按 SH/T 3543- G406的“自编号”填写,同规格、同型号、 同公称压力、

同试验项目的阀门可填写“自编号”范围。

D.3 SH/T 3503- J403“弹簧支 /吊架安装检验记录”中“安装冷态负荷值”指弹簧支 /吊架的制造厂按

照设计文件要求对弹簧支 /吊架出厂前的弹簧定位值。

D.4 SH/T 3503- J404“滑动 /固定管托安装检验记录”适用于设计温度超过 350℃管道和 低于 -29℃管

道 的滑动或固定管托的安装检验记录,其中“型式”指滑动管托或固定管托。

D.5 SH/T 3503- J405“管道补偿器安装检验记录”按表格中所列的项目记录波纹膨胀节、填料式补偿

器、球型 补偿器、膨胀弯管等补偿器的设计条件和预变形量。

D.6 SH/T 3503- J406-1“管道系统压力试验条件确认记录”,系管道系统压力试验前,建设 /监理单

位、施工单位应按记录中所列 12项内容进行检查,确认合格后方可进行系统耐压试验并记录。

D.8 SH/T 3503- J407“管道系统泄漏性 /真空试验条件确认与试验记录”系管道系统压力试验合格后,建设

/监理单位、施工承包单位应按记录中所列 5项内容进行检查,确认合格后方可进行系统泄漏性 /真空试验。

D.9 SH/T 3503- J408“管道吹扫 /清洗检 验记录”用于管道系统水冲洗、油冲洗、化学清洗、空气吹

扫、蒸汽吹扫。饮用水给水管道需进行消毒处理的,应将消毒处理结果记入“检验方法及结论”栏目内。

D.10 SH/T 3503- J409A“给排水压力流管道压力试验条件确认与试验记录”中的“压力流管道”为

工作压力大于或等于 0.1MPa 的给水和排水管道。

D.13 SH/T 3503- J410“给排水无压力管道闭水试验条件确认与试验记录”中的“无压力管道”为工

作压力小于 0.1MPa 的给水和排水管道。

D.16 SH/T 3503- J412-1“管道无损 检测结果汇总表”由检测单位负责填写,区号、 检测类别号、管

道编号、单线号、检测批号、焊工号、焊口号按照检测委托单填写,对接接头、角焊接头、支管连接接

头按照 SH3501进行分类,其焊口号参照 SH/T3558进行识别。检测报告编号上要能识别不同的检测方法。

所有检测过的焊口(包括因各种原因割除的焊口)均应在本表中体现,检测后割除焊口要在备注中说明。

除 RT、 UT、 MT、 PT外的检测方法结果单独汇总。

D.18 SH/T 3503- J413-1“管道无损检测数量统计表”由施工单位负责填写, 检测合格数量只填写检

测的最终 合格数,不合格的数量不要计算在内。对割除的焊口要包含在焊口总数内,并在备注中说明割

除数量(也是指合格的割除数量)。

检测方法代号可视实际情况进行增减。

SH/T 3503— 2017

447

附 录 E

(规范性附录)

交工技术文件电气安装工程用表使用说明

E.1 SH/T 3503- J501“变电所受电条件确认表”,是对变电所是否具备受电条件的检查确认,检查电

气设备的安装质量,一、二次设备的检试验记录,受送电方案及各项技术、安全措施等是否完成并得到

落实。签字栏中的“相关单位代表”,是除建设单位、监理单位和施工承包单位之外的其 他 相关单位人

员。

E.2 SH/T 3503- J502“盘、柜基础型钢安装质量验收记录”中的不直度、不平度、位置偏差及不平行

度实测偏差的测量点数根据现场实际情况填写,并附 基础型钢测点布置示意图 。

E.3 SH/T 3503- J503“电缆桥架安装检查记录”,按照单位工程的区域划分进行填写。

E.4 SH/T 3503- J504“电缆敷设及绝缘检测记录”的“绝缘电阻”栏应填写电缆与设备连接前测量的

绝缘电阻值。通常测量每相对其他相及地的绝缘电阻值,填写其中的最低值。

E.5 SH/T 3503- J505“电缆安装质 量验收记录”,按照单位工程的区域划分进行填写。

E.6 SH/T 3503- J506“交流电动机安装检验与空载运行记录”用于同步电动机和异步电动机,对于

1000V 及 100kW 以下的鼠笼电动机只填写此记录,不再填写交流电动机试验记录,故记录中列有“测

量定子绕组的绝缘电阻”栏,绝缘电阻应在电动机接线前测量,下列栏目按说明填写:

—— “轴承润滑脂(油)及填充量符合产品技术文件规定”栏,既不拆卸端盖也不更换润滑脂时,

此栏填写“-”;当拆卸端盖只更换润滑脂,而不进行电机抽芯检查时填写此栏,并写明润滑

脂牌号,但不再填 写电机抽芯检查记录;

—— “短路保护设备整定值”和“过载保护设备整定值”栏,在“检查结果”栏中填写设备名称

(如低压断路器、熔断器、热继电器、过流继电器)及整定值。如果是综保设备,可在备注

中加以说明;

—— “主回路绝缘电阻”、“控制回路绝缘电阻”系指空载运行前测量线路连同电动机或控制设备

的绝缘电阻值;

—— “定子电流”栏应填写空载运行时的三相电流值;

—— “轴承温度”栏应填写实测温度值,而非负荷端因有风扇罩无法测量时,填写“-”;

—— “振动测量值”栏应填写同步转速下的双倍振幅值或振速。

E.7 SH/T 3503- J507“变压器安装检验记录”用于电力变压器,也可用于变流、整流、电炉变压器。

E.8 SH/T 3503- J508“高 /低压开关柜安装检验记录”以组为单位,每组填写一个记录。一段开关柜

为一组,但有母联开关的两段开关柜也划为一组。

E.9 SH/T 3503- J509“保护 /控制盘(屏)安装检验记录”以组为单位,每组填写一个记录。保护和

控制盘、屏应分别填写,不能划为一组,而信号盘可与控制盘划为一组。

E.10 SH/T 3503- J510“直流系统 / UPS/EPS 安装检验记录”以系统为单位 ,每一系统填写一个记录。

E.11 SH/T 3503- J508“火灾自动报警系统安装检验记录”,填写此表时,每一报警控制器(盘)及其

控制范围内的探测器、报警按钮、控制设备及线路为一个系统,填写一个记录。



SH/T 3503— 2017

448

附 录 F

(规范性附录)

交工技术文件仪表安装工程用表使用说明

F.1 SH/T 3503- J601“仪表设备校验确认表”因仪表的调校记录作为过程控制文件,编入《石油化工

建设工程项目施工过程技术文件规定》 SH/T3543- 2017 中,该表是在联校之前,用于建设 /监理单位对

仪表设备施工过程单体 校验合格及数量的确认。

F.2 SH/T 3503- J602“节流装置检查记录”,应在节流装置安装前,对节流件直径、节流件厚度进行

实测记录,在节流件安装后,对直管长度和测量管引出方式进行实测记录。

F.3 SH/T 3503- J603“仪表管道压力试验记录”中的“管道名称”栏填写“测量管”、“伴热管”或“气

动管道”。

F.6 SH/T 3503- J606“综合控制系统送电条件确认表” 在对系统送电前,进行送电条件确认时填写 。

在各项目施工完成,达到送电条件的情况下,填写确认结果。

F.7 SH/T 3503- J607“综合控制系统基本功能检测记录”可以是进行检测的 制造厂、供应商、施工单

位 、调试单位、检测单位 ,据实填写;检测依据,可以是 制造 厂家 或供应 商提供的调试方案 。

F.8 SH/T 3503- J608“报警 /联锁系统与可编程序控制系统调试记录” 对确认、复位两项 应 在 调试 操

作后填写 。

F.9 SH/T 3503- J609“联校试验条件确认表”是在联校之前,对联校条件和仪表施工过程的确认,只

有该表确认合格后方可进行系统联校。

F.10、 F.11 SH/T 3503- J610-1“ 联校调试记录”、 SH/T 3503- J610-2“ 联校调试记录(续)”在联校

点较少时可以只用“联校调试记录”,联校点较多时,可以通过“联校调试记录(续)”予以扩充。联校

调试记录的总页数及当前页应标在“第页共页”栏中,只有 1 页时,填写为“第 1 页共 1 页”,备注及

相关人员签字填入“联校调试记录”中。

表格中栏目按下列说明填写:

—— “输入 /显示(指示、记录) /输出”栏目应填写变送器的输入值、 DCS的显示值(或二次仪表的指

示值、记录值)、调节阀的行程值;开关信号填写正常或不正常;

—— 调节器作用填写正作用或反作用;

—— 调节阀 确认后,在对应的 FC、 FO 栏填写正常或不正常。



SH/T 3503— 2017

449

附 录 G

(规范性附录)

交工技术文件压力容器现场组焊安装工程用表使用说明

本部分的表格应各方意见,将原 SH/T 3543 附录 G 压力容器现场组焊施工用表中压力容器 现场组装、

焊接及球罐安装用表提前至 SH/T 3503,作为项目交工资料:

G.1 SH/T 3503- J701“现场组装记录”适用于圆筒形设备现场组装口的检查, “测量部位”按设备排

板图的焊缝编号填写, 保证组对口周长、焊缝错边量、棱角度等的尺寸等符合要求; 纵焊缝不填写 “筒

体外周长偏差”、“ 筒体上口水平度偏差”、“分段筒体垂直度偏差”、“筒体最大与最小直径偏差”、“组对

方位偏差”;“筒体外周长偏差”为组对前测量,栏中“上口”为组对口下段筒体的上口外圆周长偏差值;

“下口”为组对口上段筒体的下口外圆周长偏差值。“筒体上口水平度偏差”在组对上段前测量。“ 分段

筒体垂直偏差 ” 分别在测量段组对前和焊接后测量。 “ 筒体最大与最小直径偏差 ” 在组对后距组对口

100mm 附近测量。 “ 方位偏差 ” 在筒体 0?方位线 处测量。 “ 对口间隙 ” 、 “ 对口错边量 ” 在组对后焊接前

测量; “ 角变形 ” 在焊接后测量。 “ 筒体直线度偏差 ”、“ 筒体总长 (高)度 偏差” 在筒体全部组对焊接完

成后测量, “ 筒体总垂直偏差 ” 在设备全部安装就位、找正完成后测量。

G.2 SH/T 3503- J702“球壳板 /支柱到货检验报告” 为汇总表,具体检测数据填写表 G. 3 即 SH/T 3503

- J703“球形储罐预制件检查记录赤道带 /温带板” 、 G.4 即 SH/T 3503- J704“球形储罐预制件检查记录

极板 /极中板”、 G.5 即 SH/T 3503- J705“球形储罐预制件检查记录支柱”三张表格, 表中“球壳板编号”、

“支柱编号”按出厂编号或按排版图自编号填写。球壳板厚度等需无损检测的 数据需根据无损检测报告

填写, 必要时附检测报告或检查记录。

G.6 SH/T 3503- J706“球形储罐组装尺寸检查记录”,侧重球罐现场组对焊缝的检查, 在 球形储罐组

装完成后焊接前检查, 包含组对间隙、组对错边量、组对棱角度符合标准要求, “ 焊缝编 号”按排板 图

中的 焊缝编 号填写。

G.7 SH/T 3503- J707“球形储罐组装尺寸检查记录(续)”,侧重球罐整体组装尺寸检查记录 “管口

编号”按设计图纸给定的管口编号填写,“ 实测值”为 抽 查实测 最大 值 ,支柱编号位置示意图中应根据

设备实际支柱数量、编号顺序在图上进行绘 制和标注。 不合格 项 需要在 结论栏 中做出描述或附 页说 明 。

G.8 SH/T 3503- J708“球形储罐支柱检查记录”,适用球罐支柱直线度和垂直度的检查,注意球支柱

的动态检控;测量时机的设置一般包括:球罐组装完成后(焊接前)、焊接过程监控及焊接完成后、热

处理过程监控及热处理完成后、全部施工完后等几个阶段。

G.9 SH/T 3503- J709“球形储罐焊后几何尺寸检查记录”,检查在球罐焊接施工完毕 水压试验前进行

测量。

G.10 SH/T 3503- J710“封头 /过渡段组装尺寸检查记录”适合于封头、过渡段 的组装尺寸检查。

G.11 SH/T 3503- J711-1“设备焊接工作记录”,对设备特别是压力容器的焊接过程中焊缝规格、焊接

方法、人员、焊接电流、电压、速度进行、热处理等进行记录。

G.13 SH/T 3503- J712“焊缝返修施工记录”,对焊缝的返修过程进行记录。



SH/T 3503— 2017

450

附 录 H

(规范性附录)

交工技术文件起重机械安装工程用表使用说明

H.1~ H.11 本附录所列入的 14 张表格 为 起重机安装用表,其中 SH/T 3503— J801“ 起重机轨道与车

挡 安装检查记录” ~ SH/T 3503— J811“ 臂上起重机和柱式 悬 臂 起重机安装 检查记录” 是 根据 GB50278

— 2010《 起重设备安装工程施工及验收规范 》的规定 编制。对起重机本体的各项检查应在起重机吊装前

和组装过程进行,起重机跨度两 侧 都 应测 量, 测 量方法 应 符合 GB50278— 2010《 起重设备安装工程施

工及验收规范 》附录 A 的要求。主梁上拱度最大值应处在主梁跨度中部 S/10 的范围内,测量方法应符

合 GB 50278- 2010《 起重设备安装工程施工及验收规 范 》附录 B 的要求,上拱度 F 为 S/1000。表中 测

量允许值应按设备安装说明书规定填写,无规定时,按 GB50278— 2010《 起重 设备 安装 工程 施工及 验

收规范 》 规定填写 ; 表格中的实测项目,当实测数据多于一个时,记录偏差 最大的数据,且在“备注”

中说明最大偏差的具体情况,必要时附图说明。

H.1 SH/T 3503— J801“ 起重机轨道与车 挡 安装检验记录”,“控制方式”填写“手动”或“电动”;“供

电方式”填写“直流”或“交流”;“工作环境”填写“室内”或“室外”。

H.2 SH/T 3503— J802“ 手 动单 梁起重机安装 检验记录” ,当有特殊要求时,应检查起重机跨度的相对差。

H.3 SH/T 3503— J803“ 手 动 双 梁起重机安装 检验记录” ,当有特殊要求时, 应检查对 角 线 的相 对 差 。

H.4 SH/T 3503— J804“ 手 动单 梁悬挂起重机安装 检验记录” ,当有特殊要求时, 应检查对 角 线 的相 对

差; 当 现场组 装主梁 时 , 应检查 主梁旁弯度 。

H.5 SH/T 3503— J805“ 电 动单 梁起重机安装 检验记录” , 当 现场组 装主梁 时 , 应检查 主梁旁弯度, f 为

S/2000。

H.6 SH/T 3503— J806“ 电 动葫芦双 梁起重机安装 检验记录” ,有特殊要求时,检查对角线相对差。大

车车轮水平偏斜,在同一端梁下两车轮的偏斜方向应相反。当现场组 装主梁时,应检查主梁旁弯度,并

应向两主梁外侧凸起。

H.7 SH/T 3503— J807“ 电 动单 梁悬挂起重机安装 检验记录” , 当 现场组 装主梁 时 , 应检查 主梁旁弯度 。

主梁 上拱度 F 为 S/1000。

H.8 SH/T 3503— J808“ 通用桥式 起重机安装 检验记录” , 当 现场组 装主梁 时 , 应检查 起重机跨度的相 对 差。

H.9 SH/T 3503— J809“ 双梁通用门式 起重机和装卸桥安装 检验记录” , 悬 臂端上 翘 度的 测 量方法 应 符

合 GB 50278— 2010《起重设备安装工程施工及验收规范》 附 录 B的要求 , 悬 臂端上 翘 度 F0为 L0/350。

当 现场组 装 桥 架 时 , 应检查对 角 线 相 对 差。 主梁旁弯度 应 向外 侧 凸起,并 应 在上翼 缘 板距离 100mm 的

腹板 处测 量 。

H.10 SH/T 3503— J810“ 单主梁门式 起重机和装卸桥安装 检验记录” , 悬 臂端上 翘 度 F0为 L0/350。 主

梁旁弯度 应 向外 侧 凸起,并 应 在上翼 缘 板距离 100mm 的腹板 处测 量 。

H.11 SH/T 3503— J811“ 臂上起重机和柱式 悬 臂 起重机安装 检验记录” ,适用于起重量为 0.5t~ 5t 的壁

上起重机和 1 t~ 5t 的柱式悬臂起重机。

H.12~ H.14 SH/T 3503— J812《起重 机械 负 荷 试验 条件确 认 表 》、 SH/T 3503— J813《起重机械空 负 荷

试验记录 》、 SH/T 3503— J814《起重机械 负 荷 试验记录 》,根据部分地区特 种设 备安全监督管理部门制

定的起重机械试验检查报告表格进行编制,用于施工、监理、建设单位对起重机械 试验结 果的 验 收确 认 。